# Civil Technology Grade 11 Exemplar November 2022 Memo (Eng)

> Grade 11 Civil Technology memorandum from the Exemplar November Exam 2022 (English), 16 pages. Read online or download the free PDF.

- Page: https://www.hlayiso.com/library/civ-tech-gr11-memo-nov2022-construction-english/e228481b-9c9c-4de7-816b-e609ecefefc7
- Updated: 2026-09-27
- Subject: Civil Technology
- Grade: Grade 11
- Language: English
- Document type: Memorandum
- Year: 2022
- Exam period: Exemplar November Exam
- Curriculum: CAPS
- Pages: 16

Breadcrumbs: [Home](https://www.hlayiso.com/) › [Library](https://www.hlayiso.com/library) › [Grade 11](https://www.hlayiso.com/library/grade-11) › [Civil Technology](https://www.hlayiso.com/library/grade-11/civil-technology) › [Civil Technology Grade 11 Exemplar November 2022 Memo (Eng)](https://www.hlayiso.com/library/civ-tech-gr11-memo-nov2022-construction-english/e228481b-9c9c-4de7-816b-e609ecefefc7)

## About this document

Civil Technology · Grade 11 · Exemplar November Exam · 2022 · English. Memorandum, 16 pages. Read online or download the PDF.

Read it free online on the page above; download the PDF from there.

## Document text

Text extracted from the PDF. Layout, diagrams and tables may not survive extraction.

### Page 1

Downloaded from hlayiso.com

                              NATIONAL
                         SENIOR CERTIFICATE

                                GRADE 11

                          NOVEMBER 2022

         CIVIL TECHNOLOGY: CONSTRUCTION
                 MARKING GUIDELINE
                    (EXEMPLAR)

MARKS:   200

         This marking guideline consist of 16 pages including 1 answer sheet.

### Page 2

Downloaded from hlayiso.com
2                         CIVIL TECHNOLOGY: CONSTRUCTION                       (EC/NOVEMBER 2022)

INSTRUCTIONS FOR THE MARKERS
1.    Markers should:
       • Familiarise themselves with the question and answer before evaluating the
         responses of candidates.
       • Always interpret the responses of the candidates within the context of the
         question.
       • Consider any relevant and acceptable answer during pre-marking but
         should strictly adhere to the answers after finalisation of the marking
         guideline.
       • There are two approaches to answering questions, these are (1) to
         describe and (2) to explain.
       • If a candidate is required to explain e.g., a process in 4 steps, only the first
         4 responses should be considered.
       • If, however a candidate is required to e.g., explain or describe how to
         transfer heights from one point to another using a transparent pipe level
         we need to consider that candidates may write a long description not
         necessarily well organised as an intellectual response may do. In this case
         the marker needs to evaluate the complete statement to judge if the
         candidate explained the required outcome satisfactorily and allocate
         marks on merit. The marker should apply his/her professional judgement
         with these types of questions.
       • Mark what the candidate wrote and do not award marks for answers that
         the marker thinks the candidate meant with what was written.
       • Indicate the tick or cross right at the position where the mark needs to be
         awarded or where the candidate made the error.
       • Accept the letter corresponding with the correct answer as well as the
         answer written in full in multiple-choice questions.
       • Accept incorrect spelling in one-word answers unless the spelling changes
         the meaning of the answer.
2.    For calculations:
       • A mark is only awarded if the correct unit is written next to the answer.
       • If TWO marks are awarded ONE mark is awarded for the answer and
         ONE mark for the correct unit.
       • Where the candidate made a principle error e.g. added instead of
         multiplying, no marks will be awarded for the steps. If the answer is correct
         according to what the candidate did, the mark for the answer can be
         awarded for the application of skills.
       • Where an incorrect answer could be carried over to the next step, the first
         answer will be deemed incorrect. However, should the incorrect answer be
         carried over correctly, the marker has to recalculate the values, using the
         incorrect answer from the first calculation. If correctly used, the candidate
         should receive the full marks for subsequent calculations.
       • Markers should consider when and where a candidate has rounded off in
         a calculation, as well as the subsequent effect it has on the final answer
         obtained. The calculation should therefore be awarded marks on merit.
       • Alternative methods of calculations must be considered, provided that the
         correct answer is obtained.

Copyright reserved                                                               Please turn over

### Page 3

Downloaded from hlayiso.com
(EC/NOVEMBER 2022)                CIVIL TECHNOLOGY: CONSTRUCTION                                 3

3.    When marking drawings:

       • The member for which the mark should be awarded should be drawn
         correctly in the correct position to receive a mark.
       • A member incorrectly drawn but wrongfully repeated in another position
         will be awarded the mark for the repeated incorrect member provided that
         the marking guideline provide for TWO or more marks for that member
         (positive marking).
       • Marks can only be awarded for a label if the label is correctly indicating the
         correct member.
       • Scale drawings should always be marked using an appropriate mask.

      When a candidate drew the wrong drawing e.g.:

       • A horizontal section instead of a vertical section, no marks will be
         allocated to the drawing as the candidate did not respond to the expected
         outcome.
       • An orthographic view instead of sectional view, no marks will be allocated
         to the drawing as the candidate did not respond to the expected outcome.
       • An orthographic view instead of an isometric view, no marks will be
         allocated to the drawing as the candidate did not respond to the expected
         outcome.
       • If the incorrect drawing was drawn, the candidate can be awarded for only
         what was asked but mark/s for the correctness of the drawing will not be
         awarded e.g., if a King Post roof truss was asked in the question, and
         candidate drew SA-Howe Truss.

Copyright reserved                                                            Please turn over

### Page 4

Downloaded from hlayiso.com
4                         CIVIL TECHNOLOGY: CONSTRUCTION                     (EC/NOVEMBER 2022)

QUESTION 1: SAFETY AND MATERIALS (GENERIC)

1.1   Gum boots                                                                            (1)

1.2   Under what circumstances will the following personal protective equipment be
      used?

      1.2.1 Safety glasses
            When working with a bench grinder, drills, electrical saws, etc. or any
            electrical equipment.                                                          (1)

      1.2.2 Earplugs
            When noise levels are high.                                                    (1)

1.3   Loose clothing can be pulled (1) into the machine by its moving parts (1).           (2)

1.4   Describe the safety precaution that is applicable with the following hand tools:

      1.4.1 Hammer heads
            Should fit snugly into the handle and be wedged in properly.                   (1)

      1.4.2 Sawing equipment
            Should be sharp and clean / Handles should be properly attached.               (1)

      1.4.3 When carrying chisels.
            Carry the blade facing downwards.                                              (1)

1.5   The petrol fumes can be harmful (1), when inhaled (1).
      (Similar answer.)                                                                    (2)

1.6   Any TWO requirements for the storing of cement:
      • Store on a pallet / planks / damp proof course or similar answer.
      • Store under cover / inside a building.
      • No contact with water.                                            (Any 2 x 1)      (2)

1.7   Any ONE similar answer:
      • Warning people against overhead work / dangers.
      • To show that the wearing of a hard hat is compulsory.                              (1)

1.8   Any FOUR requirements for storing hazardous material in the workplace:
      • The room must be well ventilated.
      • The door must have a threshold.
      • Material that may cause a spark must not be stored here.
      • Liquids that may interact chemically must be stored in close proximity.
      • Containers must always be sealed or properly closed.
      • Never store other flammable material with hazardous material. (Any 4 x 1)          (4)

Copyright reserved                                                              Please turn over

### Page 5

Downloaded from hlayiso.com
(EC/NOVEMBER 2022)                CIVIL TECHNOLOGY: CONSTRUCTION                                5

1.9    THREE ingredients to mix screed:
       • Cement (1)
       • Sand (1)
       • Water (1)                                                             (3 x 1)    (3)

1.10 Any THREE uses for screed:
     • Finish for floors and walls.
     • Facing material
     • Levelling layer for suspended floors.
     • Levelling layer for floor covering.
     • Infill to accommodate various levels.
     • Insulated roof screed.                                              (Any 3 x 1) (3)

1.11 •    Aggregate is too coarse.
     •    Aggregate too big for a mortar joint.
     •    Rough parts will give a weak finish.
     •    Similar answer.                                                 (Any 1 x 1)     (1)

1.12 Identify the type of board products that will be used for the following work:

       1.12.1    Backs of cupboards
                 Hard board or plywood.                                                   (1)

       1.12.2    Formwork for concrete
                 Shutter board                                                            (1)

1.13 Stock bricks:
     No attractive appearance / Must be plastered / Not good quality (1)

       Face bricks:
       Attractive appearance / Require no plaster / Good quality (1)                      (2)

1.14 Any TWO uses of cast iron:
     • Manhole covers
     • Sewerage pipes and fittings
     • Baths
     • Wash basins
     • Tools
     • Hinges
     • Similar answer                                                     (Any 2 x 1)     (2)
                                                                                         [30]

Copyright reserved                                                           Please turn over

### Page 6

Downloaded from hlayiso.com
6                           CIVIL TECHNOLOGY: CONSTRUCTION                   (EC/NOVEMBER 2022)

QUESTION 2: EQUIPMENT, TOOLS AND GRAPHICS (GENERIC)

2.1    Round shovel cannot shape the corners / square edges / straight lines (similar
       answer).                                                                       (1)

2.2    Any THREE hand tools that can be used to dress / cut bricks:
       • Comb hammer
       • Cold chisel
       • Bolster
       • Club hammer
       • Brick hammer                                                           (3 x 1)   (3)

2.3    2.3.1    Hand hawk                                                                 (1)

       2.3.2    Straight edge                                                             (1)

       2.3.3    External corner trowel                                                    (1)

       2.3.4    Nose trowel                                                               (1)

2.4    The rip saw is used for cutting with the grain of the wood. (1)
       The cross-cut saw is used for cutting across the grain of wood. (1)                (2)

2.5     2.5.1   Sliding bevel (1)                                                         (1)

                Any ONE use:
                • Drawing inclined / oblique lines.
                • Drawing angles other than 90⁰.
                • Copying angles to transfer them to other surfaces.         (Any1 x 1) (1)

        2.5.2   Bench grinder (1)                                                         (1)

                Any ONE use:
                • Sharpening tools
                • Grinding
                • Wire brush attachment can be installed.                    (Any 1 x 1) (1)

        2.5.3   Electrical drill (1).                                                     (1)

                Any ONE use:
                • Drilling holes.
                • Can be used as a screwdriver.
                • Sanding / buffing / cutting accessories attached to drill. (Any 1 x 1) (1)

2.6     2.6.1   Plate compactor                                                           (1)

        2.6.2   Any ONE use:
                • Compacting disturbed or loose soil up to 150 mm.
                • Tamping fillings for a hard-core layer under concrete floors.
                • Compacting soil before paving bricks are laid.
                • Similar answer.                                           (Any 1 x 1) (1)

Copyright reserved                                                             Please turn over

### Page 7

Downloaded from hlayiso.com
(EC/NOVEMBER 2022)                   CIVIL TECHNOLOGY: CONSTRUCTION                              7

2.7    See ANSWER SHEET 1.                                                                (13)

2.8    Part of the structure is enlarged (1) to include more information to the
       drawing (1)                                                                        (2)

2.9    Any THREE particulars of a site plan:
       • Boundaries of property
       • Building line
       • Erf numbers of plot and adjacent plots
       • Services and connections
       • Name of street
       • Driveway
       • Trees / boulders
       • Measurements
       • Existing buildings
       • Contours
       • North arrow
       • Scale                                                              (Any 3 x 1)   (3)

2.10 2.10.1          Water closet

                                                                                          (2)

       2.10.2        Hot-water cylinder

                      HW                                                                   (2)
                                                                                          [40]

Copyright reserved                                                            Please turn over

### Page 8

Downloaded from hlayiso.com
8                             CIVIL TECHNOLOGY: CONSTRUCTION    (EC/NOVEMBER 2022)

 QUESTION 3: QUANTITIES, JOINING AND GRAPHICS

 3.1    FIGURE 3.1 shows a foundation strip for a building.
        The foundation is 600 mm wide and 200 mm thick.
        A concrete mix of 1 : 4 : 4 is used.

                                               9 000

                     6 000

                                            FIGURE 3.1

        3.1.1    Determine the centre line of the foundation:
                 2 x 9 000 = 18 000
                 2 x 6 000 = 12 000
                             20 000
                 4 x 600     - 2 400
                             17 600 = 17,6 m                                 (5)

        3.1.2    Determine the volume of concrete needed:

                 17,6 x 0,6 x 0,2 = 2,112 m³

 3.2    A one brick wall of 1,2 m high and 12 m long.
        Determine the amount of bricks needed:                               (5)

        Area of wall:
           12
        x 1,2    =           14,4 m2

          14,4
          x 2
          x 50        =      1 440 bricks

Copyright reserved                                                Please turn over

### Page 9

Downloaded from hlayiso.com
(EC/NOVEMBER 2022)                   CIVIL TECHNOLOGY: CONSTRUCTION                              9

3.3     Apply a thin layer of PVC glue (1) to the fitting and the pipe. (1)
        Push the parts into position (1), while twisting. (1)                             (4)

3.4     3.4.1    True                                                                     (1)

        3.4.2    False                                                                    (1)

        3.4.3    False                                                                    (1)

        3.4.4    True                                                                     (1)

        3.4.5    True                                                                     (1)

3.5     Any TWO safety precautions when using epoxy:
        • Apply with care – cleaning excess/overruns is difficult once dry.
        • Be careful – the fumes may be toxic.
        • Join surfaces firmly together, before the compound dry          (Any 2 x 1) (2)

3.6

                                                                                          (2)

3.7     Bottom (1) right-hand corner (1) of the drawing page.                             (2)

3.8     3.8.1    Fluorescent light                                                        (1)

        3.8.2    Wall light                                                               (1)
                                                                                         [30]

Copyright reserved                                                            Please turn over

### Page 10

Downloaded from hlayiso.com
10                        CIVIL TECHNOLOGY: CONSTRUCTION              (EC/NOVEMBER 2022)

QUESTION 4: MATERIAL, EQUIPMENT AND JOINING (SPECIFIC)

4.1    4.1.1    Any ONE use of cellular bricks:
                • Brick/cavity walls
                • Foundations
                • Cellars
                • External walls
                • Similar answer                                                  (1)

       4.1.2    25%                                                               (1)

       4.1.3    Any TWO advantages of cavities in cellular bricks:
                • Reduce the amount of clay needed.
                • Ensure uniformly shaped bricks.
                • Help to resist shrinking.
                • Uniform density.
                • Improve insulating properties.
                • Allow bricks to dry more quickly.
                • Makes the brick lighter.
                • Reduce the weight of the building.
                • Easier to dry and fire the bricks.
                • Similar answer.                                    (Any 2 x 1) (2)

4.2    4.2.1    False                                                             (1)

       4.2.2    False                                                             (1)

       4.2.3    True                                                              (1)

4.3    4.3.1    Keyed brick

       4.3.2    Hollow concrete blocks

       4.3.3    Concrete paving bricks

4.4    Clay or shale (1) and limestone or chalk (1)                               (2)

4.5    4.5.1    15 MPa                                                            (1)

       4.5.2    30 MPa                                                            (1)

Copyright reserved                                                      Please turn over

### Page 11

Downloaded from hlayiso.com
(EC/NOVEMBER 2022)                   CIVIL TECHNOLOGY: CONSTRUCTION                     11

4.6    4.6.1    Independent scaffolding                                                (1)

       4.6.2    A – Guard rail (1)

                B – Kickboard (1)

                C – Horizontal transoms (1)

                D – Vertical standard (1)

                E – Baseplate (1)                                                      (5)

       4.6.3    Any ONE purpose of the kickboard:
                • Prevent material from falling off the scaffolding.
                • Prevent tools from falling off.
                • Prevent workers from slipping and injuries.
                • Similar answer.                                      (Any 1 x1)      (1)

4.7    4.7.1    Portable concrete vibrator                                             (1)

       4.7.2    Power float                                                            (1)

       4.7.3    Builders trestle                                                       (1)

4.8    Any TWO joining methods by using:
       • Metal straps
       • Fixing lug
       • Hoop iron ties
       • Nails                                                         (Any 2 x 1)     (2)

4.9    Any TWO types of wall ties:
       • Stainless steel
       • Butterfly pattern
       • Nylon wall tie
       • Twisted pattern
       • Double triangle pattern.                                      (Any 2 x 1)     (2)

4.10   Stainless steel or nylon or a rust-free / rustproof material.                   (1)

4.11   Join two brick rows / eaves with each other.                                   (1)
                                                                                     [30]

Copyright reserved                                                        Please turn over

### Page 12

Downloaded from hlayiso.com
12                        CIVIL TECHNOLOGY: CONSTRUCTION                    (EC/NOVEMBER 2022)

QUESTION 5: EXCAVATIONS, FOUNDATIONS AND STEEL (SPECIFIC)

5.1     5.1.1    A – Sighting line.                                                     (1)

                 B – Boning rod.                                                        (1)

                 C – Profile board / plank.                                             (1)

        5.1.2    150 mm                                                                 (1)

5.2     5.2.1    D (all heights are determined from this point)                         (1)

        5.2.2    F (cheaper material for formwork)                                      (1)

        5.2.3    E (remove 300 mm)                                                      (1)

        5.2.4    A (expensive material for formwork)                                    (1)

        5.2.5    B (most accurate way to test levelness).                               (1)

5.3     Any TWO methods of dewatering:
        • Pumping out water
        • Creating drains
        • Bailing of water / use buckets to scoop
        • Similar answer (mechanical or manually)                          (Any 2 x 1) (2)

5.4     Any THREE causes of trench accidents:
        • Excavated earth on the edge of the trench (sides can collapse).
        • Safety precautions for poor soil conditions.
        • Buildings, utilities, heavy traffic routes nearby and any source of vibration.
        • Previously disturbed ground.
        • Proximity of streams, old sewers and underground cables.
        • Availability of adequate equipment, protective gear, shoring materials and
          warning signs and lights.                                         (Any 3 x 1) (3)

5.5     5.5.1    Block foundation                                                        (1)

        5.5.2    Steel pipe with casing pile                                             (1)

        5.5.3    Wide strip foundation                                                   (1)

        5.5.4    Franki-pile                                                             (1)

        5.5.5    Short-bored pile (auger drill)                                          (1)

5.6     Step 1: Drill hole to correct depth (1)                                          (1)

        Step 2: Place reinforcing in position in the hole (1)                            (1)

        Step 3: Fill the hole with concrete (1)                                          (1)

Copyright reserved                                                            Please turn over

### Page 13

Downloaded from hlayiso.com
(EC/NOVEMBER 2022)                CIVIL TECHNOLOGY: CONSTRUCTION                           13

5.7    Any THREE advantages of piles:
       • Can be used in poor soil.
       • Can be used anywhere, even in water.
       • Larger base ensures stability.
       • Relatively quick and easy to install, if equipment is available.
       • If prefabricated piles are used, much time is saved.
       • Resists tensile stress well.
       • Quick and less expensive to produce.
       • Can be manufactured elsewhere beforehand.
       • Installation can continue, even in poor weather conditions.
       • Length of piles can easily be adjusted, depending on circumstances.
       • Offers sound resistance against moving soil.                     (Any 3 x 1)     (3)

5.8    I-beam: the web is longer than the flanges (1)                                     (1)

       H-beam: the web and the flanges are the same length (1)                            (1)

5.9    Angle iron                                                                         (1)

5.10   5.10.1    H-beam                                                                   (1)

       5.10.2    Angle iron                                                              (1)
                                                                                        [30]

Copyright reserved                                                           Please turn over

### Page 14

Downloaded from hlayiso.com
14                       CIVIL TECHNOLOGY: CONSTRUCTION                    (EC/NOVEMBER 2022)

QUESTION 6: FORMWORK, BRICKWORK, STAIRS AND QUANTITIES (SPECIFIC)

6.1    Formwork is a temporary mould / structure that contains poured concrete. (1)
       and supports until it has hardened and gained strength to support itself. (1)    (2)

6.2    Any THREE requirements of good formwork:
       • Sturdy enough to bear the mass of wet concrete without collapsing.
       • Strong enough to provide sufficient support, without deflection.
       • Easy to repair on site.
       • Erected accurately.
       • Sealed properly – no leaking and forming of honeycombing / fins.
       • Free of dirt (sawdust / release agents).
       • Quick and simple to erect (hand / mechanical).
       • Correct depth for reinforcing – prevent failure.
       • Easy to remove.
       • Close-fitting along joints and seams.
       • Made of recyclable components.                                   (Any 3 x 1)   (3)

6.3    6.3.1 Column                                                                     (1)

       6.3.2 A – Yoke                                                                   (1)

               B – Clamp                                                                (1)

               C – Shutter boards                                                       (1)

               D – Wedge                                                                (1)

6.4    Any TWO reasons for the cover depth of reinforcement in concrete:
       • To protect steel against corrosion / rust.
       • To provide adequate bonding between the steel and concrete.
       • To ensure adequate protection of steel in an event of fire.   (Any 2 x 1) (2)

6.5    6.5.1 True                                                                       (1)

       6.5.2 False                                                                      (1)

       6.5.3 True                                                                       (1)

       6.5.4 False                                                                      (1)

6.6    55 mm                                                                            (1)

6.7    No                                                                               (1)

6.8    Where maximum strength is required.                                              (1)

Copyright reserved                                                           Please turn over

### Page 15

Downloaded from hlayiso.com
(EC/NOVEMBER 2022)                 CIVIL TECHNOLOGY: CONSTRUCTION                        15

6.9    Any THREE places for DPC in a house:
       • Under / sides of concrete floors
       • In walls
       • At windows
       • At doors
       • In roofs
       • Similar answer.                                                 (Any 3 x 1) (3)

6.10 6.10.1 Gauged segmental arch                                                      (1)

       6.10.2 Stretcher bond                                                           (1)

       6.10.3 A – Extrados                                                             (1)

                B – Springer                                                           (1)

                C – Key brick.                                                         (1)

                D – Intrados                                                           (1)

6.11 6.11.1 Run                                                                        (1)

       6.11.2 Riser                                                                    (1)

6.12 6.12.1 Perimeter = side + side + side + side

                           = 2(2,3 m) + 2(1,5 m + 0,44 m)

                           = 4,6 m + 3, 88 m

                           = 8,48 m                                                    (3)

       6.12.2 Area = length x breadth

                      = (2,3 – 0,22 – 0,22) x 1, 5

                      = 1,86 m x 1,5 m

                      = 2,79 m²                                                        (3)

       6.12.3 Floor skirtings = 2(2,3 m – 0, 44 m) + 1,5 m + (1, 5 m – 0, 9 m)

                               = 3,72 m + 1,5 m + 0,6 m

                               = 5,82 m                                                 (4)
                                                                                       [40]

                                                                            TOTAL: 200

Copyright reserved                                                         Please turn over

### Page 16

Downloaded from hlayiso.com
16                      CIVIL TECHNOLOGY: CONSTRUCTION              (EC/NOVEMBER 2022)

                               CIVIL TECHNOLOGY
  ANSWER SHEET        1          CONSTRUCTION
                                                  NAME:

2.7    FIGURE 2.7 on ANSWER SHEET 1 shows the isometric view of a
       T-junction of a half brick wall in stretcher bond.
       Draw the front view of the brick wall on scale 1 : 10.                   (13)

                                  FIGURE 2.7

       T-junction                     4
       Brick sizes / Scale            3
       Height and length              2
       Stretcher bond                 2
       Line work / Neatness           2
                              TOTAL: 13

Copyright reserved                                                    Please turn over

## Related documents

- [CIV TECH GR11 QP NOV2022 Woodworking English](https://www.hlayiso.com/library/civ-tech-gr11-qp-nov2022-woodworking-english/a861fa2b-c73e-4904-b61c-4c353984f188) — Civil Technology · QP · 2022 · Eng
- [CIV TECH GR11 QP NOV2022 Civil Services English](https://www.hlayiso.com/library/civ-tech-gr11-qp-nov2022-civil-services-english/ed0b5808-e643-408f-bef2-165736e1c4b6) — Civil Technology · QP · 2022 · Eng
- [CIV TECH GR11 QP NOV2022 Construction English](https://www.hlayiso.com/library/civ-tech-gr11-qp-nov2022-construction-english/ef9cc9f6-54a4-49fb-a7b1-407a487eeec8) — Civil Technology · QP · 2022 · Eng
- [CIV TECH GR11 MEMO NOV2019 Wood English](https://www.hlayiso.com/library/civ-tech-gr11-memo-nov2019-wood-english/d9292b82-a65b-4b49-b85f-48201a66cec4) — Civil Technology · Memo · 2019 · Eng
- [Civil Technology PAT GR 11 2017 Eng](https://www.hlayiso.com/library/civil-technology-pat-gr-11-2017-eng/1f5dca71-f3a0-422d-a710-07cec778ad51) — Civil Technology · PAT · 2017 · Eng
- [CVLT GR11 MEMO (Revised) Afr Nov 2020 SIVIELE DIENSTE .docx](https://www.hlayiso.com/library/cvlt-gr11-memo-revised-afr-nov-2020-siviele-dienste-docx/a014afb0-d15f-4eaa-838f-0768b568dc8b) — Civil Technology · Memo · 2020 · Afr

## More from Grade 11 Civil Technology

- [Gr 11 Cons ATP 2023-24](https://www.hlayiso.com/library/gr-11-cons-atp-2023-24/5adb6254-7b36-487a-a882-c42b36bf49b7) — ATP
- [Gr 11 Civil Ser ATP 2023-24](https://www.hlayiso.com/library/gr-11-civil-ser-atp-2023-24/91ce1dc1-91cc-4a38-926b-b3d45f5b5305) — ATP
- [CVLT GR11 QP MEMO Nov2020 Civil Services ENG D](https://www.hlayiso.com/library/cvlt-gr11-qp-memo-nov2020-civil-services-eng-d/3f8bbf56-245d-44d0-924d-bd4e2a4b63e2) — Memo · 2020 · Eng
- [CVLT CONSTRUCTION GR11 QP MEMO NOV2020 AFR D](https://www.hlayiso.com/library/cvlt-construction-gr11-qp-memo-nov2020-afr-d/725f8d55-3826-49c5-8cfb-56f282e6e3a3) — Memo · 2020 · Afr
- [CVLT GR11 QP MEMO Nov2020 SIVIELE DIENSTE AFR D](https://www.hlayiso.com/library/cvlt-gr11-qp-memo-nov2020-siviele-dienste-afr-d/7c8b4398-3523-408c-bdf0-2998a85031f7) — Memo · 2020 · Afr
- [CVLT GR11 MEMO Nov2020 SIVIELE DIENSTE AFR D](https://www.hlayiso.com/library/cvlt-gr11-memo-nov2020-siviele-dienste-afr-d/da33973a-5831-474f-9ba4-c0dd58162697) — Memo · 2020 · Afr

## Collection

- [Grade 11 past papers](https://www.hlayiso.com/grade-11/past-papers)

---

Hlayiso: free CAPS and IEB past papers, memos, notes and study guides for South African learners. When citing, link the page URL above, not a PDF or /api/ URL.