# Civil Technology Grade 12 Eastern Cape Mock 2022 Memo (Eng)

> Grade 12 Civil Technology memorandum from the Eastern Cape Mock Exam 2022 (English), 18 pages. Read online or download the free PDF.

- Page: https://www.hlayiso.com/library/civ-tech-gr12-memo-sept2022-woodworking-english/62d9cbb1-1077-4edb-86c4-7a21fd6749a9
- Updated: 2026-09-27
- Subject: Civil Technology
- Grade: Grade 12
- Language: English
- Document type: Memorandum
- Year: 2022
- Exam period: Eastern Cape Mock Exam
- Curriculum: CAPS
- Pages: 18

Breadcrumbs: [Home](https://www.hlayiso.com/) › [Library](https://www.hlayiso.com/library) › [Grade 12](https://www.hlayiso.com/library/grade-12) › [Civil Technology](https://www.hlayiso.com/library/grade-12/civil-technology) › [Civil Technology Grade 12 Eastern Cape Mock 2022 Memo (Eng)](https://www.hlayiso.com/library/civ-tech-gr12-memo-sept2022-woodworking-english/62d9cbb1-1077-4edb-86c4-7a21fd6749a9)

## About this document

Civil Technology · Grade 12 · Eastern Cape Mock Exam · 2022 · English. Memorandum, 18 pages. Read online or download the PDF.

Read it free online on the page above; download the PDF from there.

## Document text

Text extracted from the PDF. Layout, diagrams and tables may not survive extraction.

### Page 1

NATIONAL
                         SENIOR CERTIFICATE

                                 GRADE 12

                          SEPTEMBER 2022

         CIVIL TECHNOLOGY: WOODWORKING
                 MARKING GUIDELINE

MARK:   200

         This marking guideline consists of 17 pages, including 9 answer sheets.

### Page 2

2                         CIVIL TECHNOLOGY: WOODWORKING                     (EC/SEPTEMBER 2022)

 INSTRUCTIONS FOR THE MARKERS

 1.   Markers should:

      • Familiarise themselves with the question and answer before evaluating the
        responses of candidates.
      • Always interpret the responses of the candidates within the context of the
        question.
      • Consider any relevant and acceptable answer during pre-marking but should
        strictly adhere to the answers after finalisation of the marking guideline.
      • There are two approaches to answering questions, these are (1) to describe and
        (2) to explain.
      • If a candidate is required to explain e.g., a process in 4 steps, only the first 4
        responses should be considered.
      • If, however a candidate is required to e.g., explain or describe how to transfer
        heights from one point to another using a transparent pipe level we need to
        consider that candidates may write a long description not necessarily well
        organised as an intellectual response may do. In this case the marker needs to
        evaluate the complete statement to judge if the candidate explained the required
        outcome satisfactorily and allocate marks on merit. The marker should apply
        his/her professional judgement with these types of questions.
      • Mark what the candidate wrote and do not award marks for answers that the
        marker thinks the candidate meant with what was written.
      • Indicate the tick or cross right at the position where the mark needs to be awarded
        or where the candidate made the error.
      • Accept the letter corresponding with the correct answer as well as the answer
        written in full in multiple-choice questions.
      • Accept incorrect spelling in one-word answers unless the spelling changes the
        meaning of the answer.

 2.   For calculations:

      • A mark is only awarded if the correct unit is written next to the answer.
      • If TWO marks are awarded ONE mark is awarded for the answer and ONE mark
        for the correct unit.
      • Where the candidate made a principle error e.g. added instead of multiplying, no
        marks will be awarded for the steps. If the answer is correct according to what the
        candidate did, the mark for the answer can be awarded for the application of skills.
      • Where an incorrect answer could be carried over to the next step, the first answer
        will be deemed incorrect. However, should the incorrect answer be carried over
        correctly, the marker has to recalculate the values, using the incorrect answer
        from the first calculation. If correctly used, the candidate should receive the full
        marks for subsequent calculations.
      • Markers should consider when and where a candidate has rounded off in a
        calculation, as well as the subsequent effect it has on the final answer obtained.
        The calculation should therefore be awarded marks on merit.
      • Alternative methods of calculations must be considered, provided that the correct
        answer is obtained.

Copyright reserved                                                             Please turn over

### Page 3

(EC/SEPTEMBER 2022)               CIVIL TECHNOLOGY: WOODWORKING                                  3

 3.   When marking drawings:

      • The member for which the mark should be awarded should be drawn correctly in
        the correct position to receive a mark.
      • A member incorrectly drawn but wrongfully repeated in another position will be
        awarded the mark for the repeated incorrect member provided that the marking
        guideline provide for TWO or more marks for that member (positive marking).
      • Marks can only be awarded for a label if the label is correctly indicating the correct
        member.
      • Scale drawings should always be marked using an appropriate mask.

      When a candidate drew the wrong drawing e.g.:

      • A horizontal section instead of a vertical section, no marks will be allocated to the
        drawing as the candidate did not respond to the expected outcome.
      • An orthographic view instead of sectional view, no marks will be allocated to the
        drawing as the candidate did not respond to the expected outcome.
      • An orthographic view instead of an isometric view, no marks will be allocated to
        the drawing as the candidate did not respond to the expected outcome.
      • If the incorrect drawing was drawn, the candidate can be awarded for only what
        was asked but mark/s for the correctness of the drawing will not be awarded e.g.,
        if a King Post roof truss was asked in the question, and candidate drew SA-Howe
        Truss.

Copyright reserved                                                              Please turn over

### Page 4

4                         CIVIL TECHNOLOGY: WOODWORKING                 (EC/SEPTEMBER 2022)

QUESTION 1: OHSA, SAFETY MATERIALS, TOOLS, EQUIPMENT AND
            JOINING (GENERIC)

1.1 It is an unplanned/uncontrolled (1) event that occurs because of an unsafe
    act/unsafe conditions. (1)                                                         (2)

1.2 Steel alloy pipe                                                                   (1)

1.3 1.3.1     Two                                                                      (1)

     1.3.2    38 mm                                                                    (1)

     1.3.3    900 mm                                                                   (1)

1.4 Any TWO:
    •   To ensure that the scaffolding is stable in all directions
    •   Must be able to carry the mass of the load
    •   Free of any defects
    •   Similar answer                                                (Any 2 x 1)      (2)

1.5 1,8 meters                                                                         (1)

1.6 3 meters                                                                           (1)

1.7 1.7.1     Any ONE:
              • Higher person can slip and fall on the lower person
              • Can damage the ladder
              • Makes it more unstable
              • Similar answer                                        (Any 1 x 1)      (1)

     1.7.2    Red or orange flag                                                       (1)

     1.7.3    Any ONE:
              • Aluminium
              • Wood
              • Metal
              • Similar answer                                        (Any 1 x 1)      (1)

     1.7.4    Any ONE:
              • Defects must be visible (clean)
              • Will prevent slipping accidents (oil / grease)
              • Similar answer                                        (Any 1 x 1)      (1)

1.8 Any TWO:
    • Can be applied with a brush, roller or spray-gun
    • Enhances appearance of surfaces
    • Easy to apply
    • Makes cleaning and maintenance easier
    • Dry quickly
    • Marks/smudges are easily cleaned with water
    • Gives elastic/flexible finish resistant to cracking             (Any 2 x 1)      (2)
Copyright reserved                                                         Please turn over

### Page 5

(EC/SEPTEMBER 2022)   CIVIL TECHNOLOGY: WOODWORKING                 5

Copyright reserved                                    Please turn over

### Page 6

6                         CIVIL TECHNOLOGY: WOODWORKING                    (EC/SEPTEMBER 2022)

1.9     Any TWO:
        • Increases the strength of concrete
        • Decreases the permeability of concrete
        • Improves the durability of concrete
        • Reduces cracks
        • Makes concrete more watertight
        • Reduce crimping cracks in the concrete
        • Provides volume stability
        • Concrete can carry more weight without being damaged            (Any 2 x 1)      (2)

1.10 Any TWO:
     • Painting
     • Electroplating
     • Powder coating
     • Galvanising                                                        (Any 2 x 1)      (2)
                                                                                          [20]
QUESTION 2: GRAPHICS, JOINING AND EQUIPMENT (GENERIC)

2.1    FIGURE 2.1 on ANSWER SHEET A shows the outer lines of a structure that
       must be built on a site. Draw the site plan on scale 1 : 200 on ANSWER
       SHEET A so that the structure is in the middle of the site.

       The site plan must comply with the following requirements:

       2.1.1    Plot size is 30 m wide from east to west and 40 m long from south to
                north                                                                      (2)

       2.1.2    Pavement of 2 m and the street of 6 m on the south side                    (3)

       2.1.3    Building boundaries are 2 m on the east, north and west sides and
                4 m on the south side                                                      (4)

       2.1.4    3 m wide entrance to the site                                              (2)

       2.1.5    Datum level in the north-west corner of the site                           (2)

       Also draw in the sewer lay-out on the structure and show the following:

       2.1.6    Water closet and symbol at the abbreviation                                (1)

       2.1.7    Sewer pipes                                                                (2)

       2.1.8    Rodding eye with the abbreviation                                          (2)

       2.1.9    Inspection eye with the abbreviation                                       (2)

       2.1.10 Manhole with the abbreviation                                                (2)

       Indicate the following measurements:

       2.1.11 Length and width of the site                                                 (4)

       2.1.12 South and west building boundaries                                           (2)

       Use the points table on ANSWER SHEET A as reference.
Copyright reserved                                                            Please turn over

### Page 7

(EC/SEPTEMBER 2022)               CIVIL TECHNOLOGY: WOODWORKING                         7

2.2    When square shoulder is driven in it resists rotation.                          (1)

2.3    A – Nut (1)
       B – Thread (1)
       C – Run-out (1)
       D – Shank (1)                                                      (4 x 1)      (4)

2.4    Prevents backing off.                                                           (1)

2.5    Can be tightened with fingers.                                                  (1)

2.6    2.6.1    1,61 m                                                                 (1)

       2.6.2    1,64 – 1,584 x 100 = 5,6 m                                            (4)
                                                                                     [40]

                                                                TOTAL SECTION A:       60

Copyright reserved                                                        Please turn over

### Page 8

8                             CIVIL TECHNOLOGY: WOODWORKING             (EC/SEPTEMBER 2022)

                                  CIVILCTECHNOLOGY     NAME:
    ANSWER SHEET              A        GENERIC

2.1 FIGURE 2.1 on ANSWER SHEET A shows the outer lines of a structure that must
    be built on a site. Draw the site plan on scale 1 : 200 on ANSWER SHEET A so
    that the structure is in the middle of the site.                             (28)

                                       30 m

                RE
                                  SK
              SO
40 m          m
              IO
        2m           IE

                                                              Site size              2
                                                              Pavement + street      3
                                                              Building boundaries    4
                                                              Entrance               2
                                                              Exit point             2
                                                              Water closet           1
                      MH
                      MG                                      Sewer connection       2
                      m                                       Inspection eye + abbr. 2
                                                              Rodding eye +abbr.     2
                                                              Manhole + abbr.        2
                      4 4mm                                   Measurements           6
                                                                            TOTAL: 28

Copyright reserved                                                         Please turn over

### Page 9

(EC/SEPTEMBER 2022)                    CIVIL TECHNOLOGY: WOODWORKING                            9

QUESTION 3:           CASEMENTS, CUPBOARDS, WALL-PANELLING AND
                      QUANTITIES (SPECIFIC)

3.1    3.1.1    16 mm ✓                                                                        (1)

       3.1.2    Skirting ✓                                                                     (1)

       3.1.3    7,5 m² ✓                                                                       (1)

       3.1.4    Mullion ✓                                                                      (1)
3.2    3.2.1    • Transom ✓
                • Bottom rail of fanlight ✓
                • Top rail of casement ✓                                                       (3)

       3.2.2    Drip groove/Throat ✓                                                           (1)

3.3    3.3.1      A        B            C      D
                                               Area of roof sheeting needed:

                                               Width of the roof = 150 mm + 8 000 mm +
                                               150 mm
                                               = 8 300 mm ✓

                ✓                              Length of sheet = x Length of rafter +
                                               overhang of roof sheeting
                2/      8,3 ✓                  = 2 900 mm + 50 mm = 2 950 mm ✓
                        2,95 ✓ 48,97 m2 ✓                                                      (6)

       3.3.2                                   Number of ridge plates needed:

                                               Length of one ridge capping = 1 800 mm
                                               Width of roof covering = 8 300 mm

                                               Number of      Width of roof covering
                                               ridge     =    Length of one ridge plate
                                               plates
                                               = 8,3 ✓
                                                  1,8 ✓
                                               = 4,61
                                               = 5 ✓ ridge plates of 1,8 m long are
                                               needed                                          (3)

3.4
                                                       ASSESSMENT               MARK
                               ✓                       CRITERIA
                                                       Wall                         1
                                                       Capping                      1
                 ✓
                                                       Rough ground                 1
                           ✓       ✓                   Tongue and groove
                                                                                    1
                                                       board
                                                       Correctness of drawing       1
                                                                       TOTAL:       5
                                       Correctness ✓
                                                                                               (5)
Copyright reserved                                                                Please turn over

### Page 10

10                       CIVIL TECHNOLOGY: WOODWORKING          (EC/SEPTEMBER 2022)

 3.5

                     ✓

                ✓

            ✓
                               ✓

                     ✓
                                ✓

                                           ASSESSMENT CRITERIA MARK
                                           Top shelf (full width)      1
                                           Intermediate side in middle 1
                                           Hanging space on left side  1
                                           Oval hanging rail           1
                                           FOUR shelves                2
                                           TWO drawer units below
                                                                       1
                                           shelving
                                ✓          Correctness of drawing      1
                                                                TOTAL: 8

                                          Correctness ✓
                                                                               (8)
                                                                              [30]

Copyright reserved                                                 Please turn over

### Page 11

(EC/SEPTEMBER 2022)               CIVIL TECHNOLOGY: WOODWORKING                           11

 QUESTION 4:          ROOFS, CEILINGS, TOOLS AND EQUIPMENT, AND MATERIALS
                      (SPECIFIC)

 4.1 4.1.1      A – Jigsaw ✓
                B – Lathe ✓                                                                (2)

       4.1.2    • Clean the jigsaw blade after use and store in a safe place. ✓
                • Use the correct blade only for the intended purposes. ✓
                • Do not force the jigsaw blade to cut through material.
                • Avoid the use of blunt saw blades.
                • Keep the power cord away from the blade.
                • Always plan your cuts carefully – make pre-cuts if necessary to
                  prevent blade from breaking.
                • Use the correct blade for the specific work.
                ANY TWO OF THE ABOVE                                                       (2)

       4.1.3    • Always ensure that the work piece/stock is fastened tightly. ✓
                • Ensure that the work piece/stock moves freely. ✓
                • Ensure that the tool rest is locked as close as possible to the work-
                  piece/stock.
                ANY TWO OF THE ABOVE                                                       (2)

 4.2   • Store the belt sander in a place where it cannot be damaged by dirt or dust. ✓
       • Store in a wooden box away from moisture.
       ANY ONE OF THE ABOVE                                                                (1)

 4.3   •   Strength ✓
       •   Density ✓                                                                       (2)

 4.4   •   Sand the wood surface with different grades of sandpaper ✓
       •   Sand until the surface is smooth and free from scratches. ✓
       •   Remove all dust. ✓                                                              (3)

 4.5   •    A conventional trapdoor consists of a panel that can be pushed up ✓
       •    Hinged trapdoor open upwards/downwards by pivoting around the hinges. ✓        (2)

 4.6 Timber framework ✓
     Panel ✓
     Cover strip
     ANY TWO OF THE ABOVE                                                                  (2)

 4.7 King post:  114 mm x 38 mm ✓
     Brandering: 38 mm x 38 mm/38 mm x 50 mm ✓                                             (2)

 4.8 Hurricane clips:
     • Securing purlins to rafter (roof truss)
     • Securing trusses to wall plates
     • Ideally used at eaves overhangs
     • Where truss cross each other or where truss members cross each other or
       meet at 90°
     • To fix opposite faces of roof members. ✓

       Storm clips: Securing roof tiles to the battens. ✓                                  (2)

Copyright reserved                                                           Please turn over

### Page 12

12                         CIVIL TECHNOLOGY: WOODWORKING               (EC/SEPTEMBER 2022)

 4.9                                                RIDGE BEAM ✓
                                                    228 mm x 38 ✓
                                                    mm
                                           ✓             RAFTER ✓
                                                         114 mm x 38       ✓
                            ✓                            mm
                                                         ✓

                                           ✓
                     ✓
                         WALL PLATE ✓       TIE BEAM ✓            ✓
         ✓               114 mm x 38        114 mm x 38                      ✓
                         mm                 mm
                                           ✓
                                        SPAN 3 m

                         WALL 220 mm
                     ✓                                           ✓

       ASSESSMENT CRITERIA              MARK
       Walls drawn correctly              2
       Wall plates drawn correctly        2
       Tie beam drawn correctly           2
       Rafters drawn correctly            2
       Ridge beam drawn correctly         2
       Overhang drawn correctly           2                Scale ✓✓✓
       Labels (any TWO)                   2
       Span                               1
       Dimensions of members (any         2
       TWO)
       Application of scale:
       ONE or TWO incorrect        =3
       THREE or FOUR incorrect = 2        3
       More than FIVE incorrect = 1
       NO measurement correct = 0
                                 TOTAL:  20

       DRAWING NOT TO SCALE
       A MASK MUST BE USED TO MARK THIS QUESTION                                        (20)
                                                                             TOTAL:          40

Copyright reserved                                                        Please turn over

### Page 13

(EC/SEPTEMBER 2022)                 CIVIL TECHNOLOGY: WOODWORKING                    13

 QUESTION 5:          CENTRING, FORMWORK, SHORING AND GRAPHICS AS
                      MEANS OF COMMUNICATION (SPECIFIC)

 5.1 5.1.1      Open laggings ✓                                                      (1)

       5.1.2    Closed laggings ✓                                                    (1)

 5.2

                                                               RIB ✓

                      ✓                          ✓

                                    ✓                          TIE BEAM ✓

        ASSESSMENT CRITERIA                          MARK
        Tie beam                                       1
        Ribs                                           2
                                                             Correctness ✓
        Two labels                                     2
        Correctness of drawing                         1
                                          TOTAL:       6                             (6)

 5.3 Steel ✓                                                                         (1)

 5.4 Releasing oil ✓                                                                 (1)

Copyright reserved                                                      Please turn over

### Page 14

14                       CIVIL TECHNOLOGY: WOODWORKING               (EC/SEPTEMBER 2022)

 5.5         SHUTTERING
             BOARD SIDE ✓
               CLEAT                              ✓
                                                      ✓

          STRUT/STAY ✓                       ✓
                                              ✓
                WEDGE
        BEARER/HEAD TREE                      ✓
       KICKER/FIXING PLATE

              FISHPLATE
          STRUT/BRACE

                     PROP

                                                             Correctness ✓

         ASSESSMENT CRITERIA                          MARK
         Shuttering board side                          1
         Cleat                                          1
         Kicker/Fixing plate                            1
         Wedge                                          1
         Stay/Strut                                     1
         Any TWO labels                                 2
         Correctness of drawing                         1
                                          TOTAL:        8                             (8)

 5.6 A – Needle ✓
     B – Straining sill ✓
     C – Inclining strut/Raking strut ✓
     D – Horizontal shore ✓
     E – Folding wedge ✓
     F – Wall plate ✓                                                    (6 x 1)      (6)

Copyright reserved                                                      Please turn over

### Page 15

(EC/SEPTEMBER 2022)        CIVIL TECHNOLOGY: WOODWORKING                15

 5.7

                                   ✓

                                       ✓
                               ✓
                                                   ✓

                               ✓

                                              Scale ✓

        ASSESSMENT CRITERIA                 MARK
        Stile                                 1
        Top rail                              1
        Haunch                                3
        Application of scale                  1
                                   TOTAL:     6
                                                                        (6)

                                                           TOTAL:       30

Copyright reserved                                         Please turn over

### Page 16

16                         CIVIL TECHNOLOGY: WOODWORKING                (EC/SEPTEMBER 2022)

 QUESTION 6:           SUSPENDED FLOORS, STAIRCASES, IRONMONGERY, DOORS
                       AND JOINING (SPECIFIC)

 6.1 6.1.1      D✓                                                                       (1)

       6.1.2    D✓                                                                       (1)

       6.1.3    A✓                                                                       (1)

       6.1.4    A✓                                                                       (1)

       6.1.5    B✓                                                                       (1)

 6.2 6.2.1      Double bareface mortise and tenon joint ✓                                (1)

       6.2.2    Framed ledge braced batten door ✓                                        (1)

 6.3

                   ✓               ✓

            Doorframe ✓
                                                                                         (3)

                           ✓

               ✓

                   ✓
                   ✓           ✓                 OR

                                                                                         (3)
            Jamb lining
                                             ASSESSMENT CRITERIA              MARK
                                             Walls                               2
                                             Frame profile of door               1
                                             Jamb lining profile                 1
                                             Title                               1
                                             Architraves                         1
                                                                     TOTAL:      6

Copyright reserved                                                         Please turn over

### Page 17

(EC/SEPTEMBER 2022)               CIVIL TECHNOLOGY: WOODWORKING                               17

 6.4

                          ✓                    ✓       ✓       ✓                 ✓

                                                                            Correctness ✓
        ASSESSMENT CRITERIA                            MARK
        Muntin                                           1
        Raised panels                                    2
        Space for expansion and shrinkage                1
        Hatching                                         1
        Correctness of drawing                           1
                                       TOTAL:            6                                     (6)

 6.5   • On a cupboard door ✓
       • On a drawer ✓                                                                         (2)

 6.6 Night latch ✓                                                                             (1)

 6.7

                                          ✓
                                  ✓

                                          ✓
                              ✓                    ✓

                                                              Correctness    ✓

        ASSESSMENT CRITERIA                            MARK
        Treads on each flight of stairs                  2
        Half-landing                                     1
        Newel post                                       1
        Open well                                        1
        Correctness of drawing                           1
                                              TOTAL:     6                                     (6)

Copyright reserved                                                               Please turn over

### Page 18

18                    CIVIL TECHNOLOGY: WOODWORKING             (EC/SEPTEMBER 2022)

 6.8

                                   ✓
                                   ✓
                                                                  ✓

                                       ✓                              ✓

            ✓                                             ✓
        AIR BRICK

          ✓                            ✓
        ANT GUARD                               ✓
                                               DPC

                                                         Hatching ✓
                                                      Correctness ✓

           ASSESSMENT CRITERIA          MARK
        Bearer                            1
        Joists                            2
        Wall plate                        1
        Tongue and groove floorboard      1
        Skirting                          1
        Quadrant                          1
        Hatching                          1
        Labels for: Ant guard             1
                    Air brick             1
                    DPC                   1
        Correctness of drawing            1
                                 TOTAL:  12                                     (12)
                                                                                [40]

                                                                      TOTAL:    200

Copyright reserved                                                 Please turn over

## Related documents

- [CIV TECH GR12 MEMO SEPT2022 Civil Services English](https://www.hlayiso.com/library/civ-tech-gr12-memo-sept2022-civil-services-english/896ddb1f-2144-4bfc-a35a-3a71507d7637) — Civil Technology · Memo · 2022 · Eng
- [CIV TECH GR12 QP SEPT2022 Woodworking English](https://www.hlayiso.com/library/civ-tech-gr12-qp-sept2022-woodworking-english/c3b4a7c0-761a-45aa-a578-9b98afc86830) — Civil Technology · QP · 2022 · Eng
- [CIV TECH GR12 QP SEPT2022 Civil Services English](https://www.hlayiso.com/library/civ-tech-gr12-qp-sept2022-civil-services-english/90720b3f-011a-43dc-8be9-862cb2bbc268) — Civil Technology · QP · 2022 · Eng
- [CIV TECH GR12 MEMO SEPT2021 English Civil Services](https://www.hlayiso.com/library/civ-tech-gr12-memo-sept2021-english-civil-services/80eb9860-b118-41e2-98fd-5bea1b29a026) — Civil Technology · Memo · 2021 · Eng
- [CIVIL TECH GR12 MEMO GR12 SEPT2017 English](https://www.hlayiso.com/library/civil-tech-gr12-memo-gr12-sept2017-english/fcb77566-a1ac-4dff-af72-678e70ccfbc4) — Civil Technology · Memo · 2017 · Eng
- [CIV TECH GR12 QP SEPT 2023 Construction English](https://www.hlayiso.com/library/civ-tech-gr12-qp-sept-2023-construction-english/4163a632-f091-41bf-8a36-993d566fb2cc) — Civil Technology · QP · 2023 · Eng

## More from Grade 12 Civil Technology

- [CVLT Woodworking Eng watermark](https://www.hlayiso.com/library/cvlt-woodworking-eng-watermark/8e178c6e-fa7b-40f4-8a2c-936e0bee3b38) — QP · 2025 · Eng
- [Civil Technology Nov 2025 (Woodworking) Afr](https://www.hlayiso.com/library/grade-12-civil-technology-2025-nsc-november-exam-question-paper/05a95faf-5891-4d88-9e5e-7d13c1d21648) — QP · 2025 · Afr
- [CIV TECH GR12 QP SEPT2024 Construction English](https://www.hlayiso.com/library/civ-tech-gr12-qp-sept2024-construction-english/12643629-87af-4230-a48a-002beb7f6cd7) — QP · 2024 · Eng
- [Civil Technology Nov 2024 (Woodworking) Afr](https://www.hlayiso.com/library/civil-technology-nov-2024-woodworking-afr/eefaae29-fe93-4b75-8223-87bf4f3fc14c) — QP · 2024 · Afr
- [Civil Technology Nov 2024 (Civil Services) Afr](https://www.hlayiso.com/library/civil-technology-nov-2024-civil-services-afr/307147a5-3280-4a11-a82e-cf3e33388eb0) — QP · 2024 · Afr
- [Civil Technology Nov 2023 (Construction) Eng](https://www.hlayiso.com/library/civil-technology-nov-2023-construction-eng/e6743728-8140-42ae-838d-282654a975a5) — QP · 2023 · Eng

## Collection

- [Grade 12 past papers](https://www.hlayiso.com/grade-12/past-papers)

---

Hlayiso: free CAPS and IEB past papers, memos, notes and study guides for South African learners. When citing, link the page URL above, not a PDF or /api/ URL.