# Civil Technology Grade 12 Eastern Cape Mock 2023 QP (Eng)

> Grade 12 Civil Technology question paper from the Eastern Cape Mock Exam 2023 (English), 17 pages. Read online or download the free PDF.

- Page: https://www.hlayiso.com/library/civ-tech-gr12-qp-sept-2023-construction-english/4163a632-f091-41bf-8a36-993d566fb2cc
- Updated: 2026-09-27
- Subject: Civil Technology
- Grade: Grade 12
- Language: English
- Document type: Question paper
- Year: 2023
- Exam period: Eastern Cape Mock Exam
- Curriculum: CAPS
- Pages: 17

Breadcrumbs: [Home](https://www.hlayiso.com/) › [Library](https://www.hlayiso.com/library) › [Grade 12](https://www.hlayiso.com/library/grade-12) › [Civil Technology](https://www.hlayiso.com/library/grade-12/civil-technology) › [Civil Technology Grade 12 Eastern Cape Mock 2023 QP (Eng)](https://www.hlayiso.com/library/civ-tech-gr12-qp-sept-2023-construction-english/4163a632-f091-41bf-8a36-993d566fb2cc)

## About this document

Civil Technology · Grade 12 · Eastern Cape Mock Exam · 2023 · English. Question paper, 17 pages. Read online or download the PDF.

Read it free online on the page above; download the PDF from there.

## Document text

Text extracted from the PDF. Layout, diagrams and tables may not survive extraction.

### Page 1

NATIONAL
                         SENIOR CERTIFICATE

                                 GRADE 12

                          SEPTEMBER 2023

         CIVIL TECHNOLOGY: CONSTRUCTION

MARKS:    200

TIME:     3 hours

                    This paper consists of 17 pages and 2 answer sheets.

### Page 2

2                         CIVIL TECHNOLOGY: CONSTRUCTION                   (EC/SEPTEMBER 2023)

REQUIREMENTS:

1.     ANSWER BOOK

2.     Drawing instruments

3.     A non-programmable pocket calculator

INSTRUCTIONS AND INFORMATION

1.     This question paper consists of SIX questions: TWO questions are generic
       and FOUR questions are subject specific.

2.     Answer ALL the questions.

3.     Answer each question as a whole. Do NOT separate subsections of
       questions.

4.     Start the answer to EACH question on a NEW page.

5.     Do NOT write in the margins of the ANSWER BOOK.

6.     You may use sketches to illustrate your answers.

7.     Write ALL calculations and answers in the ANSWER BOOK or on the
       attached ANSWER SHEETS.

8.     Use the mark allocation as a guide to the length of your answers.

9.     Make drawings and sketches in pencil, fully dimensioned and neatly finished
       off with descriptive titles and notes to conform to the SANS/SABS Code of
       Practice for Building Drawings.

10.    For the purpose of this question paper, the size of a brick should be taken
       as 220 mm x 110 mm x 75 mm.

11.    Use your own discretion where dimensions and/or details have been
       omitted.

12.    Answer QUESTIONS 2.2, 5.2 and 5.9 on the attached ANSWER SHEETS
       using drawing instruments where necessary.

13.    Write your NAME on every ANSWER SHEET and hand them in with your
       ANSWER BOOK, whether you have answered the question or not.

14.    Owing to electronic transfer, drawings in the question paper are NOT to
       scale.

15.    Write neatly and legibly.

Copyright reserved                                                             Please turn over

### Page 3

(EC/SEPTEMBER 2023)                  CIVIL TECHNOLOGY: CONSTRUCTION                          3

QUESTION 1: SAFETY AND MATERIALS (GENERIC)

Start this question on a NEW page.

1.1    What is the aim of the Occupational Health and Safety Act (Act 85 of 1993)
       (OHS Act)?                                                                           (1)

1.2    Name the TWO main causes of accidents.                                   (2 x 1)     (2)

1.3    Name ONE reason why scaffolding should be inspected, before it can be used.
                                                                            (1 x 1)         (1)

1.4    Answer the following questions with regard to the scaffolding in FIGURE 1.4.

               A

                   B

                                                                        C

                                           FIGURE 1.4

       1.4.1       Name parts A to C.                                           (3 x 1)     (3)

       1.4.2       Is this a dependant or an undependant scaffolding?                       (1)

       1.4.3       What is the maximum height that part A must be from the platform?        (1)

1.5    Answer the following questions regarding the regulations on a construction site.

       1.5.1       Name ONE way to transport waste material from higher levels in a
                   building to the ground level.                            (1 x 1)         (1)

       1.5.2       If work is done above an entrance, what will prevent materials from
                   falling on workers below?                                                (1)

Copyright reserved                                                             Please turn over

### Page 4

4                          CIVIL TECHNOLOGY: CONSTRUCTION                  (EC/SEPTEMBER 2023)

1.6    Indicate whether the following statements are TRUE or FALSE.

       1.6.1    Trestle scaffold is used on heights greater than 3 m.                      (1)

       1.6.2    No stack height should exceed three times the width of the material.       (1)

       1.6.3    Aluminium ladders can be used in the proximity of electrical wires.        (1)

       1.6.4    The horizontal part of a ladder is called a stile.                         (1)

1.7    Name the TWO main groups into which paint can be divided.               (2 x 1)     (2)

1.8    What is the purpose of galvanising?                                                 (1)

1.9    Name TWO advantages of curing (concrete).                               (2 x 1)     (2)
                                                                                          [20]

Copyright reserved                                                             Please turn over

### Page 5

(EC/SEPTEMBER 2023)                CIVIL TECHNOLOGY: CONSTRUCTION                            5

QUESTION 2: GRAPHICS, JOINING AND EQUIPMENT (GENERIC)

Start this question on a NEW page.

2.1    Identify SIX of the descriptions below which are applicable to the checklist of
       a floor plan.

       •   Window numbers
       •   Building lines
       •   Plot number
       •   Door swings
       •   Names of rooms
       •   Ground contours
       •   Stair directions
       •   Sliding doors
       •   Street number
       •   Water connection point
       •   Position of proposed building
       •   Floor covering                                                      (6 x 1)      (6)

2.2    FIGURE 2.2 on ANSWER SHEET A shows the incomplete elevation of a
       building. Complete the elevation by drawing in the following parts on scale
       1 : 50.

       2.2.1    A window with a length of 1 800 mm and a height of 900 mm.
                The window is built in 700 mm from the right-hand side and one-third
                of the right side of the window can open.                                   (7)

       2.2.2    A door according to standard measurements, 900 mm from the left
                side of the building. The door opens to the left. There is one step to
                the ground level.                                                           (5)

       2.2.3    The barge board against the gable end.                                      (2)

2.3    Identify the appliances which are illustrated by the following drawing symbols.

       2.3.1
                                                                                            (1)

       2.3.2
                                                                                            (1)

Copyright reserved                                                             Please turn over

### Page 6

6                          CIVIL TECHNOLOGY: CONSTRUCTION                  (EC/SEPTEMBER 2023)

2.4    Make neat sketches according to standard building drawing practice to
       illustrate the following symbols.

       2.4.1    Water meter                                                                  (2)

       2.4.2    Plaster                                                                      (2)

       2.4.3    Invert level                                                                 (2)

2.5    Briefly explain the advantages of the square shoulder screw.                          (2)

2.6    Explain the meaning of the following code on rawl bolts: R-RBL M06/18.                (3)

2.7    What is the purpose of the foot screws of the dumpy level?                            (1)

2.8    Identify the cross hairs A to C in the telescope of the dumpy level in
       FIGURE 2.8.

                               A
                               B
                                                                C

                                       FIGURE 2.8
                                                                                (3 x 1)      (3)

2.9    Name TWO uses of the dumpy level.                                        (2 x 1)      (2)

2.10   Motivate briefly why labels and metal plates should be removed from the
       multi-detector before using the instrument.                                           (1)
                                                                                            [40]

                                                               TOTAL SECTION A:              60

Copyright reserved                                                                Please turn over

### Page 7

(EC/SEPTEMBER 2023)                   CIVIL TECHNOLOGY: CONSTRUCTION                             7

QUESTION 3: ROOFS, STAIRCASES AND JOINING (SPECIFIC)

Start this question on a NEW page.

3.1   Answer the following questions with regard to the roof truss in FIGURE 3.1.

               A
                                                                             D

           B                                                                 E

                             C
                                          FIGURE 3.1

      3.1.1    Name parts A to E.                                                (5 x 1)      (5)

      3.1.2    Identify this type of roof truss.                                              (1)

3.2   Name THREE requirements that roof trusses should meet.                     (3 x 1)      (3)

3.3   Answer the following questions with regard to thatched roofs.

      3.3.1    What is the minimum diameter of roof poles?                                    (1)

      3.3.2    What is the thickness of the dry thatch bundles that are fixed to the
               roof?                                                                          (1)

      3.3.3    Why should the thatched roof overhangs be at least 4,5 m from any
               neighbouring property?                                                         (1)

3.4   Name TWO advantages for the use of roof underlay.                          (2 x 1)      (2)

3.5   Provide the MEASUREMENT for the following descriptions of staircases.

      3.5.1        The minimum measurement from the pitch line to the ceiling.                (1)

      3.5.2        The maximum measurement of the gaps between the vertical posts.            (1)

      3.5.3        The maximum pitch of the stairs used by the public.                        (1)

Copyright reserved                                                                 Please turn over

### Page 8

8                         CIVIL TECHNOLOGY: CONSTRUCTION                     (EC/SEPTEMBER 2023)

3.6   Provide ONE term for the following descriptions of staircases.

      3.6.1    A level area between two flights of stairs.                                 (1)

      3.6.2    The horizontal part of a stair.                                             (1)

      3.6.3    A combination of balusters.                                                 (1)

3.7   Answer the following questions with regard to the staircase in FIGURE 3.7.

                                                                         A

                                                                         B

                                                                         C

                                        FIGURE 3.7

      3.7.1    Name parts A to C.                                              (3 x 1)     (3)

      3.7.2    Name ONE material that part B can be made of.                               (1)

3.8   Indicate whether the following statements are TRUE or FALSE.

      3.8.1    Galvanised steel straps cannot rust.                                        (1)

      3.8.2    Roof underlays is 250 micron in thickness.                                  (1)

      3.8.3    The ridge plate joins the roof truss to the wall plate.                     (1)

      3.8.4    The cornice joins the wall plate to the wall.                               (1)

3.9   Name TWO types of cast-in anchors.                                       (2 x 1)     (2)
                                                                                          [30]

Copyright reserved                                                               Please turn over

### Page 9

(EC/SEPTEMBER 2023)                 CIVIL TECHNOLOGY: CONSTRUCTION                            9

 QUESTION 4:          MATERIAL, EQUIPMENT AND TOOLS, EXCAVATIONS AND
                      FOUNDATIONS (SPECIFIC)

 Start this question on a NEW page.

 4.1    Choose a description from COLUMN B that best matches with an item in
        COLUMN A. Write only the letter next to the question numbers (4.1.1 to
        4.1.6) in the ANSWER BOOK, for example 4.1.7 J.

                    COLUMN A                                COLUMN B
        4.1.1    Brass                         A   alloy of steel and tin

        4.1.2    Polystyrene                   B   highly toxic

        4.1.3    Cast iron                     C   pumps small volumes of concrete

        4.1.4    Line pipe concrete pump       D   hard, but is brittle and breaks
                                                   easily

        4.1.5    Lead                          E   packaging material

        4.1.6    Boom pump                     F   dipped in molten zinc

                                               G   alloy of copper and zinc

                                               H   pumps high volumes of concrete
                                                                            (6 x 1)        (6)
 4.2    Answer the following questions with regard to the test in FIGURE 4.2.

                                           FIGURE 4.2

        4.2.1    Identify this type of test.                                               (1)

        4.2.2    What is the bottom (bigger) diameter of the cone?                         (1)

        4.2.3    What is the length of the tamping rod?                                    (1)

        4.2.4    Name TWO reasons for this test.                              (2 x 1)      (2)

Copyright reserved                                                              Please turn over

### Page 10

10                           CIVIL TECHNOLOGY: CONSTRUCTION                  (EC/SEPTEMBER 2023)

4.3     Name TWO ways of curing concrete.                                        (2 x 1)     (2)

4.4     Name the TWO main groups into which metals can be classified.           (2 x 1)      (2)
4.5     Name THREE types of material that can be used for the cladding of
        buildings.                                                        (3 x 1)            (3)

4.6     Answer the following questions on the construction machine in FIGURE 4.6.

                                              FIGURE 4.6

        4.6.1        Identify this machine.                                                  (1)

        4.6.2        Name TWO ways of maintaining the machine.                  (2 x 1)      (2)

        4.6.3        Where will this machine be used?                                        (1)

4.7     Name THREE causes for the collapse of an excavation.                     (3 x 1)     (3)

4.8     Name THREE ways of making excavations safe during the night.             (3 x 1)     (3)

4.9     Explain the safety regulations for the following during excavations.

        4.9.1        Access to a deep excavation                                             (1)

        4.9.2        The distance of machinery away from trenches                            (1)

        4.9.3        Testing for atmospheric hazards                                         (1)

4.10    Identify the following statements as TRUE or FALSE.

        4.10.1       Bracing is necessary for trenches deeper than one metre.                (1)

        4.10.2       Shoring is not compulsory where the banks are sloped.                   (1)

        4.1.0.3      Excavated material must be at least two metres from trench edges.       (1)

Copyright reserved                                                               Please turn over

### Page 11

(EC/SEPTEMBER 2023)                CIVIL TECHNOLOGY: CONSTRUCTION                        11

4.11   Answer the following questions with regard to the shuttering in FIGURE 4.11.

                                                                     B

                      A

                                                                     C

                                        FIGURE 4.11

       4.11.1    Identify the type of soil in FIGURE 4.11.                               (1)

       4.11.2    Name the parts A to C.                                      (3 x 1)     (3)

4.12   Name any TWO foundation types.                                        (2 x 1)    (2)
                                                                                       [40]

Copyright reserved                                                          Please turn over

### Page 12

12                         CIVIL TECHNOLOGY: CONSTRUCTION                  (EC/SEPTEMBER 2023)

QUESTION 5: BRICKWORK, GRAPHICS, PLASTER AND SCREED (SPECIFIC)

Start this question on a NEW page.

5.1    Answer the following questions with regard to the wall in FIGURE 5.1.

                                                                 A

                                          FIGURE 5.1

       5.1.1    In what type of bond has this wall been build?                             (1)

       5.1.2    Identify the wall type.                                                    (1)

       5.1.3    What is the width of the wall?                                             (1)

       5.1.4    Identify part A.                                                           (1)

5.2    Draw a neat sketch on ANSWER SHEET B and show a three-layer brick wall
       in stretcher bond. Show raking back on the left-hand side and toothing on the
       right-hand side. Use any sufficient scale.                                          (4)

5.3    Answer the following questions with regard to cavity walls.

       5.3.1    What is the purpose of a weep hole?                                        (1)

       5.3.2    What is the maximum length for a cavity wall?                              (1)

       5.3.3    What is the maximum height for a cavity wall?                              (1)

       5.3.4    What connects the two skins?                                               (1)

       5.3.5    In what type of regions will ventilating bricks be used?                   (1)

       5.3.6    How high above ground level must the damp-proof course be laid?            (1)

5.4    Name TWO advantages of cavity walls.                                    (2 x 1)     (2)

5.5    Name any TWO types of wall ties.                                        (2 x 1)     (2)

Copyright reserved                                                             Please turn over

### Page 13

(EC/SEPTEMBER 2023)                   CIVIL TECHNOLOGY: CONSTRUCTION                               13

5.6    Choose a description from COLUMN B that fits best with the item in
       COLUMN A. Write only the letter next to the question numbers (5.6.1 to 5.6.4)
       in the ANSWER BOOK, for example. 5.6.5 G.

               COLUMN A                                 COLUMN B
       5.6.1    Kerb              A      natural soil on which the paving will be laid

       5.6.2    Sub-base          B      sand used as grouting between paving blocks

       5.6.3    Subgrade          C      best form of edge restraint for paving

       5.6.4    Bedding sand      D      final layer upon which paving is laid

                                  E      preparation of the sub-base

                                  F      prepared layer beneath paving and bedding
                                         sand
                                                                            (4 x 1)              (4)

5.7    Name TWO advantages of mortar-set paving.                                      (2 x 1)    (2)

5.8    Name TWO reasons for construction failure of paving.                           (2 x 1)    (2)

5.9    Draw a neat sketch with EIGHT (8) bricks of the basket-weave paving pattern
       on ANSWER SHEET B. Use own sufficient scale.                                              (4)

5.10   Answer the following question with regard to the arch in FIGURE 5.10.

                                                                                  B

                                              A

                                              C

                                          FIGURE 5.10

       5.10.1    Identify this type of arch construction.                                        (1)

       5.10.2    Name parts A to C.                                                   (3 x 1)    (3)

5.11   Name the TWO ingredients of plaster (water and lime excluded).                 (2 x 1)    (2)

5.12   Name TWO types of plaster finishes.                                            (2 x 1)    (2)

5.13   Name TWO types of screed layers.                                           (2 x 1)        (2)
                                                                                                [40]

Copyright reserved                                                                    Please turn over

### Page 14

14                         CIVIL TECHNOLOGY: CONSTRUCTION                  (EC/SEPTEMBER 2023)

QUESTION 6:          FORMWORK, REINFORCEMENT, CONCRETE FLOORS AND
                     QUANTITIES (SPECIFIC)

Start this question on a NEW page.

6.1    Name TWO materials that can be used to line the formwork, to obtain a
       smoother finish for the concrete.                                   (2 x 1)         (2)

6.2    Name TWO types of timber boards that can be used for formwork.          (2 x 1)     (2)

6.3    Name THREE properties of good formwork.                                 (3 x 1)     (3)

6.4    Answer the following questions in regard to the floor construction in
       FIGURE 6.4.

                                     A                    B
                                          FIGURE 6.4

       6.4.1    Name parts A and B.                                            (2 x 1)     (2)

       6.4.2    Identify this type of concrete floor.                                      (1)

       6.4.3    Name ONE disadvantage of this floor type.                      (1 x 1)     (1)

6.5   Answer the following questions with regard to the rod code in FIGURE 6.5.

                                Rod / bar code: 16Y20-01-250
                                         FIGURE 6.5

       6.5.1    What type of steel is used?                                                (1)

       6.5.2    What is the diameter of the rods?                                          (1)

       6.5.3    What is spacing of the rods?                                               (1)

6.6    What forces are counteracted by the following parts in a concrete beam?

       6.6.1    Main bar                                                                   (1)

       6.6.2    Anchor bar                                                                 (1)

Copyright reserved                                                             Please turn over

### Page 15

(EC/SEPTEMBER 2023)                  CIVIL TECHNOLOGY: CONSTRUCTION                     15

6.7    Name THREE properties of reinforced steel bars.                    (3 x 1)       (3)

6.8    Name TWO reasons for the cover depth of reinforcement in concrete work.
                                                                          (2 x 1)       (2)

6.9    FIGURE 6.9 shows the foundation strips with inside measurements for a
       storeroom. The foundation is 700 mm wide and 250 mm thick.
       Answer the following questions in the ANSWER BOOK.
       Table format is NOT compulsory (Show ALL formulas and steps.)

                                                 8 500

               4 750

                                          FIGURE 6.9

       6.9.1      Calculate the centreline of the foundation.                           (5)

       6.9.2      Calculate the volume of concrete needed.                             (4)
                                                                                      [30]

                                                                        TOTAL:         200

Copyright reserved                                                         Please turn over

### Page 16

16                         CIVIL TECHNOLOGY: CONSTRUCTION                   (EC/SEPTEMBER 2023)

                                CIVIL TECHNOLOGY
  ANSWER SHEET           A           GENERIC
                                                          NAME:

 2.2 FIGURE 2.2 on ANSWER SHEET A shows the incomplete elevation of a
     building. Complete the elevation by drawing in the following parts on scale
     1 : 50.

       2.2.1    A window with a length of 1 800 mm and a height of 900 mm.
                The window is built in 700 mm from the right-hand side and one-third
                of the right side of the window can open.                                     (7)

       2.2.2    A door according to standard measurements, 900 mm from the left
                side of the building. The door opens to the left. There is one step to
                the ground level.                                                             (5)

       2.2.3    The barge board against the gable end.                                        (2)

                                                                 Window                   7
                                                                 Door                     5
                                                                 Barge board              2

                                                                             TOTAL: 14

                             FIGURE 2.2

Copyright reserved                                                               Please turn over

### Page 17

(EC/SEPTEMBER 2023)             CIVIL TECHNOLOGY: CONSTRUCTION                          17

                            CIVIL TECHNOLOGY
  ANSWER SHEET        B       CONSTRUCTION
                                                      NAME:

5.2 Draw a neat sketch and show a three layer brick wall in stretcher bond.
    Show raking back on the left-hand side and toothing on the right-hand side.
    Use own sufficient scale

                                                                                      (4)

5.9 Draw a neat sketch with eight (8) bricks of the basket-weave paving pattern.
    Use own sufficient scale.

                                                                                      (4)

Copyright reserved                                                         Please turn over

## Related documents

- [CIV TECH GR12 MEMO SEPT2023 Construction English](https://www.hlayiso.com/library/civ-tech-gr12-memo-sept2023-construction-english/9ab6f3f0-4774-49bf-8311-57f09822adf6) — Civil Technology · Memo · 2023 · Eng
- [CIV TECH GR12 QP SEPT2022 Woodworking English](https://www.hlayiso.com/library/civ-tech-gr12-qp-sept2022-woodworking-english/c3b4a7c0-761a-45aa-a578-9b98afc86830) — Civil Technology · QP · 2022 · Eng
- [CIV TECH GR12 QP SEPT2022 Civil Services English](https://www.hlayiso.com/library/civ-tech-gr12-qp-sept2022-civil-services-english/90720b3f-011a-43dc-8be9-862cb2bbc268) — Civil Technology · QP · 2022 · Eng
- [CIV TECH GR12 QP SEPT2021 English Construction](https://www.hlayiso.com/library/civ-tech-gr12-qp-sept2021-english-construction/551ab3e9-47c5-4ab0-a0cf-bc66dda5a956) — Civil Technology · QP · 2021 · Eng
- [CIVIL TECH QP GR12 SEPT 2019 Woodwork English](https://www.hlayiso.com/library/civil-tech-qp-gr12-sept-2019-woodwork-english/7eaa0222-4bca-4690-a584-eab0441f77d9) — Civil Technology · QP · 2019 · Eng
- [CIV TECH GR12 MEMO SEPT2022 Woodworking English](https://www.hlayiso.com/library/civ-tech-gr12-memo-sept2022-woodworking-english/62d9cbb1-1077-4edb-86c4-7a21fd6749a9) — Civil Technology · Memo · 2022 · Eng

## More from Grade 12 Civil Technology

- [Civil Technology Nov 2025 (Construction) MG Eng](https://www.hlayiso.com/library/grade-12-civil-technology-2025-nsc-november-exam-memorandum/0e265899-dc44-4809-aabf-8f374f1af392) — Memo · 2025 · Eng
- [CIV TECH GR12 MEMO SEPT2024 Civil Services English](https://www.hlayiso.com/library/civ-tech-gr12-memo-sept2024-civil-services-english/c1f2441d-22ba-4ae6-9e56-137cc442080c) — Memo · 2024 · Eng
- [CIV TECH GR12 MEMO SEPT2024 Construction English](https://www.hlayiso.com/library/civ-tech-gr12-memo-sept2024-construction-english/4d9c54ef-f526-46ad-82d4-8dd419eafb50) — Memo · 2024 · Eng
- [CIV TECH GR12 MEMO SEPT2024 Woodworking English](https://www.hlayiso.com/library/civ-tech-gr12-memo-sept2024-woodworking-english/6e7f4be5-4ffb-4654-b98b-b4cc4dfc4cc7) — Memo · 2024 · Eng
- [Civil Technology Nov 2022 (Civil Services) MG Afr](https://www.hlayiso.com/library/civil-technology-nov-2022-civil-services-mg-afr/42b5315c-825c-40e3-b394-85e0253fc0fb) — Memo · 2023 · Afr
- [Civil Technology Nov 2023 (Civil Services) Afr](https://www.hlayiso.com/library/civil-technology-nov-2023-civil-services-afr/b820ac91-947c-4aed-821f-256aa13aabe1) — QP · 2023 · Afr

## Collection

- [Grade 12 past papers](https://www.hlayiso.com/grade-12/past-papers)

---

Hlayiso: free CAPS and IEB past papers, memos, notes and study guides for South African learners. When citing, link the page URL above, not a PDF or /api/ URL.