# Civil Technology Grade 12 Eastern Cape Mock 2017 QP (Eng)

> Grade 12 Civil Technology question paper from the Eastern Cape Mock Exam 2017 (English), 22 pages. Read online or download the free PDF.

- Page: https://www.hlayiso.com/library/civil-tech-gr12-qp-sept2017-english/165974ea-5928-4471-aea5-c08917fd9010
- Updated: 2026-09-27
- Subject: Civil Technology
- Grade: Grade 12
- Language: English
- Document type: Question paper
- Year: 2017
- Exam period: Eastern Cape Mock Exam
- Curriculum: CAPS
- Pages: 22

Breadcrumbs: [Home](https://www.hlayiso.com/) › [Library](https://www.hlayiso.com/library) › [Grade 12](https://www.hlayiso.com/library/grade-12) › [Civil Technology](https://www.hlayiso.com/library/grade-12/civil-technology) › [Civil Technology Grade 12 Eastern Cape Mock 2017 QP (Eng)](https://www.hlayiso.com/library/civil-tech-gr12-qp-sept2017-english/165974ea-5928-4471-aea5-c08917fd9010)

## About this document

Civil Technology · Grade 12 · Eastern Cape Mock Exam · 2017 · English. Question paper, 22 pages. Read online or download the PDF.

Read it free online on the page above; download the PDF from there.

## Document text

Text extracted from the PDF. Layout, diagrams and tables may not survive extraction.

### Page 1

Downloaded from hlayiso.com

                             NATIONAL
                        SENIOR CERTIFICATE

                              GRADE 12

                        SEPTEMBER 2017

                      CIVIL TECHNOLOGY

MARKS:   200

TIME:    3 hours

                                 *CVLTE*

                  This question paper consists of 17 pages,
               including 4 answer sheets and a formula sheet.

### Page 2

Downloaded from hlayiso.com
2                                  CIVIL TECHNOLOGY                         (EC/SEPTEMBER 2017)

 REQUIREMENTS:

 1.     ANSWER BOOK

 2.     Drawing instruments

 3.     A non-programmable calculator

 INSTRUCTIONS AND INFORMATION

 1.     This question paper consists of SIX questions.

 2.     ALL questions are COMPULSORY.

 3.     Answer each question as a whole. Do NOT separate subsections of
        questions.

 4.     Start EACH question on a NEW page.

 5.     You may use sketches to illustrate your answers.

 6.     ALL calculations and written answers must be done in the ANSWER BOOK
        or on the attached ANSWER SHEETS.

 7.     Use the mark allocation as a guide for the length of your answer.

 8.     Make drawing and sketches in pencil, fully dimensioned and neatly finished
        off with descriptive titles and notes, to conform to the SANS (SABS)
        Recommended Practice for Building Drawings.

 9.     For the purpose of this examination, the size of a brick should be taken as
        220 mm x 110 mm x 75 mm.

 9.     Use your discretion where dimensions and/or details have been omitted.

 10.    Answer QUESTION 4.11, 4.12, 5.1, 5.2, 5.3, and 6.4 on the attached
        ANSWER SHEETS using drawing instruments where necessary.

 11.    Due to electronic transfer, drawings in the question paper are NOT to scale.

Copyright reserved                                                             Please turn over

### Page 3

Downloaded from hlayiso.com
(EC/SEPTEMBER 2017)                CIVIL TECHNOLOGY                                           3

 QUESTION 1: CONSTRUCTION PROCESSES

 1.1 FIGURE 1.1 shows the substructure of a structure. Answer the following
     questions with regard to the construction in FIGURE 1.1.

                                                                        1.1.C
                              1.1.A
                                                                        1.1.D

               1.1.B

                                        FIGURE 1.1

       1.1.1    What is the minimum measurement of the damp-proofing above the
                ground level at 1.1.A?                                                       (1)

       1.1.2    What is the minimum measurement of the foundation bottom below
                ground at 1.1.B?                                                             (1)

       1.1.3    What is the thickness of the wall construction in FIGURE 1.1?                (1)

       1.1.4    What type of material is the floor at 1.1.C manufactured from?               (1)

       1.1.5    What is part 1.1.D called?                                                   (1)

       1.1.6    Name TWO purposes of part 1.1.D.                                (2 x 1)      (2)

 1.2 Briefly motivate why the water table level must be determined when an
     effective foundation for a structure is planned.                                        (2)

 1.3 Describe the advantage of holes in clay bricks during the baking process.               (2)

 1.4 Name THREE properties of face bricks.                                       (3 x 1)     (3)

 1.5 Describe in point form the manufacturing process of clay bricks.                        (6)

Copyright reserved                                                              Please turn over

### Page 4

Downloaded from hlayiso.com
4                                   CIVIL TECHNOLOGY                       (EC/SEPTEMBER 2017)

 1.6 FIGURE 1.6 shows a wooden door frame. Answer the following questions
     with regard to the door frame in FIGURE 1.6.

                     1.1.A

                     1.1.B

                     1.1.C

                     1.1.D

                 1.1.E

                                        FIGURE 1.6

       1.6.1    Briefly describe the method of building door frames into walls.            (2)

       1.6.2    Name parts 1.1.A to 1.1.C.                                                 (3)

       1.6.3    What is the measurement of the door opening at 1.1.D?                      (1)

       1.6.4    What is the purpose of the pegs at 1.1.E?                                  (1)

 1.7 Name the tools in FIGURES 1.7.1 to 1.7.3.

       1.7.1

                                                                                           (1)
       1.7.2

                                                                                           (1)
       1.7.3

                                                                                          (1)
                                                                                         [30]

Copyright reserved                                                            Please turn over

### Page 5

Downloaded from hlayiso.com
(EC/SEPTEMBER 2017)              CIVIL TECHNOLOGY                                         5

QUESTION 2: ADVANCED CONSTRUCTION PROCESSES

2.1 Answer the following questions with regard to the reinforced concrete beam in
    FIGURE 2.1.

        2.1.A

        2.1.B

                                                        2 Y 1601

                                        FIGURE 2.1

      2.1.1 What is bar 2.1.A called?                                                     (1)

      2.1.2 What is the purpose of bar 2.1.A?                                             (1)

      2.1.3 From which type of steel is bar 2.1.A manufactured?                           (1)

      2.1.4 What is the sectional size of bar 2.1.A?                                      (1)

      2.1.5 What are the bars at 2.1.B called?                                            (1)

      2.1.6 Name TWO purposes of the bars at 2.1.B.                          (2 x 1)      (2)

2.2 Describe TWO requirements with which the steel for steel reinforcement must
    comply.                                                              (2 x 2)          (4)

2.3 Briefly describe the purpose of efficient concrete covering for reinforced
    concrete.                                                                             (2)

2.4 Briefly describe the difference between the type of bricks which are used for a
    rough arch and bricks that are used for a gauged arch.                                (2)

2.5 Briefly motivate why a clearance of 2 mm must be around the glass when it is
    fixed to a frame.                                                                     (2)

2.6 Name THREE safety rules to be observed when working on floors and stairs
    with open sides.                                                  (3 x 1)             (3)

Copyright reserved                                                          Please turn over

### Page 6

Downloaded from hlayiso.com
6                                    CIVIL TECHNOLOGY                       (EC/SEPTEMBER 2017)

2.7 Name the parts of beam the shuttering in FIGURE 2.7.

                     2.7.1

                     2.7.2

                     2.7.3

                             2.7.4

                         2.7.5
                                                                                             (5)
                                           FIGURE 2.7

2.8 Make a neat sectional sketch to illustrate the construction of an open eave
    construction. The following parts must be indicated in the sketch: outer wall,
    rafter, tie beam, facia board (gutter board), 2 purlines, tile roof covering and
    beam filling.                                                                            (8)

2.9 Briefly describe the purpose of a raking shore.                                          (2)

2.10 Indicate whether the following statements are TRUE or FALSE.
     Write only the word ‘true’ or ‘false’ next to the number in the ANSWER BOOK.

      2.10.1 Trestles are used to support walls.                                             (1)

      2.10.2 Scaffolds for high buildings must be assembled at an angle of 5°.               (1)

      2.10.3 High scaffolds must be attached to a building.                                  (1)

      2.10.4 Scaffolds should not be moved while workers are still on it.                    (1)

      2.10.5 The depth of kitchen units is 900 mm.                                          (1)
                                                                                           [40]

Copyright reserved                                                             Please turn over

### Page 7

Downloaded from hlayiso.com
(EC/SEPTEMBER 2017)                 CIVIL TECHNOLOGY                                          7

QUESTION 3: CIVIL SERVICES

3.1 Answer the following questions with regard to the drainage structure in
    FIGURE 3.1.

       3.1.A
       3.1.B                                                      LIQUID LEVEL
                                                                           3.1.D

        3.1.C

                                         FIGURE 3.1

      3.1.1     What is the structure called?                                                (1)

      3.1.2     Briefly describe how the organic matter decomposes in the structure.         (2)

      3.1.3     What is the purpose if the inlet pipe opening at 3.1.B?                      (1)

      3.1.4     Briefly motivate why the inflow at 3.1.B must be lower than the liquid
                level.                                                                       (2)

      3.1.5     To which structure is the effluent at 3.1.D discharged?                      (1)

3.2 Briefly describe the disadvantageous effects in a drain system when it is not
    equipped with a ventilation pipe.                                                        (2)

3.3 Make a neat sketch to illustrate the construction of an S-trap.                          (3)

3.4 Identify the correct answer in each of the following descriptions of the drain
    test methods. Write only the correct word next to the number in the ANSWER
    BOOK.

      3.4.1     The mirror and torch test check that the drain pipe is
                STRAIGHT / SEALED.                                                           (1)

      3.4.2     The ball of the ball test must be 10 mm / SLIGHTLY SMALLER than
                the diameter of the pipe.                                                    (1)

      3.4.3     If the drop in the water level is greater than 16 mm / 6 mm, the pipe
                probably has a leak.                                                         (1)

3.5 Name THREE methods of generating electricity.                                (3 x 1)     (3)

Copyright reserved                                                              Please turn over

### Page 8

Downloaded from hlayiso.com
8                                       CIVIL TECHNOLOGY                       (EC/SEPTEMBER 2017)

3.6      What is the purpose of the conduit pipes in an electrical system?                     (1)

3.7      Briefly describe what an indirect water supply system is.                             (3)

3.8      What is the water supply pipe from the water service point to the dwelling
         called?                                                                               (1)

3.9      Indicate whether the following statements with regard to solar heating
         systems are TRUE or FALSE. Write only the word ‘true’ or ‘false’ next to
         the number in the ANSWER BOOK.

       3.9.1         The hot water of the independent solar heating system is stored in
                     the geyser.                                                               (1)

       3.9.2         The tray of the solar heating system is coated with an isolation
                     material.                                                                 (1)

       3.9.3         The inside of the tray of the solar heating system is coated with
                     white paint to reflect the sun’s rays.                                    (1)

       3.9.4         The best position for the sun collector is due east.                      (1)

       3.9.5         Photovoltaic cells can also be used to heat the water.                    (1)

3.10 Answer the following questions with regard to the tap in FIGURE 3.10.

                                            FIGURE 3.10

       3.10.1        What is this type of tap called?                                          (1)

       3.10.2        Give ONE example where this type of tap must be installed.
                                                                                   (1 x 1)    (1)
                                                                                             [30]

Copyright reserved                                                                Please turn over

### Page 9

Downloaded from hlayiso.com
(EC/SEPTEMBER 2017)                CIVIL TECHNOLOGY                                        9

 QUESTION 4: MATERIALS AND QUANTITIES

 4.1    Name TWO reactions which take place during the hydration process of
        cement.                                                          (2 x 1)          (2)

 4.2    Briefly motivate why cement must not be stored longer than three months.          (2)

 4.3    Name ONE purpose of lime in a mortar mix.                             (1 x 1)     (1)

 4.4    Which ingredient is first put into the concrete mixer when concrete must be
        mixed?                                                                            (1)

 4.5    Name THREE methods that can be used for curing concrete.              (3 x 1)     (3)

 4.6    Briefly motivate why the cube test must be performed on concrete.                 (2)

 4.7    Name TWO uses of each of the following materials in the construction
        trade:

        4.7.1    Copper                                                       (2 x 1)     (2)

        4.7.2    Zink                                                         (2 x 1)     (2)

 4.8    Make a neat sketch to illustrate the profile of channel iron.                     (2)

 4.9    Name THREE properties of a good preservative for wood.                (3 x 1)     (3)

 4.10   Briefly describe the composition of plywood.                                      (2)

 4.11   Use the quantity list on ANSWER SHEET A and determine the volume of
        concrete which will be needed for a floor with a length of 6 m, width of 3 m
        and thickness of 75 mm.                                                           (3)

 4.12   Use the quantity list on ANSWER SHEET A and determine the number of
        bricks which will be needed for a cavity wall with a length of 4 m and a
        height of 2,4 m.                                                                 (5)
                                                                                        [30]

Copyright reserved                                                           Please turn over

### Page 10

Downloaded from hlayiso.com
10                                CIVIL TECHNOLOGY                     (EC/SEPTEMBER 2017)

 QUESTION 5: APPLIED MECHANICS

 5.1 FIGURE 5.1 on ANSWER SHEET B shows the space diagram of a lean-to
     roof. Determine graphically on scale 1 mm = 1 N on ANSWER SHEET B
     the size and nature of the forces in the parts of the truss by drawing the
     force diagram and completing the table.

                                                                                     (14)
                                     FIGURE 5.1

 5.2 FIGURE 5.2 on ANSWER SHEET C shows a beam with point loads.
     Calculate, on ANSWER SHEET C, the following:

        SCALE/SKAAL: 1 mm = 1 N

        10 N          40 N              20 N         30 N

               2m            4m                 2m

                     60 N                            40 N

         a              b                   c          d

                                     FIGURE 5.2

       5.2.1    The bending moment values                                              (6)

       5.2.2    Complete the bending moment diagram on scale 1 mm = 1 N
                according to the bending moment values                                 (4)

Copyright reserved                                                        Please turn over

### Page 11

Downloaded from hlayiso.com
(EC/SEPTEMBER 2017)             CIVIL TECHNOLOGY                                     11

 5.3 Determine, from point P, the sentroid of the body in FIGURE 5.3.
     (The table on ANSWER SHEET C can be used for the calculations.)

                           Y-as

                                                   6

                                                   4

                            P                      X-as

                                     6

                                    FIGURE 5.3                                      (6)
                                                                                   [30]

Copyright reserved                                                      Please turn over

### Page 12

Downloaded from hlayiso.com
12                                  CIVIL TECHNOLOGY                    (EC/SEPTEMBER 2017)

 QUESTION 6: GRAPHICS AND COMMUNICATION

 6.1 Name FOUR responsibilities of the architect which must be reflected in the
     sketch drawings of the design of a structure.                        (4 x 1)      (4)

 6.2 Make neat sketches to illustrate the following symbols:

       6.2.1    Water closet                                                           (2)

       6.2.2    Sink                                                                   (2)

       6.2.3    Water meter                                                            (2)

 6.3 In which working drawing is the entrance to a site indicated?                     (1)

 6.4 FIGURE 6.4 on SHEET D shows the floor plan of a store room on scale
     1 : 50. Draw, on SHEET D, the south elevation on scale 1 : 50 from the
     given ground level line by using the following information:

       -    The floor level above the ground level: 200 mm
       -    Wall height from the floor level to the ceiling: 2 600 mm
       -    Window 1 : 600 x 2 100 mm
       -    Door 1 : 1 400 x 2 100 mm
       -    Door knob
       -    Roof construction pitch: 30º
       -    Indicate construction lines to determine the roof height
       -    Gabel end at west elevation
       -    Hipped roof at east elevation

       Use the marks table on ANSWER SHEET D as reference.                           (29)
                                                                                     [40]

                                                                         TOTAL:      200

Copyright reserved                                                         Please turn over

### Page 13

Downloaded from hlayiso.com
(EC/SEPTEMBER 2017)              CIVIL TECHNOLOGY                                        13

 ANTWOORDBLAD                SIVIELE TEGNOLOGIE         NAAM:

  ANSWER SHEET
                         A    CIVIL TECHNOLOGY          NAME:

  4.11 Use the quantity list on ANSWER SHEET A and determine the volume of
       concrete which will be needed for a floor with a length of 6 m, width of 3 m
       and thickness of 75 mm.                                                           (3)

  4.12 Use the quantity list on ANSWER SHEET A and determine the number of
       bricks which will be needed for a cavity wall with a length of 4 m and a
       height of 2,4 m.                                                                  (5)

    A          B        C                                 D

Copyright reserved                                                          Please turn over

### Page 14

Downloaded from hlayiso.com

### Page 15

Downloaded from hlayiso.com
14                              CIVIL TECHNOLOGY                  (EC/SEPTEMBER 2017)

 ANTWOORDBLAD               SIVIELE TEGNOLOGIE     NAAM:

  ANSWER SHEET
                        B   CIVIL TECHNOLOGY       NAME:

VRAAG/QUESTION 5.1

RUIMTEDIAGRAM/SPACE DIAGRAM:

KRAGTEDIAGRAM/FORCE DIAGRAM

SKAAL/SCALE: 1 mm = 1 N                    DEEL/    Grootte/    Aard/Nature
                                           PART       Size
                                             AD
                                             BE
                                             CE
                                             DE

                                                     Akkuraatheid / Accuracy

                                                                               (14)

Copyright reserved                                                   Please turn over

### Page 16

Downloaded from hlayiso.com

### Page 17

Downloaded from hlayiso.com
(EC/SEPTEMBER 2017)                          CIVIL TECHNOLOGY                                          15

 ANTWOORDBLAD                          SIVIELE TEGNOLOGIE                         NAAM:

  ANSWER SHEET
                             C          CIVIL TECHNOLOGY                          NAME:

VRAAG/QUESTION. 5.2

 5.2.1    Die buigmomentwaardes/The bending moment values                                             (4)

              a   = ...........................................................
              b   = ...........................................................
              c   = ...........................................................
              d   = ...........................................................

 5.2.2     FIGUUR 5.2: Die buigmomentdiagram/The bending moment diagram                               (4)

SKAAL/SCALE: 1 mm = 1 N

10 N          40 N                              20 N              30 N

     2m                     4m                             2m
           60 N                                                   40 N

FIGUUR 5.2

VRAAG/QUESTION 5.3                                                                              (6)

  Vorm /                           X                                                 Y
  Shape

Copyright reserved                                                                        Please turn over

### Page 18

Downloaded from hlayiso.com

### Page 19

Downloaded from hlayiso.com
16                                  CIVIL TECHNOLOGY                       (EC/SEPTEMBER 2017)

 ANTWOORDBLAD                SIVIELE TEGNOLOGIE        NAAM:

  ANSWER SHEET
                        D     CIVIL TECHNOLOGY         NAME:

VRAAG/QUESTION 6.4                                                                      (26)

                            4 200

                            3 640

                                                       2 740   3 300

       SCALE 1 : 50

                                                                       Floor level    2
                                                                       Wall           3
                                                                       Window         3
                                                                       Window sill    1
                                                                       Door           4
                                                                       Step           1
                                                                       Ramp           1
                                                                       Facia board    2
                                                                       Gutter         1
                                                                       Down pipe      1
                                                                       Gable end      4
                                                                       Hipped roof    3
                                                                       Roof height    3
                                                                             TOTAL    29

Copyright reserved                                                            Please turn over

### Page 20

Downloaded from hlayiso.com

### Page 21

Downloaded from hlayiso.com
(EC/SEPTEMBER 2017)                          CIVIL TECHNOLOGY                                                      17

 FORMULA SHEET

 IMPORTANT ABBREVIATIONS

 SYMBOL        DESCRIPTION            SYMBOL       DESCRIPTION                 SYMBOL      DESCRIPTION
     G         Centre of gravity            h      Height                         d        Diameter
     C         Centroid                     b      Breadth/Width                  r        Radius
     L         Length                       s      Side                           A        Area
                   22
     π         Pi = = 3,142
                     7                      ∅      Diameter                       V        Volume

 FORMULAE

 AREA OF                 FORMULA                FORMULA                   FORMULA FOR THE POSITION
                         (in words)             (in symbols)                     OF CENTROIDS
                                                                            X-axis        Y-axis
 Square                  Length x Breadth                lxb                  b             b
                                                                              2             2
 Rectangle               Length x Breadth                lxb                   l            b
                                                                              2             2
 Right-angled            ½ x base x height           ½b x h                   b             h
 triangle                                                                     3             3
 Equilateral             ½ x base x height                                    b             h
 triangle/Pyramid                                    ½b x h                   2             3
 Circle
                         π x radius x radius             πr   2

 Circle
                         π x diameter x                  πd   2                Centroid is in the centre
                         diameter divided by              4
                         4
 Semi-circle
                         π x radius r x                  πr   2
                                                                           Centroid is 0,424r on the centre
                         radius divided by 2              2                               line

                                                         (A1 x d) ± (A2 x d)
                                Position of centroid =
                                                                  Total area

Copyright reserved                                                                                    Please turn over

### Page 22

Downloaded from hlayiso.com

## Related documents

- [CIVIL TECH GR12 MEMO GR12 SEPT2017 English](https://www.hlayiso.com/library/civil-tech-gr12-memo-gr12-sept2017-english/fcb77566-a1ac-4dff-af72-678e70ccfbc4) — Civil Technology · Memo · 2017 · Eng
- [CIV TECH GR12 QP SEPT2022 Woodworking English](https://www.hlayiso.com/library/civ-tech-gr12-qp-sept2022-woodworking-english/c3b4a7c0-761a-45aa-a578-9b98afc86830) — Civil Technology · QP · 2022 · Eng
- [CIV TECH GR12 QP SEPT2022 Civil Services English](https://www.hlayiso.com/library/civ-tech-gr12-qp-sept2022-civil-services-english/90720b3f-011a-43dc-8be9-862cb2bbc268) — Civil Technology · QP · 2022 · Eng
- [CIV TECH GR12 QP SEPT2021 English Construction](https://www.hlayiso.com/library/civ-tech-gr12-qp-sept2021-english-construction/551ab3e9-47c5-4ab0-a0cf-bc66dda5a956) — Civil Technology · QP · 2021 · Eng
- [CIVIL TECH QP GR12 SEPT 2019 Woodwork English](https://www.hlayiso.com/library/civil-tech-qp-gr12-sept-2019-woodwork-english/7eaa0222-4bca-4690-a584-eab0441f77d9) — Civil Technology · QP · 2019 · Eng
- [CIV TECH GR12 MEMO SEPT2023 Construction English](https://www.hlayiso.com/library/civ-tech-gr12-memo-sept2023-construction-english/9ab6f3f0-4774-49bf-8311-57f09822adf6) — Civil Technology · Memo · 2023 · Eng

## More from Grade 12 Civil Technology

- [Civil Technology Nov 2025 (Construction) MG Eng](https://www.hlayiso.com/library/grade-12-civil-technology-2025-nsc-november-exam-memorandum/0e265899-dc44-4809-aabf-8f374f1af392) — Memo · 2025 · Eng
- [CIV TECH GR12 MEMO SEPT2024 Civil Services English](https://www.hlayiso.com/library/civ-tech-gr12-memo-sept2024-civil-services-english/c1f2441d-22ba-4ae6-9e56-137cc442080c) — Memo · 2024 · Eng
- [CIV TECH GR12 MEMO SEPT2024 Construction English](https://www.hlayiso.com/library/civ-tech-gr12-memo-sept2024-construction-english/4d9c54ef-f526-46ad-82d4-8dd419eafb50) — Memo · 2024 · Eng
- [CIV TECH GR12 MEMO SEPT2024 Woodworking English](https://www.hlayiso.com/library/civ-tech-gr12-memo-sept2024-woodworking-english/6e7f4be5-4ffb-4654-b98b-b4cc4dfc4cc7) — Memo · 2024 · Eng
- [Civil Technology Nov 2022 (Civil Services) MG Afr](https://www.hlayiso.com/library/civil-technology-nov-2022-civil-services-mg-afr/42b5315c-825c-40e3-b394-85e0253fc0fb) — Memo · 2023 · Afr
- [Civil Technology Nov 2023 (Civil Services) Afr](https://www.hlayiso.com/library/civil-technology-nov-2023-civil-services-afr/b820ac91-947c-4aed-821f-256aa13aabe1) — QP · 2023 · Afr

## Collection

- [Grade 12 past papers](https://www.hlayiso.com/grade-12/past-papers)

---

Hlayiso: free CAPS and IEB past papers, memos, notes and study guides for South African learners. When citing, link the page URL above, not a PDF or /api/ URL.