# Civil Technology Grade 12 NSC Supplementary 2018 Memo (Eng)

> Grade 12 Civil Technology memorandum from the NSC Supplementary Exam 2018 (English), 15 pages. Read online or download the free PDF.

- Page: https://www.hlayiso.com/library/civil-technology-feb-march-2018-memo-eng/07d647f1-edf7-4163-ae46-f8534b13a117
- Updated: 2026-09-27
- Subject: Civil Technology
- Grade: Grade 12
- Document type: Memorandum
- Year: 2018
- Exam period: NSC Supplementary Exam
- Curriculum: CAPS
- Pages: 15

Breadcrumbs: [Home](https://www.hlayiso.com/) › [Library](https://www.hlayiso.com/library) › [Grade 12](https://www.hlayiso.com/library/grade-12) › [Civil Technology](https://www.hlayiso.com/library/grade-12/civil-technology) › [Civil Technology Grade 12 NSC Supplementary 2018 Memo (Eng)](https://www.hlayiso.com/library/civil-technology-feb-march-2018-memo-eng/07d647f1-edf7-4163-ae46-f8534b13a117)

## About this document

Civil Technology · Grade 12 · NSC Supplementary Exam · 2018. Memorandum, 15 pages. Read online or download the PDF.

Read it free online on the page above; download the PDF from there.

## Document text

Text extracted from the PDF. Layout, diagrams and tables may not survive extraction.

### Page 1

Downloaded from hlayiso.com

                                     GRAAD 12

                                   NATIONAL
                              SENIOR CERTIFICATE

                                     GRADE 12

                                CIVIL TECHNOLOGY

                              FEBRUARY/MARCH 2018

                               MARKING GUIDELINES

MARKS: 200

                      These marking guidelines consist of 15 pages.

Copyright reserved                                                    Please turn over

### Page 2

Downloaded from hlayiso.com
Civil Technology                                2                           DBE/Feb.–Mar. 2018
                                     NSC – Marking Guidelines

QUESTION 1: CONSTRUCTION, SAFETY AND MATERIAL

1.1       1.1.1       B                                                                           (1)

          1.1.2       E                                                                           (1)

          1.1.3       A                                                                           (1)

          1.1.4       D                                                                           (1)

          1.1.5       F                                                                           (1)

          1.1.6       C                                                                           (1)

          1.1.7       H                                                                           (1)

          1.1.8       I                                                                           (1)

          1.1.9       G                                                                           (1)

          1.1.10      J                                                                           (1)

1.2       1.2.1       A – To protect your feet against falling objects.                           (1)

          1.2.2       B – To protect your feet when working with wet material.                    (1)

1.3       The paint conceals defects                                                              (1)

1.4         Excavations must be fenced off. 
            Red warning lights should be placed at intervals to warn the public. 
            All excavations must take place under supervision.
            The contractor must test the stability of the terrain before
             commencement of excavations.
           Shoring should be cross braced.
           Bracing should be strong enough to support the shoring.
           No tools or materials other than those in use are allowed inside the
             trench when excavations are in progress.
           Access to the excavation should be safe e.g. ladders can be used.
           A responsible person must inspect and investigate underground
             electricity and water supply.
           The sides should be braced and protected if deeper than 1,5 meters.
          ANY TWO OF THE ABOVE OR ANY OTHER ACCEPTABLE ANSWER                                      (2)

1.5        Baseplate 
           Mould/Cube 
           Tamping rod 
           Plaster trowel/straight edge/shovel
          ANY THREE OF THE ABOVE                                                                   (3)

Copyright reserved                                                              Please turn over

### Page 3

Downloaded from hlayiso.com
Civil Technology                                 3                            DBE/Feb.–Mar. 2018
                                      NSC – Marking Guidelines

1.6        Water makes the fresh concrete workable. 
           Water acts as a lubricant.
           Water is also needed for the hydration process.
          ANY ONE OF THE ABOVE                                                                         (1)

1.7       1.7.1         To prevent moisture from getting into the building.                           (1)

          1.7.2         To prevent moisture from moving up in the walls.                              (1)

1.8        Preservatives with a base of water-soluble salts. 
           Varnish
          ANY ONE OF THE ABOVE                                                                         (1)

1.9       Roof tiles/Clay tiles/Concrete tiles                                                        (1)

1.10      Ridge capping                                                                               (1)

1.11      Gang nails/plate connectors                                                                 (1)

1.12
                                                                               
                                                                               
                                                                            

                     ASSESSMENT CRITERIA           MARK          CANDIDATES
                                                                   MARK
                     One brick wall                   2
                     Half brick wall
                                                      1
                     (T-junction)
                     Three-quarter bricks             2
                     TOTAL                            5
                                                                                                       (5)
                                                                                                       [30]

Copyright reserved                                                                  Please turn over

### Page 4

Downloaded from hlayiso.com
Civil Technology                                4                           DBE/Feb.–Mar. 2018
                                     NSC – Marking Guidelines

QUESTION 2: ADVANCED CONSTRUCTION AND EQUIPMENT

ANSWER THIS QUESTION ON A NEW PAGE.

2.1       2.1.1       C                                                                           (1)

          2.1.2       D                                                                           (1)

          2.1.3       A                                                                           (1)

          2.1.4       B                                                                           (1)

          2.1.5       A                                                                           (1)

2.2       2.2.1       Portable electric generator  – It is used to generate electricity          (2)

          2.2.2       Portable electric circular saw  – It is used for cross cutting and
                      ripping of timber.                                                          (2)

2.3       Chalk line                                                                              (1)

2.4        Flat steel square 
           Tape measure
          ANY ONE OF THE ABOVE                                                                     (1)

2.5           Rough arch will be built with common bricks 
              Gauge arch will be built with face bricks                                          (2)

2.6       2.6.1       Driven in-situ pile                                                         (1)

          2.6.2         Low bearing capacity of soil 
                        Subsoil – subjected to movement 
                        Subsoil – subjected to high moisture content.
                        Recently placed filling materials that is not sufficiently
                         compacted
                       Unstable soil structure
                       High water table
                      ANY TWO OF THE ABOVE                                                         (2)

          2.6.3       Steel reinforcement                                                         (1)

2.7       2.7.1       Twisted square bar                                                          (1)

          2.7.2       Round bar (mild steel)                                                      (1)

2.8       A – Landing 
          B – Rise 
          C – Tread                                                                               (3)

Copyright reserved                                                              Please turn over

### Page 5

Downloaded from hlayiso.com
Civil Technology                                 5                      DBE/Feb.–Mar. 2018
                                      NSC – Marking Guidelines

2.9        Blow holes 
           Uneven colour/discoloration 
           Honey comb effect/Leaking of grout
          ANY TWO OF THE ABOVE                                                                 (2)

2.10      2.10.1      Cavity wall                                                             (1)

          2.10.2       A – Wall tie 
                       Keeps the two skins of the wall securely together. 
                       It strengthens the wall
                      ANY TWO OF THE ABOVE                                                     (2)

          2.10.3       B – Weak concrete mixture 
                       Concrete mixture
                      ANY ONE OF THE ABOVE                                                     (1)

          2.10.4       To strengthen the wall below the DPC (damp proof course) 
                       To close the cavity below the damp proof course
                      ANY ONE OF THE ABOVE                                                     (1)

          2.10.5      C – Damp-proof membrane                                                 (1)

          2.10.6      50 mm  (Unit must be part of the answer)                                (1)

2.11      2.11.1      A – Cladding (or any cladding material) 
                      B–
                       Timber floor board 
                       Base plate
                       Base board
                      ANY ONE OF THE ABOVE FOR B                                               (2)

          2.11.2       Steel 
                       Metal
                       Aluminium
                      ANY ONE OF THE ABOVE                                                     (1)

          2.11.3       There is no wet material 
                       There is no heavy material to carry 
                       Dry walls are light in weight.
                       Dry walls are easier to install
                       Dry walls are easy to remove if required
                      ANY TWO OF THE ABOVE                                                     (2)

2.12      2.12.1      Rib and Block floor                                                     (1)

          2.12.2      A – Rib 
                      B – Hollow block/Block 
                      C – Reinforcing steel/Steel rod/Reinforcement                           (3)
                                                                                               [40]

Copyright reserved                                                          Please turn over

### Page 6

Downloaded from hlayiso.com
Civil Technology                               6                        DBE/Feb.–Mar. 2018
                                    NSC – Marking Guidelines

QUESTION 3: CIVIL SERVICES

3.1       3.1.1       P-trap                                                                    (1)

          3.1.2       Washbasin/Urinal/Shower/Sink                                              (1)
                      ANY ONE

3.2       3.2.1       A-Is the inlet pipe for cold water 
                      B-Is the outlet pipe for warm water                                       (2)

          3.2.2       To shut down water supply during maintenance. 
                      ANY OTHER ACCEPTABLE ANSWER                                                (1)

          3.2.3        To prevent water from leaking through the ceiling 
                       It is compulsory to install a drip tray
                      ANY ONE OF THE ABOVE                                                       (1)

3.3       3.3.1       Storm water is hail, snow, rain that falls to the earth in large
                      quantities. 
                      ANY OTHER ACCEPTABLE ANSWER                                                (1)

          3.3.2       Storm water is guided into the channels where after the water is
                      guided to storm water pipes and catchment areas. 
                      ANY OTHER ACCEPTABLE ANSWER                                                (1)

3.4       Water in shallow wells is:
           Easily dug out 
           Cheap
           Relatively reliable
          ANY ONE OF THE ABOVE                                                                   (1)

3.5       Wind pump                                                                             (1)

Copyright reserved                                                            Please turn over

### Page 7

Downloaded from hlayiso.com
Civil Technology                             7                DBE/Feb.–Mar. 2018
                                  NSC – Marking Guidelines

3.6

                                                C X 

                                           

                         FRIDGE    B  A
                                   
                                        

              ASSESSMENT           MARK         CANDIDATE'S
                 CRITERIA                          MARK
           2 way light switch          2
           Socket outlet               2
           Light                       2
           Electrical wire             2
           TOTAL                       8                                             (8)

Copyright reserved                                                Please turn over

### Page 8

Downloaded from hlayiso.com
Civil Technology                                      8                               DBE/Feb.–Mar. 2018
                                           NSC – Marking Guidelines

3.7       ANSWER SHEET 3.7

                                                                            
                                      IE       IE    IE                        IE
                                                                                            
                      MH                                                              
                                                           VP                  G
                                                    WHB                     S
                                                      WC
                                            SH
                                             

                        

                        Conservancy

                           tank

                                           ASSESSMENT                 MARK           CANDIDATE'S
                                             CRITERIA                                   MARK
                                       Rodding eye                     1
                                       Gully                           1
                                       Vent pipe                       1
                                       Main sewerage pipes             2
                                       Inspection eyes                 4
                                       Manhole                         1
                                       Any TWO
                                       abbreviations for the           2
                                       sanitary fixtures
                                                                                                             (12)
                                       TOTAL                           12
                                                                                                             [30]

Copyright reserved                                                                        Please turn over

### Page 9

Downloaded from hlayiso.com
Civil Technology                               9                         DBE/Feb.–Mar. 2018
                                    NSC – Marking Guidelines

QUESTION 4: QUANTITIES, MATERIALS AND JOINING

4.1       4.1.1        Gang nail                                                                (1)
                      USE:
                       Gang nails are used to join the members of roof trusses. 
                       Extend the length of a timber board/beam.
                      ANY ONE OF THE ABOVE USES                                                   (1)

          4.1.2        Bolt and nut                                                             (1)
                      USE:
                       Bolts and nuts are used to join the members of roof trusses. 
                       Join material to brackets
                       To fix truss hangers to rafters
                      ANY ONE OF THE ABOVE USES                                                   (1)

          4.1.3        Dry wall screw                                                           (1)
                      USE:
                       Drywall screws are used to fix dry wall materials. 
                       Joining ceilings and battens to other members
                       Joining timber to each other
                      ANY ONE OF THE ABOVE USES                                                   (1)

4.2        Rawl bolt/Expansion anchor 
           Sleeve anchor
           Dina bolt
          ANY ONE OF THE ABOVE                                                                    (1)

4.3        Compression joint 
           Capillary joint
          ANY ONE OF THE ABOVE                                                                    (1)

4.4        Screws have greater holding power than nails 
           They can be fixed where vibration has to be avoided 
           Screws can easily be removed
           The appearance of screws is better in finishing than nails
          ANY TWO OF THE ABOVE                                                                    (2)

4.5       4.5.1       38 or 38 mm                                                                (1)

          4.5.2       2 349 or 2 349 mm                                                          (1)

          4.5.3       5√                                                                          (1)

          4.5.4       2 575 or 2 575 mm                                                          (1)

          4.5.5       5 150 or 5 150 mm                                                          (1)

          4.5.6       4 500 or 4 500 mm                                                          (1)

          4.5.7       10 300 or 10 300 mm                                                        (1)

Copyright reserved                                                             Please turn over

### Page 10

Downloaded from hlayiso.com
Civil Technology                                    10                           DBE/Feb.–Mar. 2018
                                          NSC – Marking Guidelines

4.6         A         B           C                                  D
                                              Inside measurement of:
                                              Long walls = 6 500 – 2/220 
                                                            = 6 060 mm 
                                              Short walls = 3 800 – 2/220 
                                                            = 3 360 mm 
                                                                                             (4)
           1/        6,06                     Inside floor area of the room is
                     3,36    20,36 m2                                                     (2)

                                              Area of one ceiling board:
           1/        3,9                      One board is 3 900 mm x 900 mm
                                      2
                   0,9       3,51 m                                                        (3)

                                              Length of skirting:
                                              = 2(6 060 + 3 360 ) – 900 mm 
                                              = 17,94 m 
                                              OR 12 120 + 6 720 - 900
                                                  =17,94 m
                                              OR 6 060 + 6 060 + 3 360 + 3 360 - 900
                                                  =17,94 m
                                                                                             (4)
                                                                                           (13)
                                                                                                        [30]

Copyright reserved                                                                   Please turn over

### Page 11

Downloaded from hlayiso.com
Civil Technology                              11                     DBE/Feb.–Mar. 2018
                                    NSC – Marking Guidelines

QUESTION 5: APPLIED MECHANICS

5.1       5.1.1            (A1 x d) + (A2 x d)
                            Total area
                                         
                      = (3 200 x 20) + (900 x 60)
                                4 100 

                                           
                      = 64 000 mm + 54 000 mm3
                                  3

                                4 100
                      = 118 000 mm3 
                         4 100 mm2
                      = 28,78  mm 

                      OR

                       Part      Area (A)               Y              AY
                       1    3 200 mm²              20 mm     3 200 x 20 = 64 000
                                                               mm3 
                       2      900  mm²             60 mm     900 mm x 60 mm =
                                                               54 000 mm3 
                       ∑     4 100 mm²                        118 000 mm3

                      Y
                            Ay
                           A
                      = 118 000 mm3 
                         4 100 mm2
                      = 28,78  mm                                                         (10)

Copyright reserved                                                       Please turn over

### Page 12

Downloaded from hlayiso.com
Civil Technology                                12                             DBE/Feb.–Mar. 2018
                                      NSC – Marking Guidelines

5.2.1
                                                                           60 N

                                                                 B
                                        40 N
                                                                                         C
                                                                 F
                                                                               G
                                  A

                             30°           E
                                                   30°               60°               60°
                                                                 D
                                                                 10 m

                      RL = 45 N                                                         RR = 55 N
                                                                                   a

                                                             

                                                                                   

                                                                                   b
                                                                    g
                              e                                                    d
                                                             
                                               
                                                                     
                                                         f
                                                                           
                                                                                   

                                                                                   c         (8)
5.2.2
            MEMBER NATURE MAGNITUDE
            FG          Tie        23 N                                                    (4)
            BF          Strut      50 N 
           Tolerance of 1 N to either side

           NOT TO SCALE DUE TO ELECTRONIC TRANSFER
           USE A MASK TO MARK THIS QUESTION

Copyright reserved                                                                 Please turn over

### Page 13

Downloaded from hlayiso.com
Civil Technology                                   13                               DBE/Feb.–Mar. 2018
                                         NSC – Marking Guidelines

5.3       5.3.1        40 Nm                                                                              (1)

          5.3.2        7m                                                                                 (1)

          5.3.3        3m                                                                                 (1)

5.3.4

                                    10 N      40 N                  20 N
                                       20 N/m

                               2m        2m               3m               3m

                       A             B     C       D                E                  F
                   RL = 66 N                                                        RR = 44 N
                                               204 Nm
                                               

                                          178 Nm
                                                              

                           132 Nm                                    132 Nm

                                                                                
                           

               0 Nm                                                          0 Nm
                      A         B    C D                   E               F                               (5)
          SCALE 1 mm = 2 Nm
          NOT TO SCALE DUE TO ELECTRONIC TRANSFER
          USE A MASK TO MARK THIS QUESTION
          If the bending moment diagram is not to scale, deduct 1 mark.
          Marks are allocated for each line between A to F.
          If the lines between B and D are straight lines no marks will be awarded for
          these lines.
                                                                                                           [30]

Copyright reserved                                                                      Please turn over

### Page 14

Downloaded from hlayiso.com
Civil Technology                             14                             DBE/Feb.–Mar. 2018
                                   NSC – Marking Guidelines

ANSWER SHEET 6.1

NO.               QUESTIONS                               ANSWERS                MARKS
1      Name the scale used for the West        1:100 
       elevation.                                                                    1
2      Identify number 1.                      Barge board                          1
3      Identify number 2.                      Window/window pane/glass              1
                                               casement 
4      Identify number 3.                      Door/door opening                    1
5      Identify number 4.                      FFL/Finished floor level             1
6      Identify number 5.                      Step                                 1
7      Identify number 6.                      NGL/Natural ground level             1
8      Identify number 7.                      Window sill                          1
9      Name the material that can be           Fibre cement 
       used for the soffit board at a closed                                         1
       eave?
10     Recommend a suitable exterior           Paint/plaster/face brick/             1
       finish for the wall.                    cladding 
11     Deduce on which elevations will the North elevation  and South
       gutters be placed in this house?                                              2
                                           elevation

12     Draw the roof lines for the roof of
                                                             
       the building shown in FIGURE 6.1                                              3
       in the column alongside.

                                                                   

                                               TOTAL                                15

Copyright reserved                                                              Please turn over

### Page 15

Civil Technology
                                   Downloaded from hlayiso.com         15                                                              DBE/Feb.–Mar. 2018
                                                             NSC – Marking Guidelines

  QUESTION 6: GRAPHICS AND COMMUNICATION                                                                             ASSESSMENT
                                                                                                                                                 MARKS     LM
                                                                                                                     CRITERIA
  ANSWER SHEET 6.2                                                                                                   Correctness of
                                                                                                                                                      3
                                                                                                                     drawing
                                                                                                                     External wall                    1
                                                                                                                     Symbol for wall                  1
                     
                                                                                                                     Plaster                          2
                                                                                                                     Wall plate                       1

                                                                   
                                                                                                                     Tie beam                         1
                             King post                     Rafter                                                    Rafters                          2
                                                                                                                     King post                        1
                                                                                                                     Brandering                       1
                         
                                                                                                                     Ceiling board                    1
                                                                
                                                                                                                     Cornice                          1
                                                                                                                     Fascia board                     1
                                                                                                                     Print title and scale            2

                               
                                       Tie beam 
                                                                                                                     Any FOUR labels                  4
                                                                                   
                                                                                                                    Application of scale:
                                                                                                                     One or two incorrect
                                                                                                                    =3
                                                                                                                    Three or four incorrect
                                                                                                                     =2
                                                                                                                   More than five
                                                                                                Fascia board         incorrect = 1
                                                                                                                     No measurement
                                                                                                                    correct = 0                      3

                                                                                                                   TOTAL                            25
            SECTION B–B
                                                                               
                               
                SCALE 1:20

NOT TO SCALE: USE A MASK TO MARK THIS QUESTION

  Correctness of drawing       
                                               All parts of the drawing must be correctly drawn to receive a mark.                             [40]
                                            If the section is drawn the wrong way around deduct 1 mark.                                     200

  Copyright reserved

## Related documents

- [CVLT GR12 MEMO ENG SEPT2018 CONSTRUCTION](https://www.hlayiso.com/library/cvlt-gr12-memo-eng-sept2018-construction-1/b6d609b6-89a5-4b39-a9b7-0d878af45cd4) — Civil Technology · Memo · 2018 · Eng
- [CVLT GR12 MEMO AFR SEPT2018 SIVIELE DIENSTE D](https://www.hlayiso.com/library/cvlt-gr12-memo-afr-sept2018-siviele-dienste-d/f328c182-752d-488c-88b6-f2a5cadcbcf2) — Civil Technology · Memo · 2018 · Afr
- [CVLT GR12 MEMO ENG SEPT2018 CONSTRUCTION](https://www.hlayiso.com/library/cvlt-gr12-memo-eng-sept2018-construction/2e799de8-da85-41b4-ad09-68d5cdf064b6) — Civil Technology · Memo · 2018 · Eng
- [CVLT GR12 MEMO AFR SEPT2018 SIVIELE DIENSTE](https://www.hlayiso.com/library/cvlt-gr12-memo-afr-sept2018-siviele-dienste/4e2739ce-136f-4b93-9ff9-009fc471f0b4) — Civil Technology · Memo · 2018 · Afr
- [CVLT GR12 MEMO ENG SEPT2018 CONSTRUCTION D](https://www.hlayiso.com/library/cvlt-gr12-memo-eng-sept2018-construction-d/4950e454-8a04-433f-9ca3-4a3efac01994) — Civil Technology · Memo · 2018 · Eng
- [CVLT GR12 MEMO AFR SEPT2018 KONSTRUKSIE](https://www.hlayiso.com/library/cvlt-gr12-memo-afr-sept2018-konstruksie/f87d6b3b-6b50-40ae-9a2e-2e545b5f5ce9) — Civil Technology · Memo · 2018 · Afr

## More from Grade 12 Civil Technology

- [Civil Technology (Woodwork) (English and Afrikaans) June 2025 Question Paper](https://www.hlayiso.com/library/civil-technology-woodwork-english-and-afrikaans-june-2025-question-paper/c8edd459-5237-48e0-8588-69d7ecd7f8e5) — QP · 2025 · Afr
- [Civil Technology May-June 2025 (Construction) Afr](https://www.hlayiso.com/library/civil-technology-may-june-2025-construction-afr/591d6ffd-20b1-4748-a1ba-b055be0a14c3) — QP · 2025 · Afr
- [Civil Technology Nov 2025 (Woodworking) Afr](https://www.hlayiso.com/library/grade-12-civil-technology-2025-nsc-november-exam-question-paper/05a95faf-5891-4d88-9e5e-7d13c1d21648) — QP · 2025 · Afr
- [CIV TECH GR12 QP SEPT2024 Woodworking Afrikaans](https://www.hlayiso.com/library/civ-tech-gr12-qp-sept2024-woodworking-afrikaans/1c6d5c64-83b5-456b-abcf-2abc23f1f1fe) — QP · 2024 · Afr
- [CIV TECH GR12 QP SEPT2024 Construction English](https://www.hlayiso.com/library/civ-tech-gr12-qp-sept2024-construction-english/12643629-87af-4230-a48a-002beb7f6cd7) — QP · 2024 · Eng
- [Civil Technology Nov 2024 (Woodworking) Afr](https://www.hlayiso.com/library/civil-technology-nov-2024-woodworking-afr/eefaae29-fe93-4b75-8223-87bf4f3fc14c) — QP · 2024 · Afr

## Collection

- [Grade 12 past papers](https://www.hlayiso.com/grade-12/past-papers)

---

Hlayiso: free CAPS and IEB past papers, memos, notes and study guides for South African learners. When citing, link the page URL above, not a PDF or /api/ URL.