# Civil Technology Grade 12 NSC June 2019 Memo (English)

> Grade 12 Civil Technology memorandum from the NSC June Exam 2019 (English), 19 pages. Read online or download the free PDF.

- Page: https://www.hlayiso.com/library/civil-technology-may-june-2019-construction-memo-eng/1d4215a2-ff49-4e5b-be04-ad24d791de66
- Updated: 2026-09-27
- Subject: Civil Technology
- Grade: Grade 12
- Document type: Memorandum
- Year: 2019
- Exam period: NSC June Exam
- Curriculum: CAPS
- Pages: 19

Breadcrumbs: [Home](https://www.hlayiso.com/) › [Library](https://www.hlayiso.com/library) › [Grade 12](https://www.hlayiso.com/library/grade-12) › [Civil Technology](https://www.hlayiso.com/library/grade-12/civil-technology) › [Civil Technology Grade 12 NSC June 2019 Memo (English)](https://www.hlayiso.com/library/civil-technology-may-june-2019-construction-memo-eng/1d4215a2-ff49-4e5b-be04-ad24d791de66)

## About this document

Civil Technology · Grade 12 · NSC June Exam · 2019. Memorandum, 19 pages. Read online or download the PDF.

Read it free online on the page above; download the PDF from there.

## Document text

Text extracted from the PDF. Layout, diagrams and tables may not survive extraction.

### Page 1

Downloaded from hlayiso.com

              SENIOR CERTIFICATE EXAMINATION/
          NATIONAL SENIOR CERTIFICATE EXAMINATION

                       CIVIL TECHNOLOGY: CONSTRUCTION

                                          2019

                                MARKING GUIDELINES

                                                                        MARKS: 200

                      These marking guidelines consist of 19 pages.

Copyright reserved                                                    Please turn over

### Page 2

Downloaded from hlayiso.com
Civil Technology: Construction                2                                DBE/2019
                                  SC/NSC – Marking Guidelines

QUESTION 1: OHSA, SAFETY, MATERIALS, TOOLS, EQUIPMENT AND JOINING
            (GENERIC)

1.1       1.1.1        G                                                                    (1)

          1.1.2        E                                                                    (1)

          1.1.3        A                                                                    (1)

          1.1.4        C                                                                    (1)

          1.1.5        D                                                                    (1)

1.2       • When heavy materials/loads are not lifted/lowered/handled correctly. 
          • Wrong posture when lifting materials.
          • Not using safety apparel.
          ANY ONE OF THE ABOVE                                                               (1)

1.3        
          1 : 4 OR 76°                                                                       (2)

1.4       •  A qualified person must operate the device. 
          •  The device must never be overloaded. 
          •  The gates and wire components of the lift of the hoisting device must be
             at least 1 980 mm high.
          • The gates must be shut when the device is being used.
          • Emergency brake mechanisms must be installed.
          • Safety measures must be displayed inside the cage.
          • Inspections and maintenance work should be carried out regularly
             (at least six-monthly) by qualified persons.
          • Overhead protection must be provided to protect workers from falling
             objects.
          • When material or equipment is being hoisted, it must be stacked firmly
             and correctly, and secured properly.
          • The hoist must be inspected weekly by a qualified person.
          ANY TWO OF THE ABOVE                                                               (2)

          1.5.1        A = Laser level 
                       B = Dumpy level                                                      (2)

Copyright reserved                                                        Please turn over

### Page 3

Downloaded from hlayiso.com
Civil Technology: Construction                     3                                    DBE/2019
                                       SC/NSC – Marking Guidelines

          1.5.2                    Laser level (A)                      Dumpy level (B)
                         To determine levels when:                   The dumpy level is used
                     •   installing ceilings and floor tiles.       when:
                     •   installing chair rails for example in •     determining differences
                         a dining room.                              between      levels    and
                     •   installing receptacles for power            vertical           heights,
                         inside a building during                    especially over longer
                         construction.                               distances. 
                     •   hanging pictures.                      •    determining levels and
                     •   excavating for new buildings.               slopes.
                     •   aligning and levelling floors.         •    setting out buildings.
                     •   when installing doors and windows. •        transferring levels and
                     •   aligning shelves and cabinets.              heights.
                     •   levelling post and beams on decks,     •    determining/measuring
                         fences and porches.                          the distances between
                     •   setting out buildings on a site.             two points.
                     •   aligning fences, post and decks.
                     •   determining gradient/slope for
                         drainage and irrigation.
                     •   establishing contours for farming or
                         drainage.

                     • To determine levels and slopes
                       when installing sewer pipes.
                       ANY ONE IN EACH COLUMN ABOVE                                                   (2)

1.6       1.6.1          Rawl bolt                                                                   (1)

          1.6.2          A – Drill a hole of the required diameter and depth. 
                         B – Remove debris and thoroughly clean the hole with a brush or
                             by blowing into it. 
                         C – Remove the bolt and washer, insert the sleeve/shield into the
                             hole and align the fixture (for example base plate, etc…) with
                             the hole. 
                         D – Insert the bolt with washer through the fixture and tighten to the
                             recommended torque.                                                     (4)

          1.6.3          Rawl bolts:
                         • are stronger fasteners than a screw with a plastic plug. 
                         • are designed to resist pull-out failure.
                         • have excellent mechanical properties such as tensile and yield
                            stress.
                         • have excellent carrying capacity.
                         • have excellent tolerance to variance in the hole size.
                         ANY ONE OF THE ABOVE                                                         (1)
                                                                                                      [20]

Copyright reserved                                                                 Please turn over

### Page 4

Downloaded from hlayiso.com
Civil Technology: Construction                4                                    DBE/2019
                                  SC/NSC – Marking Guidelines

QUESTION 2: GRAPHICS AS MEANS OF COMMUNICATION (GENERIC)

ANSWER SHEET 2

NO.                   QUESTIONS                                 ANSWERS                      MARKS

1       Identify the elevation shown in
                                                Eastern/East elevation/East                     1
        FIGURE A.
                                                                                                 1
2       Name the scale of FIGURE B.             1 : 100 

                                                                                                 1
3       Identify number 1.                      Barge board 

                                                                                                 1
4       Identify number 2.                      Roof overhang/Eave/Open eave 

5       Recommend a suitable finish for         Plaster/Paint/Face brick/Tiles/
        number 3.                                                                                1
                                                Cladding 

6       What is indicated by number 4?          Door/Entrance door/Door opening                 1

7       Identify the drawing symbol indicated
                                                Finished floor level/FFL 
        by number 5.                                                                             1

8       Identify the drawing symbol indicated
                                                Natural ground level/NGL                        1
        by number 6.

9       What is indicated by number 7?          Step                                            1

10      Give the date on which the building
                                                                                                 1
        plan was printed.                       2019/06/16 

                                                                                                 1
11      Who checked the building plan?          P Blade 

12      Name the electrical drawing symbol      Two-way switch 
        in the column for the notes in
                                                                                                 1
        FIGURE 2 that must be placed at a
        staircase.
                                                                 DO NOT MARK
                                                                 THESE QUESTIONS
13      Name the electrical feature in the
        column for the notes in FIGURE 2
                                                Wall light                                      1
        that must be placed at the entrance
        door of the house.

Copyright reserved                                                            Please turn over

### Page 5

Downloaded from hlayiso.com
Civil Technology: Construction                  5                                     DBE/2019
                                    SC/NSC – Marking Guidelines

14      Identify the type of roof that is
        used on the building in                Gable roof                                          1
        FIGURE A.

15      Explain the purpose of number 1.       To cover ends of purlins/battens/fixed to
                                               the purlins/battens for a neat appearance.           1
                                               To finish of the gable end of the roof. 

16      Who is the owner of this house?        Mr H Smith                                          1

17      In which street is the proposed
                                               Jupiter street                                      1
        dwelling situated?

18      Identify number 8.                     Rainwater down pipe/Downpipe                        1

19                                             To wash your face/Body 
        What is the sanitary fitting           Brush your teeth                                     1
        indicated by number 9 used for?        Wash your hands
                                               Washing/Rinsing

20      Recommend an alternative
        sanitary fitting to replace
                                               Bath                                                1
        number 10 that will serve a similar
        purpose.

21      Explain the purpose of number 11       Landing to serve as resting place or
                                                                                                    1
        as indicated on the staircase.         change of direction of staircase. 

22                                             Emergency light/External light
        What is indicated by number 13?                                                             1
                                               Thickness of wall/110 mm 

23      What is indicated by number 15?        North- symbol/direction/point                       1

24      Deduce the height of window 1
                                               1,8 m or 1 800 mm                                   1
        from the window schedule.

25      Deduce the width of window 2
                                               2,4 m or 2 400 mm                                   1
        from the window schedule.

26      Name the elevations of the
        building on which the staircase is     Western/West elevation/West                         2
        situated.                              Southern/South elevation/South 

Copyright reserved                                                               Please turn over

### Page 6

Downloaded from hlayiso.com
Civil Technology: Construction                6                                   DBE/2019
                                  SC/NSC – Marking Guidelines

27                                           12 – One way light switch single pole/
        Differentiate between the
        electrical symbols indicated by      lever                                             2
        numbers 12 and 14.                   14 – One way light switch double pole/
                                             lever 

28      Recommend a suitable floor           Tiles/Novilon/Carpets/Laminated
                                                                                                1
        covering for the lounge.             flooring/Wooden flooring.

29      Calculate the area of the lounge     6 m  x 3 m  = 18 m² 
        in m². Show ALL calculations.
                                             OR                                                 3
                                             6 000 mm x 3 000 mm = 18 m²

30      Calculate the perimeter of the       (220 + 3 000 + 110 + 3 000 + 220)  x 2 
        building. Show ALL calculations.
                                             = 6 550 x 2
                                             =13 100 mm 
                                             (220 + 6 000 + 220)  x 2 
                                             = 6 440 x 2                                        7
                                             = 12 880 mm 
                                             13 100 + 12 880
                                             = 25 980 mm  OR
                                             = 25,98 m

                                             TOTAL:                                             40

Copyright reserved                                                           Please turn over

### Page 7

Downloaded from hlayiso.com
Civil Technology: Construction                 7                             DBE/2019
                                   SC/NSC – Marking Guidelines

QUESTION 3: ROOFS, STAIRCASES AND JOINING (SPECIFIC)

3.1       17°                                                                            (1)

3.2       76 mm  x 50 mm  OR 76 mm x 76 mm                                              (2)

3.3       650 mm                                                                         (1)

3.4       Tilting batten/Foot batten                                                     (1)

3.5        A - King post 
           B - Rafter 
           C - Strut 
           D - Queen post 
           E - Tie beam                                                                  (5)

3.6

                      Any TWO labels  

                                                       Rafter
                                                                           Wall

                                                                       
 Wall plate
                                             Span 
                            
               Wall
                                                 
                                      Proportion
          IF A LINE DIAGRAM IS DRAWN MINUS ONE MARK FOR PROPORTION
           ASSESSMENT CRITERIA                            MARK
           Span                                             1
           Walls                                            2
           Wall plate                                       1
           Rafter                                           1
           Any TWO labels                                   2
           Proportion                                       1
                                              TOTAL:        8
                                                                                          (8)

3.7        • At least 300 mm to 600 mm for concrete tile. 
           • The galvanised strap should be embedded above the lintel and the last
             course of bricks at wall plate level.
          • At least four brick courses.
          ANY ONE OF THE ABOVE                                                            (1)

Copyright reserved                                                     Please turn over

### Page 8

Downloaded from hlayiso.com
Civil Technology: Construction                   8                                 DBE/2019
                                     SC/NSC – Marking Guidelines

3.8       3.8.1        Nosing                                                                   (1)

          3.8.2        Apron                                                                    (1)

          3.8.3        Pitch board                                                              (1)

          3.8.4        Stairwell                                                                (1)

          3.8.5        Handrail                                                                 (1)

3.9       38°                                                                                   (1)

3.10      •    Long steel bolts are placed into holes of a loose template base plate,
               which is placed into the wet concrete. 
          •    Allow the concrete to dry. 
          •    Weld the base plate to the column/drill holes in the base plate/Fit
               prefabricated column over bolts and fasten. 
          •    Place the column with a steel foot plate with holes in over the bolts after
               the concrete has dried. 
          •    The column is then bolted firmly into the concrete base.                         (5)
                                                                                                 [30]

Copyright reserved                                                            Please turn over

### Page 9

Downloaded from hlayiso.com
Civil Technology: Construction                 9                                  DBE/2019
                                   SC/NSC – Marking Guidelines

QUESTION 4:          EXCAVATIONS, FORMWORK, TOOLS AND EQUIPMENT AND
                     MATERIALS (SPECIFIC)

4.1       4.1.1        • Very strong 
                       • Very tough 
                       • Easy to cast into shapes
                       • Durability/Long lasting/Sturdy
                       • Good tensile and yield strength
                       • Good thermal conductivity
                       • Resistance against corrosion if protected (painted, oxide)
                       • Ductile
                       • Easy to weld
                       • Heavy/High density
                       ANY TWO OF THE ABOVE                                                     (2)

          4.1.2        • Very soft metal 
                       • Malleable – can be stretched in any direction 
                       • Heavy/High density
                       • Corrosion-proof
                       • Low melting point
                       • Blue-grey metal
                       • Highly toxic
                       • Ductile
                       • Durability/Long lasting
                       • Easy to cut
                       ANY TWO OF THE ABOVE                                                     (2)

4.2       Purpose of the cube test:
          • To determine the maximum compressive strength of cured concrete
              when load is applied. 
          • To ensure that the concrete complies with the requirements of the project
              specifications. 
          • To indicate the compressive strength (measured in MPa or N/m²), thus its
              ability to resist loads.
          ANY TWO OF THE ABOVE                                                                  (2)

4.3       4.3.1        Safety factors to be considered before excavations:
                       • Ensure that a competent person evaluates the stability of the
                           ground. 
                       • Draw up a safety plan. 
                       • Take sufficient steps to ensure safe working conditions. 
                       • Ensure that any planned trench or excavation will be
                           supported by a protective system (formwork or shoring).
                       • Eliminate as many hazards and risks as possible (e.g. risk of a
                           person being buried or trapped by collapsing or dislodgement
                           of material)
                       • Erect fencing at least one metre high around the perimeter of
                           the excavation site.

Copyright reserved                                                           Please turn over

### Page 10

Downloaded from hlayiso.com
Civil Technology: Construction                  10                                   DBE/2019
                                     SC/NSC – Marking Guidelines

                         •  Ensure that all excavations take place under the supervision of
                            a qualified person whose appointment has been confirmed in
                            writing.
                         • Carry out inspections to determine whether there are electric
                            cables, water pipes, gas lines or any other service pipes in the
                            area to be excavated, since this may affect the excavation
                            process.
                         ANY THREE OF THE ABOVE                                                    (3)

          4.3.2          Factors than can cause excavations to collapse:
                         • Heavy rains 
                         • Poor soil strata, structure of composition. 
                         • Sides not dug at the correct angle. 
                         • Incorrect use of formwork or shoring to support the walls.
                         • Vibration by machinery or heavy vehicles nearby.
                         • Human traffic close to excavations.
                         • Water seeping into the excavated area.
                         • Contact with underground service.
                         • Access to and exit from the excavation.
                         • Soil slides due to cracks or loose soil.
                         • Natural causes
                         ANY THREE OF THE ABOVE                                                    (3)

4.4
                     
                                          
                                                   Poling boards
                                                   Folding wedges
                         
                                 
                                                   Struts
                                                                   
                                                  Walling boards/Wailing boards

          Shuttering correctly drawn 
          Proportion 

           ASSESSMENT CRITERIA                              MARK
           Folding wedge                                      1
           Walling boards/Wailing boards                      1
           Poling boards                                      2
           Struts                                             1
           Shuttering correctly drawn                         1
           Any ONE label                                      1
           Proportion                                         1
                                                TOTAL:        8                                    (8)

Copyright reserved                                                              Please turn over

### Page 11

Downloaded from hlayiso.com
Civil Technology: Construction                       11                                       DBE/2019
                                          SC/NSC – Marking Guidelines

4.5       •  The shape of folding wedges simplifies the erecting and dismantling of
             formwork.
          • Folding wedges ease the removal/striking of formwork by knocking one
             away from the other.
          • Folding wedges help to keep formwork components sturdy and secured.
          • Folding wedges play an important role in the levelling of formwork for
             beams, floor slabs and columns.
          • Folding wedges are used as pins to strengthen adjoining concrete
             formwork.
          • Folding wedges are used to raise or lower the formwork to the required
             height.
          ANY ONE OF THE ABOVE                                                                            (1)

4.6
                                      
                     Cleats

                                                                                Beam/Joist
         Brace for
         beams                                                   Shutterboard
      Wedges                                                           Fixing plates/kickers

                                                        
                                                            
                                                                                  Bearer

                                                                 Braces/Strut

ASSESSMENT CRITERIA                                   MARK        Proportion 
Bearer/Joist for the soffit                             1
Cleats                                                  2
Braces for beams/struts                                 2
Fixing plates/Kickers                                   2
Wedges                                                  2
Any ONE label                                           1
Proportion                                              1
                                          TOTAL:       11

                                                                                                          (11)

Copyright reserved                                                                     Please turn over

### Page 12

Downloaded from hlayiso.com
Civil Technology: Construction                 12                                 DBE/2019
                                    SC/NSC – Marking Guidelines

4.7       4.7.1        Safety precautions when using a plate compactor:
                       • Operate with care. 
                       • Wear gloves and boots etc. as personal protective
                           equipment. 
                       • Do not place your hands or feet near the moving parts.
                       • Check the controls for proper response before use.
                       • Check for wear and damaged parts before use.
                       • Never use a defective/faulty machine.
                       • Avoid making any adjustments while the machine is vibrating.
                       • Use both hands to operate the machine.
                       • Ensure a firm and well balanced stance.
                       • Work from side to side to achieve the best, even surface.
                       • Wet the soil slightly to make it easier to compact.
                       ANY TWO OF THE ABOVE                                                     (2)

          4.7.2        Care of a plate compactor:
                       • Maintain like all machinery – lubricate and adjust according to
                           the manufacturers, instruction. 
                       • Clean after use.
                       • Store in a safe dry place/allocated place.
                       • Service the plate compactor regularly.
                       • Remove loose dust and soil after use.
                       • Ensure that all parts are firmly attached.
                       • Repair or replace damaged electric cords/parts.
                       ANY ONE OF THE ABOVE                                                     (1)

4.8       4.8.1        Concrete mixer (electric)                                               (1)

          4.8.2        Care of a concrete mixer:
                       • Only use parts as recommended by the manufacturer. 
                       • Maintain like all machinery – lubricate and adjust according to
                           the manufacturers, instruction. 
                       • Rinse with water.
                       • Clean after use.
                       • Wash of any concrete residue of the body of the mixer.
                       • Do not allow the water to remain inside the drum.
                       • Oil the inside of the drum when stored for a long time.
                       • Keep bearings, bushes and gears lubricated.
                       • Replace worn parts, especially in the drum.
                       • Maintain electric or internal combustion engines according to
                           the manufacturer’s instructions.
                       • Store in a dry place.
                       • Service the concrete mixer regularly.
                       • Repair or replace damaged electric cords.
                       ANY TWO OF THE ABOVE                                                     (2)

4.9       •    Boom pump 
          •    Line pump                                                                       (2)
                                                                                                [40]

Copyright reserved                                                           Please turn over

### Page 13

Downloaded from hlayiso.com
Civil Technology: Construction              13                              DBE/2019
                                 SC/NSC – Marking Guidelines

QUESTION 5:          PLASTER AND SCREED, BRICKWORK AND GRAPHICS AS
                     MEANS OF COMMUNICATION (SPECIFIC)

5.1       5.1.1        F                                                                 (1)

          5.1.2        D                                                                 (1)

          5.1.3        A                                                                 (1)

          5.1.4        B                                                                 (1)

          5.1.5        C                                                                 (1)

5.2       Three wheelbarrows/2½ wheelbarrows                                             (1)

5.3       • Pavements 
          • Patios 
          • Town centres/Schools/Stadiums etc. 
          • Road surfaces
          • Driveways
          • Walkways
          • Any specific area suitable for paving.
          ANY THREE OF THE ABOVE                                                          (3)

5.4       Advantages of using paving:
          • It is more economical than concrete. 
          • Low initial installation cost as compared to concrete.
          • Individual pavers can be lifted to access the surface underneath while
             concrete must be broken up.
          • Easier to repair than concrete.
          • It is more user friendly than concrete.
          • It has a better appearance.
          • It can be laid in decorative patterns.
          • Less labour intensive.
          ANY ONE OF THE ABOVE                                                            (1)

Copyright reserved                                                     Please turn over

### Page 14

Downloaded from hlayiso.com
Civil Technology: Construction                  14                                    DBE/2019
                                     SC/NSC – Marking Guidelines

5.5

                                      
                                                                

                                                            

                                     FIRST COURSE

                                 

                                                                
                                                      

                                     SECOND COURSE

                                                                           Proportion 

           ASSESSMENT CRITERIA                                      MARK
           One full brick on outer skin of first course               1
           One full brick on inner skin of first course               1
           Brick on first course to close cavity                      1
           One full brick on outer skin on second course              1
           One full brick on inner skin on second course              1
           Brick on second course to close cavity                     1
           Proportion                                                 1
                                                     TOTAL:           7                             (7)

Copyright reserved                                                               Please turn over

### Page 15

Downloaded from hlayiso.com
   Civil Technology: Construction                  15                                          DBE/2019
                                        SC/NSC – Marking Guidelines

   5.6

                                                Wall plate                                 Rafter

                                                                      

         Eaves                                                                            Tie beam
         overhang
                                                             
                                                
                                                                                              Hanger
                                            
Fascia board                        
                                                                          Bearer
                                                                        Fibre cement board
                                                        
         Quarter round mould
                                                220 mm wall                     Any ONE label 
                                            SCALE: 1:10
             Application of scale 

             USE A MASK TO MARK THIS QUESTION

               ASSESSMENT CRITERIA                                                     MARK
               Wall: 220 mm wide                                                         1
               Tie beam: 114 x 38 mm                                                     1
               Wall plate: 114 x 38 mm                                                   1
               Eaves overhang: 400 mm                                                    1
               Rafter: 114 x 38 mm                                                       1
               Fascia board: 228 x 28 mm                                                 1
               Bearer: 38 x 38 mm                                                        1
               Hanger: 38 x 38 mm                                                        1
               6 mm fibre-cement board on closed eaves                                   1
               Two quarter-round mouldings below fibre-cement board                      1
               Any ONE label                                                             1
               Application of scale                                                      2
                                                                   TOTAL:               13

                                                                                                          [30]

   Copyright reserved                                                                  Please turn over

### Page 16

Downloaded from hlayiso.com
Civil Technology: Construction               16                                    DBE/2019
                                  SC/NSC – Marking Guidelines

QUESTION 6:          REINFORCEMENT IN CONCRETE, FOUNDATIONS, CONCRETE
                     FLOORS AND QUANTITIES (SPECIFIC)

6.1       6.1.1        C                                                                        (1)

          6.1.2        D                                                                        (1)

          6.1.3        C                                                                        (1)

          6.1.4        C                                                                        (1)

          6.1.5        A                                                                        (1)

6.2

                                                       Steel casing

                                                           Shape of the bottom/
                                                         Enlarged base

                                  Driven in-situ pile
                                                                   Any ONE label 

           ASSESSMENT CRITERIA                                  MARK
           Steel casing                                           1
           Shape of the bottom                                    2
           Any ONE label                                          1
                                                   TOTAL:         4
                                                                                                 (4)

6.3       The purpose of the steel capping is to protect the top of the pile from breaking
          when it is driven into the ground with the drop hammer.                               (1)

Copyright reserved                                                            Please turn over

### Page 17

Downloaded from hlayiso.com
Civil Technology: Construction                17                           DBE/2019
                                   SC/NSC – Marking Guidelines

6.4

                                                         

                  

                                                                               Stirrups

                                   

                  Minimum concrete cover

                                                     
                                                                      

                                                                 
                                  Main bar                                      Main bar

                        Any two labels   

                                         Proportion 

              ASSESSMENT CRITERIA             MARK
           L-shaped column                       2
           8 main bars                           2
           Stirrups/Binders                      2
           Minimum concrete cover                1
           Any TWO labels                        2
           Proportion                            1
           TOTAL                                10                                      (10)

6.5       6.5.1        A – In-situ cast concrete 
                       B – Concrete hollow block 
                       C – Precast ribs                                                (3)

Copyright reserved                                                   Please turn over

### Page 18

Downloaded from hlayiso.com
Civil Technology: Construction                 18                                   DBE/2019
                                    SC/NSC – Marking Guidelines

          6.5.2        The rib is used to:
                       • support the weight of the floor and any other loads imposed on
                           it. 
                       • support the hollow blocks that form part of the construction.
                       • prevents the hollow blocks from moving.
                       ANY ONE OF THE ABOVE                                                       (1)

          6.5.3        Factors to consider when planning a rib- and block floor:
                       • Maximum span 
                       • Unit weight 
                       • Nature of props 
                       • Sound insulation
                       • Thickness of units
                       • Pre-stressed units
                       • Fire resistance
                       • Construction speed
                       • Reinforcement properties
                       • Support and formwork required
                       • Safety features
                       • Weight reduction
                       • Volume reduction
                       • Precast top layer
                       ANY THREE OF THE ABOVE                                                     (3)

          6.5.4        Services:
                       • Electrical services/Conduits 
                       • Plumbing/Hot water/Cold water/Waste pipes/
                           Sewerage pipes 
                       • Communication/Telephone/Tele camera 
                       • Security services/Alarm/Camera
                       ANY THREE OF THE ABOVE                                                     (3)

Copyright reserved                                                             Please turn over

### Page 19

Downloaded from hlayiso.com
Civil Technology: Construction                 19                                DBE/2019
                                  SC/NSC – Marking Guidelines

6.6

              A          B           C                          D
                                               Concrete for foundations
                                               Centre line
                                               2/6 000         = 12 000 mm 
                                               2/3 000         = 6 000 mm 
                                               Total            = 18 000 mm 
                                               Minus 4/600       = 2 400 mm 
                                               Total centre line = 15,6 m 
         1/           15,6 
                       0,6 
                      0,25      2,34 m³ 

                                                                                            (10)
                                                                                            [40]

                                                                                TOTAL:      200

Copyright reserved

## Related documents

- [Civil Technology May June 2019 (Civil Services) Memo Afr](https://www.hlayiso.com/library/civil-technology-may-june-2019-civil-services-memo-afr/2a9b9e1b-37dc-48dc-9aa7-67dd5fa19a10) — Civil Technology · Memo · 2019 · Afr
- [Civil Technology May June 2019 (Civil Services) Memo Eng](https://www.hlayiso.com/library/civil-technology-may-june-2019-civil-services-memo-eng/8c1355fc-f6e2-40c6-85ff-1d03eb2991ea) — Civil Technology · Memo · 2019 · Eng
- [Civil Technology May June 2019 (Civil Services) Eng](https://www.hlayiso.com/library/civil-technology-may-june-2019-civil-services-eng/3f3d8211-a2ae-4ecd-89a4-623bb435b86a) — Civil Technology · QP · 2019 · Eng
- [Civil Technology May June 2019 (Construction) Afr](https://www.hlayiso.com/library/civil-technology-may-june-2019-construction-afr/87c657e9-94a5-422f-ade2-b3b897806384) — Civil Technology · QP · 2019 · Afr
- [Civil Technology May June 2019 (Wood Working) Afr](https://www.hlayiso.com/library/civil-technology-may-june-2019-wood-working-afr/bdea7087-4612-4372-bd72-70147466f760) — Civil Technology · QP · 2019 · Afr
- [Civil Technology Nov 2019 (Civil Services) Memo Afr](https://www.hlayiso.com/library/civil-technology-nov-2019-civil-services-memo-afr/13c03cd5-cfa4-42cf-9a7c-5d7b0e1069f0) — Civil Technology · Memo · 2019 · Afr

## More from Grade 12 Civil Technology

- [Civil Technology (Woodwork) (English and Afrikaans) June 2025 Question Paper](https://www.hlayiso.com/library/civil-technology-woodwork-english-and-afrikaans-june-2025-question-paper/c8edd459-5237-48e0-8588-69d7ecd7f8e5) — QP · 2025 · Afr
- [Civil Technology May-June 2025 (Construction) Afr](https://www.hlayiso.com/library/civil-technology-may-june-2025-construction-afr/591d6ffd-20b1-4748-a1ba-b055be0a14c3) — QP · 2025 · Afr
- [Civil Technology Nov 2025 (Woodworking) Afr](https://www.hlayiso.com/library/grade-12-civil-technology-2025-nsc-november-exam-question-paper/05a95faf-5891-4d88-9e5e-7d13c1d21648) — QP · 2025 · Afr
- [CIV TECH GR12 QP SEPT2024 Woodworking Afrikaans](https://www.hlayiso.com/library/civ-tech-gr12-qp-sept2024-woodworking-afrikaans/1c6d5c64-83b5-456b-abcf-2abc23f1f1fe) — QP · 2024 · Afr
- [CIV TECH GR12 QP SEPT2024 Construction English](https://www.hlayiso.com/library/civ-tech-gr12-qp-sept2024-construction-english/12643629-87af-4230-a48a-002beb7f6cd7) — QP · 2024 · Eng
- [Civil Technology Nov 2024 (Woodworking) Afr](https://www.hlayiso.com/library/civil-technology-nov-2024-woodworking-afr/eefaae29-fe93-4b75-8223-87bf4f3fc14c) — QP · 2024 · Afr

## Collection

- [Grade 12 past papers](https://www.hlayiso.com/grade-12/past-papers)

---

Hlayiso: free CAPS and IEB past papers, memos, notes and study guides for South African learners. When citing, link the page URL above, not a PDF or /api/ URL.