# Civil Technology Grade 12 NSC June 2021 Memo (English)

> Grade 12 Civil Technology memorandum from the NSC June Exam 2021 (English), 16 pages. Read online or download the free PDF.

- Page: https://www.hlayiso.com/library/civil-technology-may-june-2021-civil-services-mg-eng/76549992-6f60-4921-abf6-0ffcadda1032
- Updated: 2026-10-29
- Subject: Civil Technology
- Grade: Grade 12
- Document type: Memorandum
- Year: 2021
- Exam period: NSC June Exam
- Curriculum: CAPS
- Pages: 16

Breadcrumbs: [Home](https://www.hlayiso.com/) › [Library](https://www.hlayiso.com/library) › [Grade 12](https://www.hlayiso.com/library/grade-12) › [Civil Technology](https://www.hlayiso.com/library/grade-12/civil-technology) › [Civil Technology Grade 12 NSC June 2021 Memo (English)](https://www.hlayiso.com/library/civil-technology-may-june-2021-civil-services-mg-eng/76549992-6f60-4921-abf6-0ffcadda1032)

## About this document

Civil Technology · Grade 12 · NSC June Exam · 2021. Memorandum. Read online or download the PDF.

Read it free online on the page above; download the PDF from there.

## Document text

Text extracted from the PDF. Layout, diagrams and tables may not survive extraction.

### Page 1

Downloaded from hlayiso.com

             SENIOR CERTIFICATE EXAMINATIONS/
         NATIONAL SENIOR CERTIFICATE EXAMINATIONS

                       CIVIL TECHNOLOGY: CIVIL SERVICES

                                          2021

                                MARKING GUIDELINES

                                                                      MARKS: 200

                      These marking guidelines consist of 16 pages.

Copyright reserved                                                    Please turn over

### Page 2

Downloaded from hlayiso.com
Civil Technology: Civil Services                   2                                      DBE/2021
                                       SC/NSC – Marking Guidelines

        INSTRUCTIONS FOR THE MARKERS

   1.      Markers should:

                   Familiarise themselves with the question and answer before evaluating
                    the responses of candidates.

                   Always interpret the responses of the candidates within the context of
                    the question.

                   Consider any relevant and acceptable answer during pre-marking but
                    should strictly adhere to the answers after finalisation of the marking
                    guideline.

                   There are two approaches to answering questions, these are (1) to
                    describe and (2) to explain.
                       If a candidate is required to explain e.g., a process in 4 steps, only the
                       first 4 responses should be considered.

                       If, however a candidate is required to e.g., explain or describe how to
                       transfer heights from one point to another using a transparent pipe level
                       we need to consider that candidates may write a long description not
                       necessarily well organised as an intellectual response may do. In this
                       case the marker needs to evaluate the complete statement to judge if
                       the candidate explained the required outcome satisfactorily and allocate
                       marks on merit. The marker should apply his/her professional
                       judgement with these types of questions.

                   Mark what the candidate wrote and do not award marks for answers
                    that the marker thinks the candidate meant with what was written.

                   Indicate the tick or cross right at the position where the mark needs to
                    be awarded or where the candidate made the error.

                   Accept the letter corresponding with the correct answer as well as the
                    answer written in full in multiple-choice questions.

                   Accept incorrect spelling in one-word answers unless the spelling
                    changes the meaning of the answer.
   2.      For calculations:
                        A mark is only awarded if the correct unit is written next to the answer.
                        If TWO marks are awarded ONE mark is awarded for the answer and
                         ONE mark for the correct unit.

                        Where the candidate made a principle error e.g. added instead of
                         multiplying, no marks will be awarded for the steps. If the answer is
                         correct according to what the candidate did, the mark for the answer
                         can be awarded for the application of skills.

Copyright reserved                                                                   Please turn over

### Page 3

Downloaded from hlayiso.com
Civil Technology: Civil Services                 3                                      DBE/2021
                                     SC/NSC – Marking Guidelines

                      Where an incorrect answer could be carried over to the next step, the
                       first answer will be deemed incorrect. However, should the incorrect
                       answer be carried over correctly, the marker has to recalculate the
                       values, using the incorrect answer from the first calculation. If correctly
                       used, the candidate should receive the full marks for subsequent
                       calculations.
                      Markers should consider when and where a candidate has rounded off
                       in a calculation, as well as the subsequent effect it has on the final
                       answer obtained. The calculation should therefore be awarded marks
                       on merit.
                      Alternative methods of calculations must be considered, provided that
                       the correct answer is obtained.

   3.      When marking drawings:
                          The member for which the mark should be awarded should be
                           drawn correctly in the correct position to receive a mark.
                          A member incorrectly drawn but wrongfully repeated in another
                           position will be awarded the mark for the repeated incorrect
                           member provided that the marking guideline provide for TWO or
                           more marks for that member (positive marking).
                          Marks can only be awarded for a label if the label is correctly
                           indicating the correct member.
                          Scale drawings should always be marked using an appropriate
                           mask.
           When a candidate drew the wrong drawing e.g.:

                          A horizontal section instead of a vertical section, no marks will be
                           allocated to the drawing as the candidate did not respond to the
                           expected outcome.

                          An orthographic view instead of sectional view, no marks will be
                           allocated to the drawing as the candidate did not respond to the
                           expected outcome.

                          An orthographic view instead of an isometric view, no marks will be
                           allocated to the drawing as the candidate did not respond to the
                           expected outcome.

                          If the incorrect drawing was drawn, the candidate can be awarded
                           for only what was asked but mark/s for the correctness of the
                           drawing will not be awarded e.g., if a King Post roof truss was
                           asked in the question, and candidate drew SA-Howe Truss.

Copyright reserved                                                                 Please turn over

### Page 4

Downloaded from hlayiso.com
Civil Technology: Civil Services                 4                                        DBE/2021
                                     SC/NSC – Marking Guidelines

QUESTION 1:           OHSA, SAFETY, MATERIALS, TOOLS AND EQUIPMENT AND
                      JOINING (GENERIC)

1.1        1.1.1        Paint                                                                         (1)

           1.1.2        Curing                                                                        (1)

           1.1.3        Electroplating                                                                (1)

           1.1.4        Powder coating                                                                (1)

           1.1.5        Galvanising                                                                   (1)

1.2        1.2.1            Wood 
                            Aluminium 
                            Fibreglass
                            Steel                                                                     (2)

           1.2.2        A
                         The ladder in B is broken/has defects. 
                         The rungs of the ladder in B are broken.
                         The stiles of the ladder in B are not properly joined.
                         The ladder in A has no defects/is not broken.                                (2)

           1.2.3          A ladder can be used to safely climb to a higher level. 
                          To access a higher level than a normal person can reach from
                           the ground.
                         It can be used to safely descend from heights.
                         To enter or exit deep excavations.
                        ANY ONE OF THE ABOVE                                                           (1)

           1.2.4         ¼ (One quarter) of the upright(vertical) length of the ladder
                         1 : 4 ratio
                         75°/76°
                        ANY ONE OF THE ABOVE                                                           (1)

1.3        1.3.1       To determine:
                       (a) The gradient/slope for sewerage system                                     (1)
                       (b)    A level line/reference point from where to start tiling                 (1)

           1.3.2        If the base of the tripod is not set up wide enough:
                         the laser level can be blown or knocked over. 
                         the instrument can be damaged or its accuracy impaired if it
                             should fall over.
                         the tri-pod will be unstable.
                        ANY ONE OF THE ABOVE                                                           (1)

Copyright reserved                                                                  Please turn over

### Page 5

Downloaded from hlayiso.com
Civil Technology: Civil Services                 5                                   DBE/2021
                                     SC/NSC – Marking Guidelines

1.4         The worker can injure himself e.g. shoulder injury. 
            Can injure fellow workers e.g. load can fall.
           ANY ONE OF THE ABOVE                                                                    (1)

1.5        1.5.1         Before it is used 
                         Once a week
                         After bad weather
                        ANY ONE OF THE ABOVE
                                                                                                   (1)
           1.5.2          Qualified person 
                          Experienced person in the erection and maintenance of
                           scaffolds
                        ANY ONE OF THE ABOVE                                                       (1)

1.6        1.6.1        Bolt                                                                      (1)

           1.6.2        Nut/Washer and nut                                                        (1)

           1.6.3          Bolts and nuts secure a stronger joint. 
                          Use of bolts and nuts/bolts, washers and nuts will ensure that
                           parts are secured tightly together, which is not always possible
                           with screws.
                         Can easily be removed.
                        ANY ONE OF THE ABOVE                                                       (1)
                                                                                                   [20]

Copyright reserved                                                              Please turn over

### Page 6

Downloaded from hlayiso.com
Civil Technology: Civil Services               6                                     DBE/2021
                                   SC/NSC – Marking Guidelines

QUESTION 2: GRAPHICS AS MEANS OF COMMUNICATION (GENERIC)

NO.                     QUESTION                                  ANSWER                    MARKS
1.      Identify the type of plan in FIGURE 2.      Site plan                                     1

        Deduce from the notes the brick force
2.                                                  Every third course                            1
        installation up to window height.
        Deduce the scale that is used for
3.                                                  1 : 200                                       1
        FIGURE 2.
4.      Identify number 1.                          Boundary line                                 1
5.      Identify number 3.                          Building line                                 1
6.      Identify number 5.                          Main sewer line/Sewer line                    1
7.      Identify number 7.                          Entrance/Driveway                             1
                                                    Municipal sewer
8.      Identify number 8.                          connection/Municipal                           1
                                                    Manhole/Manhole 
9.      Identify number 9.                          North/North symbol/direction/point            1
        Name the item in the column for the
10.     notes in FIGURE 2 that must be              Shower                                        1
        installed in the bathroom.
        Draw the electrical symbol as
11.     described in the column for the notes                                                    2
        in FIGURE 2
        Deduce from FIGURE 2 which
12.                                                 Henson Printers                               1
        company printed the building plan.
13.     Give the abbreviation for number 2.         RE                                            1
        State the colour that you would use to
14.     indicate the new dwelling on the site       Red                                           1
        plan.
                                                      No plot on eastern side 
                                                      Quarter rounding at the corner
        Deduce from FIGURE 2 why the new               of the pavement
15.                                                                                                1
        dwelling is to be built on a corner plot.    Paving on the eastern side
                                                     Street on the eastern side
                                                    ANY ONE OF THE ABOVE
        Deduce the plot number of the new
16.                                                 51                                            1
        dwelling illustrated in FIGURE 2.

        Which elevation is the closest to
17.                                                 South elevation                               1
        Protea Street?

Copyright reserved                                                              Please turn over

### Page 7

Downloaded from hlayiso.com
Civil Technology: Civil Services               7                                       DBE/2021
                                   SC/NSC – Marking Guidelines

        What is the plot number of the
18.     property on the western side of the        49                                               1
        dwelling?
19.     Give the abbreviation for number 6.        MH                                               1
        State the slope at which the main     1:40                                                  1
20.
        sewer line should be installed.
21.     Describe what was done as revision 1. Rectify dimension                                     1
        Deduce the dimension fault on the
22.                                                100/14 100/14 000 mm                             1
        total width of the dwelling.
23.     State the project number for this plan.    GR 448 - 209                                     1

24.     What is the width of the pavement?         1 500 mm or 1,5 m                                1
        How many branch pipes are indicated
25.                                                5                                                1
        on the plan?
                                                   To give access to the sewer line
26.     Explain the purpose of number 4.           when blockages occur/or for                       1
                                                   inspection purposes. 
        In what SI unit are the dimensions
27.     indicated on the plan?                     mm                                               1

        Draw a neat freehand drawing of the
        top view of the symbol of a single                                   
28.     kitchen sink, as indicated in the                                                           3
        SANS/SABS Code of Practice for
        Building Drawings.
                                                   Bricks/Paving 
        Recommend TWO types of building            Tar 
29.     materials that can be used to finish the                                                     2
        area at number 7.                          Concrete slab/Gravel/Asphalt
                                                   ANY TWO OF THE ABOVE
                                                     (35 m  x 25 m )
        Calculate the total area of the plot.      = 875 m² 
30.     Give your answer in m².                       OR                                             3
        Show ALL calculations.                       (35 000 mm x 25 000 mm)
                                                   = 875 m²
                                                     (10 000 mm  - 3 000 mm )
        Calculate the distance between             = 7 000  mm 
        Number 1 and Number 3 on the north            OR
31.                                                                                                  4
        elevation.                                   (10 m - 3 m)
        Show ALL calculations.                     = 7 m

                                                                               TOTAL:             40

Copyright reserved                                                                Please turn over

### Page 8

Downloaded from hlayiso.com
Civil Technology: Civil Services                 8                                 DBE/2021
                                     SC/NSC – Marking Guidelines

QUESTION 3:          CONSTRUCTION ASSOCIATED WITH CIVIL SERVICES, OHSA
                     AND QUANTITIES (SPECIFIC)

3.1        3.1.1        Ground level before excavation/NGL                                      (1)

           3.1.2            Concrete slab 
                            Floor slab                                                          (1)

           3.1.3        Factors that can cause ground movement can include:
                         Blasting 
                         Piling 
                         Compaction
                         Any construction that involves vibrations                              (2)

           3.1.4        1:2 OR 1 ≥ 2                                                           (2)

3.2        Warning signals:

               Red 
               Orange                                                                          (2)

3.3        Items that should not be placed near the edge of an excavation are:
            Any type of load 
            Materials 
            Heavy machinery/vehicles
            Equipment
           ANY TWO OF THE ABOVE                                                                  (2)

3.4        Soil compaction is a process of increasing the density of soil  by pressing
           the soil particles closer together. 
                                                 OR
           Reducing the volume of air trapped between the particles using hand
           compaction or a rammer.                                                               (2)

3.5        Sandy soil                                                                           (1)

3.6        3.6.1        Shoring                                                                 (1)

           3.6.2         To support the sides of the excavations. 
                         To ensure that sides do not cave in.
                        ANY ONE OF THE ABOVE                                                     (1)

Copyright reserved                                                            Please turn over

### Page 9

Downloaded from hlayiso.com
Civil Technology: Civil Services                9                              DBE/2021
                                    SC/NSC – Marking Guidelines

3.7                     Volume of tank:

                        = Area of base x height
                        = π r² h 
                        = π (3,14) x 0,8  x 0,8  x 3,1 
                        = 6,23 m³ 
                                    OR

                        = π (3,14) x 800 x 800 x 3 100
                        = 6,23 m³                                                            (6)

3.8        Area of base x height  OR S x S x S          OR S³                               (1)

3.9        1 000 litres                                                                     (1)

3.10
                             
                                      

                                      
                                                                    

                 NO ASSESSMENT CRITERIA                       MARK
                  1 Half brick in correct position              1
                  2 Full bricks in correct position             6
                                                  TOTAL:        7                            (7)
                                                                                             (30)

Copyright reserved                                                        Please turn over

### Page 10

Downloaded from hlayiso.com
Civil Technology: Civil Services                10                                     DBE/2021
                                     SC/NSC – Marking Guidelines

QUESTION 4:          HOT- AND COLD-WATER SUPPLY, TOOLS, EQUIPMENT AND
                     MATERIALS (SPECIFIC)

4.1        4.1.1            Full-way valve 
                            Gate valve                                                              (1)

           4.1.2        A – Hand wheel/Wheel 
                        B – Valve head 
                        C – Valve body                                                              (3)

           4.1.3        The tapered gate (D) is used to open or shut off the water flow
                        when necessary.                                                             (1)

           4.1.4         Part D will move upwards. 
                         The tapered gate will open.
                         The water will start to flow.
                        ANY ONE OF THE ABOVE                                                         (1)

4.2        A pillar tap is fitted to the sanitary fitment itself in a vertical position and is
           provided with a long leg to allow it to be fitted to the surface of a sanitary
           fitting. 
           A bibcock is fitted to the pipework in the wall.                                         (2)

4.3        4.3.1        F                                                                           (1)

           4.3.2        G                                                                           (1)

           4.3.3        E                                                                           (1)

           4.3.4        A                                                                           (1)

           4.3.5        B                                                                           (1)

           4.3.6        C                                                                           (1)

           4.3.7        H                                                                           (1)

           4.3.8        J                                                                           (1)

4.4        4.4.1        Dumpy level                                                                 (1)

           4.4.2        Centrifugal pump                                                            (1)

           4.4.3        Drain cleaning machine/Jetting machine                                      (1)

4.5        Place a bottle/brick/solid object  inside the cistern  to limit the volume of
           water used to fill the cistern.                                                           (2)

4.6        Ball valve/Flush valve/Float valve                                                       (1)

Copyright reserved                                                                Please turn over

### Page 11

Downloaded from hlayiso.com
Civil Technology: Civil Services                   11                               DBE/2021
                                        SC/NSC – Marking Guidelines

4.7        4.7.1        The vacuum breaker allows air to enter the pipe when needed to
                        prevent siphonage.                                                       (1)

           4.7.2        Pressure control valve                                                   (1)

           4.7.3        Stopcock/Full-way valve                                                  (1)

           4.7.4        Cold  - Cold water enter at the bottom of the geyser and hot
                        water will exit at the top of the geyser.                                (2)

           4.7.5        Drip tray                                                                (1)

4.8        4.8.1
                                        B              
                                                                                                  (2)

           4.8.2

                                                  
                                                                                                  (2)

           4.8.3
                                   PS
                                                 OR
                                                                                                  (2)

4.9        4.9.1        An airlock                                                               (1)

           4.9.2          Pipes that are shorter than 1 m must be installed horizontally
                           or with an upward slope in the direction of flow. 
                         If the pipe is longer that 1 m it must be installed horizontally
                           with an upward slope in the direction of flow.
                         Vent valves can be installed in the pipeline.
                        ANY ONE OF THE ABOVE                                                      (1)

4.10       This problem can be avoided by:
            Using the same type of material (metal) throughout a system. 
            Using a non-metallic coupler when joining copper to galvanised pipes.               (2)

4.11       4.11.1       Hydrochloric acid                                                        (1)

           4.11.2       Dezincification                                                          (1)
                                                                                                  [40]

Copyright reserved                                                             Please turn over

### Page 12

Downloaded from hlayiso.com
Civil Technology: Civil Services                  12                             DBE/2021
                                       SC/NSC – Marking Guidelines

QUESTION 5:          GRAPHICS AS MEANS OF COMMUNICATION, ROOF WORK AND
                     STORM WATER (SPECIFIC)

5.1                                    
                                       
                                       

                                   

                             

                                   
                                                                                               (6)

5.2                 The concrete shoe channels water away from the house/building 
                    The surface channel channels the water to rivers/dams.                   (2)

5.3        Flashing:
            Copper 
            Galvanised sheet metal 
            Lead
            Bitumastic patents
            Rubber sealant
            Flash Harry (membrane with water proofing compound)
           ANY TWO OF THE ABOVE                                                                (2)

Copyright reserved                                                          Please turn over

### Page 13

Downloaded from hlayiso.com
Civil Technology: Civil Services                     13                                  DBE/2021
                                          SC/NSC – Marking Guidelines

5.4                                      5

                          5                        5    2
                                                               2
               6

                                                                     2
                    5    4        4         4   4     5
                                                                          2
                               5
                                                                6
                                              3     3

               USE A MASK TO MARK
               THIS QUESTION                                    1             1

               Note: Candidates may use any of the following
               methods to divide the plan view into 12 parts.

                    Transfer distance from top view.
                    Calculate circumference and divide by 12.
                    Construction to divide line into equal parts.
                    NO.   ASSESSMENT CRITERIA                              MARK
                     1    Dividing circle in 12 parts (top view)             2
                     2    Projection lines from top and front view           4
                     3    Dividing development into 12 parts                 2
                     4    Folding lines of development                       4
                     5    Outside lines of developments                      6
                     6    3 mm seam on both sides                            2
                                                                 TOTAL:     20
                                                                                                       (20)
                                                                                                       [30]

Copyright reserved                                                                  Please turn over

### Page 14

Downloaded from hlayiso.com
Civil Technology: Civil Services                14                                   DBE/2021
                                     SC/NSC – Marking Guidelines

QUESTION 6:           SEWERAGE, SANITARY FITTINGS AND JOINING (SPECIFIC)

6.1        6.1.1        A                                                                         (1)

           6.1.2        D                                                                         (1)

           6.1.3        A                                                                         (1)

           6.1.4        C                                                                         (1)

           6.1.5        C                                                                         (1)

6.2        6.2.1            Rivet gun 
                            Pop rivet gun                                                         (1)

           6.2.2            Steel 
                            Stainless steel                                                       (1)

           6.2.3            Aluminium 
                            Stainless steel                                                       (1)

6.3        6.3.1        A – PVC waste bend 90° with inspection eye 
                        B – PVC pipe 40/50 mm 
                        C – Holder bat 
                        D – Sink waste fitting/Outlet                                             (4)

           6.3.2        To secure the pipe to the wall.                                           (1)

           6.3.3            P – trap 
                            S – trap                                                             (2)

           6.3.4        The water forms a water seal to prevent bad smells and odours
                        rising from the system to escape.                                         (1)

           6.3.5        The grid can be blocked by greasy residue or leaves that collect on
                        the grating.                                                              (1)

6.4            An overflow outlet allows excess water to flow through it to the waste
                pipe. 
               It will prevent the sanitary fitting from overflowing if a tap was left open
                and the plug is in the outlet.                                                    (2)

6.5             Bath 
                Wash basin                                                                       (2)

6.6        Rodding eye - Provide access to the interior of a sewerage system. 
           Stop end – Stop the water flow at the end of the pipe.                                 (2)

Copyright reserved                                                              Please turn over

### Page 15

Downloaded from hlayiso.com
Civil Technology: Civil Services                15                            DBE/2021
                                     SC/NSC – Marking Guidelines

6.7        6.7.1        Ceramics:
                          A pleasant, glazed surface 
                          Available in a variety of colours
                          Fireclay is mostly used
                          It is strong
                          It is durable
                         ANY ONE OF THE ABOVE                                               (1)

           6.7.2        Terrazzo:
                          Very expensive 
                          Very hard to handle
                         ANY ONE OF THE ABOVE                                               (1)

6.8                     
              RWS                                                                           (2)

6.9     Working process of a septic tank:
         Sewerage enters the septic tank from the fitment into the first chamber
           through the inlet pipe. 
         Heavier particles sink to the bottom of this chamber. 
         Bacteria break the solid waste down into a liquid. 
         The sludge stays at the bottom of the tank. 
         All decomposed solids flow into the second chamber. 
         Only liquid flows from the second chamber through the outlet pipe into the
           French drain. 
         Sludge must be cleaned out at regular intervals by means of a special
           truck.                                                                           (6)

Copyright reserved                                                       Please turn over

### Page 16

Downloaded from hlayiso.com
Civil Technology: Civil Services                16                          DBE/2021
                                     SC/NSC – Marking Guidelines

6.10

                                                  

                                                       
                                                                   

                                                      
                                              
                                     

                              

          NO. ASSESSMENT CRITERIA                            MARK CANDIDATE’S
                                                                     MARK
           1     Walls                                         2
           2     Hatching                                      1
           3     Pipes                                         2
           4     Angle of junction                             1
           5     Direction of flow                             1
                                                      TOTAL:   7                       (7)
                                                                                       [40]

                                                                          TOTAL:       200

Copyright reserved

## Related documents

- [Civil Technology May June 2021 (Woodworking) Eng](https://www.hlayiso.com/library/civil-technology-may-june-2021-woodworking-eng/8f870317-4f98-4448-b660-0d528b30c2a4) — Civil Technology · QP · 2021 · Eng
- [Civil Technology May June 2021 (Woodworking) Afr](https://www.hlayiso.com/library/civil-technology-may-june-2021-woodworking-afr/ff7a7835-2450-4747-baaf-85c46ef7d411) — Civil Technology · QP · 2021 · Afr
- [CIV TECH GR12 MEMO SEPT2021 English Civil Services](https://www.hlayiso.com/library/civ-tech-gr12-memo-sept2021-english-civil-services/80eb9860-b118-41e2-98fd-5bea1b29a026) — Civil Technology · Memo · 2021 · Eng
- [Civil Technology May June 2019 (Civil Services) Memo Afr](https://www.hlayiso.com/library/civil-technology-may-june-2019-civil-services-memo-afr/2a9b9e1b-37dc-48dc-9aa7-67dd5fa19a10) — Civil Technology · Memo · 2019 · Afr
- [Civil Technology May June 2019 (Civil Services) Memo Eng](https://www.hlayiso.com/library/civil-technology-may-june-2019-civil-services-memo-eng/8c1355fc-f6e2-40c6-85ff-1d03eb2991ea) — Civil Technology · Memo · 2019 · Eng
- [Civil Technology May June 2018 Memo Eng](https://www.hlayiso.com/library/civil-technology-may-june-2018-memo-eng/559fa58b-574d-4982-8261-326355e9f841) — Civil Technology · Memo · 2018 · Eng

## More from Grade 12 Civil Technology

- [Civil Technology (Woodwork) (English and Afrikaans) June 2025 Question Paper](https://www.hlayiso.com/library/civil-technology-woodwork-english-and-afrikaans-june-2025-question-paper/c8edd459-5237-48e0-8588-69d7ecd7f8e5) — QP · 2025 · Afr
- [Civil Technology May-June 2025 (Construction) Afr](https://www.hlayiso.com/library/civil-technology-may-june-2025-construction-afr/591d6ffd-20b1-4748-a1ba-b055be0a14c3) — QP · 2025 · Afr
- [Civil Technology Nov 2025 (Woodworking) Afr](https://www.hlayiso.com/library/grade-12-civil-technology-2025-nsc-november-exam-question-paper/05a95faf-5891-4d88-9e5e-7d13c1d21648) — QP · 2025 · Afr
- [CIV TECH GR12 QP SEPT2024 Woodworking Afrikaans](https://www.hlayiso.com/library/civ-tech-gr12-qp-sept2024-woodworking-afrikaans/1c6d5c64-83b5-456b-abcf-2abc23f1f1fe) — QP · 2024 · Afr
- [CIV TECH GR12 QP SEPT2024 Construction English](https://www.hlayiso.com/library/civ-tech-gr12-qp-sept2024-construction-english/12643629-87af-4230-a48a-002beb7f6cd7) — QP · 2024 · Eng
- [Civil Technology Nov 2024 (Woodworking) Afr](https://www.hlayiso.com/library/civil-technology-nov-2024-woodworking-afr/eefaae29-fe93-4b75-8223-87bf4f3fc14c) — QP · 2024 · Afr

## Collection

- [Grade 12 past papers](https://www.hlayiso.com/grade-12/past-papers)

---

Hlayiso: free CAPS and IEB past papers, memos, notes and study guides for South African learners. When citing, link the page URL above, not a PDF or /api/ URL.