# Civil Technology Grade 12 NSC June 2022 Memo (English)

> Grade 12 Civil Technology memorandum from the NSC June Exam 2022 (English), 19 pages. Read online or download the free PDF.

- Page: https://www.hlayiso.com/library/civil-technology-may-june-2022-civil-services-mg-eng/c6d3f6fa-e26d-495d-90db-d4024a917da3
- Updated: 2026-10-29
- Subject: Civil Technology
- Grade: Grade 12
- Document type: Memorandum
- Year: 2022
- Exam period: NSC June Exam
- Curriculum: CAPS
- Pages: 19

Breadcrumbs: [Home](https://www.hlayiso.com/) › [Library](https://www.hlayiso.com/library) › [Grade 12](https://www.hlayiso.com/library/grade-12) › [Civil Technology](https://www.hlayiso.com/library/grade-12/civil-technology) › [Civil Technology Grade 12 NSC June 2022 Memo (English)](https://www.hlayiso.com/library/civil-technology-may-june-2022-civil-services-mg-eng/c6d3f6fa-e26d-495d-90db-d4024a917da3)

## About this document

Civil Technology · Grade 12 · NSC June Exam · 2022. Memorandum. Read online or download the PDF.

Read it free online on the page above; download the PDF from there.

## Document text

Text extracted from the PDF. Layout, diagrams and tables may not survive extraction.

### Page 1

Downloaded from hlayiso.com

             SENIOR CERTIFICATE EXAMINATIONS/
         NATIONAL SENIOR CERTIFICATE EXAMINATIONS

                       CIVIL TECHNOLOGY: CIVIL SERVICES

                                          2022

                               MARKING GUIDELINES

                                                                        MARKS: 200

                      These marking guidelines consist of 19 pages

Copyright reserved                                                   Please turn over

### Page 2

Downloaded from hlayiso.com
Civil Technology: Civil Services               2                                      DBE/2022
                                    SC/NSC – Marking guidelines

INSTRUCTIONS FOR THE MARKERS

1.         Markers should:

               Familiarise themselves with the question and answer before evaluating the
                responses of candidates.

               Always interpret the responses of the candidates within the context of the
                question.

               Consider any relevant and acceptable answer during pre-marking but
                should strictly adhere to the answers after finalisation of the marking
                guideline.

               There are TWO approaches to answering questions; these are (1) to
                describe and (2) to explain.
                o If a candidate is required to explain, e.g. a process in 4 steps, only the
                  first 4 responses should be considered.
                o However, if for example a candidate is required to explain or describe
                  how to transfer heights from one point to another using a transparent pipe
                  level we need to consider that candidates may write a long description,
                  not necessarily well organised, as an intellectual response may do. In this
                  case the marker needs to evaluate the complete statement to judge if the
                  candidate explained the required outcome satisfactorily and allocate
                  marks on merit. The marker should apply his/her professional judgement
                  with these types of questions.

               Mark what the candidate wrote and do not award marks for answers that the
                marker thinks the candidate meant with what was written.

               Indicate the tick or cross right at the position where the mark needs to be
                awarded or where the candidate made the error.

               Accept the letter corresponding with the correct answer as well as the
                answer written in full in multiple-choice questions.

               Accept incorrect spelling in one-word answers unless the spelling changes
                the meaning of the answer.
2.         For calculations:

               A mark is only awarded if the correct unit is written next to the answer.

               If TWO marks are awarded ONE mark is awarded for the answer and ONE
                mark for the correct unit.

               Where the candidate made a principle error, e.g. added instead of
                multiplying, no marks will be awarded for the steps. If the answer is correct
                according to what the candidate did, the mark for the answer can be
                awarded for the application of skills.

Copyright reserved                                                                Please turn over

### Page 3

Downloaded from hlayiso.com
Civil Technology: Civil Services               3                                     DBE/2022
                                    SC/NSC – Marking guidelines

               Where an incorrect answer could be carried over to the next step, the first
                answer will be deemed incorrect. However, should the incorrect answer be
                carried over correctly, the marker has to recalculate the values, using the
                incorrect answer from the first calculation. If correctly used, the candidate
                should receive the full marks for subsequent calculations.

               Markers should consider when and where a candidate has rounded off in a
                calculation, as well as the subsequent effect it has on the final answer
                obtained. The calculation should therefore be awarded marks on merit.

               Alternative methods of calculations must be considered, provided that the
                correct answer is obtained.

3.         When marking drawings:

               The member for which the mark should be awarded should be drawn
                correctly in the correct position to receive a mark.

               A member incorrectly drawn but wrongfully repeated in another position will
                be awarded the mark for the repeated incorrect member provided that the
                marking guideline provide for TWO or more marks for that member (positive
                marking).

               Marks can only be awarded for a label if the label is correctly indicating the
                correct member.

               Scale drawings should always be marked using an appropriate mask.
           When a candidate drew the wrong drawing, e.g.:

               A horizontal section instead of a vertical section, no marks will be allocated
                to the drawing as the candidate did not respond to the expected outcome.

               An orthographic view instead of sectional view, no marks will be allocated to
                the drawing as the candidate did not respond to the expected outcome.

               An orthographic view instead of an isometric view, no marks will be
                allocated to the drawing as the candidate did not respond to the expected
                outcome.

               If the incorrect drawing was drawn, the candidate can be awarded for only
                what was asked but mark/s for the correctness of the drawing will not be
                awarded e.g., if a King Post roof truss was asked in the question, and
                candidate drew SA-Howe Truss

Copyright reserved                                                               Please turn over

### Page 4

Downloaded from hlayiso.com
Civil Technology: Civil Services                4                                   DBE/2022
                                     SC/NSC – Marking guidelines

QUESTION 1:          OHSA, MATERIALS,           TOOLS,      EQUIPMENT     AND   JOINING
                     (GENERIC)

1.1        1.1.1        Thermo plastic/Thermo plastic powder coating                              (1)

           1.1.2        Electroplating                                                            (1)

           1.1.3        Curing                                                                    (1)

           1.1.4        Paint/Varnish                                                             (1)

           1.1.5        Galvanising                                                               (1)

1.2        1.2.1        Non-skid material should be fitted to:
                         Prevent ladders from moving when workers are using
                           them 
                         Ensure stability of the ladder when in use
                        ANY ONE OF THE ABOVE                                                       (1)

           1.2.2        Wooden ladders are better:
                         To prevent electrical shock 
                         Because it is a poor conductor of electricity
                        ANY ONE OF THE ABOVE                                                       (1)

           1.2.3        Aluminium ladder is:
                         Lighter 
                         More durable
                         Easier to handle
                         Easy to clean
                         Stronger
                         Suitable to extend to higher hights
                        ANY ONE OF THE ABOVE                                                       (1)

           1.2.4        Wooden ladders can be treated with:
                         Linseed Oil/Oil 
                         Clear varnish/Varnish 
                         Wood preservative/Preservative
                        ANY TWO OF THE ABOVE                                                       (2)

1.3        The scaffold platform:
            Must have guard rails 
            Must have toe boards 
            Should have sufficient room between the structure and the platform for
               the worker to sit and work
            Must be free of any obstruction/waste/projecting nails/equipment that can
               cause injury
            Must be non-slip
            Should not be filled with unnecessary equipment/Overloaded
           ANY TWO OF THE ABOVE                                                                    (2)

Copyright reserved                                                              Please turn over

### Page 5

Downloaded from hlayiso.com
Civil Technology: Civil Services                5                                 DBE/2022
                                     SC/NSC – Marking guidelines

1.4        A safety net can be erected:
            Above an entrance 
            At passageways 
            At areas where persons work while work is being performed above them
            To prevent falling objects from injuring workers
           ANY TWO OF THE ABOVE                                                                  (2)

1.5        1.5.1        Rawlbolt/Expansion bolt/Anchor bolt                                     (1)

           1.5.2            Drill hole 
                            Remove debris/Clean the hole 
                            Remove the bolt and washer/insert the shield                       (3)

1.6        Dumpy level determines:
            Levels and heights 
            Differences between levels and vertical heights
            Levels and slopes
            Distances
           ANY ONE OF THE ABOVE                                                                  (1)

           Protect the dumpy level by:
            Placing the telescope in its case directly after use 
            Not bumping the instrument against objects
            Not dropping the instrument
            Performing the collimation test regularly to ensure accuracy
            Keeping it dry
           ANY ONE OF THE ABOVE                                                                  (1)
                                                                                                 [20]

Copyright reserved                                                            Please turn over

### Page 6

Downloaded from hlayiso.com
Civil Technology: Civil Services              6                                         DBE/2022
                                   SC/NSC – Marking guidelines

QUESTION 2: GRAPHICS AS MEANS OF COMMUNICATION (GENERIC)
ANSWER SHEET 2

NO.                     QUESTIONS                                ANSWERS                      MARKS

        Identify the scale that was used for the     1:500 
  1                                                                                                2
        site plan and the floor plan respectively.   1:100 

        Who is responsible for checking the
  2                                                  C. Lee                                       1
        building plan?

        What type of fencing does the architect
  3                                                  Precast concrete fencing                     1
        recommend for the new dwelling?

        Name the town where the new dwelling
  4                                                  Jeffreys Bay                                 1
        will be erected.

  5     What was done as revision 1?                 Window in room A                             1

  6     Identify number 1.                           Municipal sewer line/Sewer line              1

        Identify number 3 by giving the
  7                                                  MH                                           1
        abbreviation.

  8     Identify number 4.                           New dwelling                                 1

  9     Identify number 5.                           Earth                                        1

 10     Identify number 9.                           Distribution board/DB                        1

 11     Identify number 11.                          One-way switch-double pole                   1
                                                     Sink unit-single/Single bowl
 12     Identify number 12.                                                                        1
                                                     sink/Sink 
        Identify the number that indicates the
 13                                                  8                                            1
        boundary line.
                                                     For pedestrians/Area dedicated for
 14     Describe the purpose of number 2.                                                          1
                                                     walking 
        Deduce the plot number of the existing
 15                                                  Plot 73                                      1
        dwelling from FIGURE A.
        What is omitted in Maple Street with         Municipal connection/Municipal
 16                                                                                                1
        reference to number 6?                       manhole 

Copyright reserved                                                                  Please turn over

### Page 7

Downloaded from hlayiso.com
Civil Technology: Civil Services              7                                       DBE/2022
                                   SC/NSC – Marking guidelines

        What leisure feature is located on the
 17                                                 Swimming pool                               1
        site plan?

                                                                   
        Draw the north symbol to show that the                     
 18                                                                                              3
        driveway side is facing east.
                                                                    OR
                                                    Direction 
        What is the purpose of the north symbol To indicate the direction/
 19                                                                                              1
        on a house plan?                        elevation 
 20     Which feature indicates that this is a      Staircase/Stairs                            1
        double storey building?
                                                    Dimension incorrectly indicated as
                                                    110 mm of outside wall 
 21     Deduce THREE faults from bedroom 2.         No electrical connection from light          3
                                                    switch to the light fitting/ 
                                                    No wiring 
                                                    Window symbol incorrect

 22     Draw the symbol for a wash tub.                                                        2
                                                                            

 23     Draw the symbol for a bath.                                              
                                                                                                 2

 24     Draw the symbol for a water meter.                                                       2
                                                                          

                                                        Omitted dimensions/
                                                         Measurements 
                                                        No levels/heights/invert
                                                         levels/corner heights
        Describe TWO reasons why the local               indicated 
 25     municipality would not approve                                                           2
                                                        Impossible to position new
        FIGURE A.                                        dwelling
                                                        No north symbol
                                                        Incomplete sewage layout
                                                        No contour lines indicated
                                                                              
        Calculate the length of the house.          4 000 + 5 000 + 4 000 + 4 000
        Give your answer in m.                                                                 6
 26
        Show all calculations.                      + 220 +220 + 110 + 110 +110
                                                    = 17 770 
                                                    = 17,77  m
                                                                               TOTAL:            40
Copyright reserved                                                              Please turn over

### Page 8

Downloaded from hlayiso.com
Civil Technology: Civil Services                    8                          DBE/2022
                                         SC/NSC – Marking guidelines

QUESTION 3:          CONSTRUCTION ASSOCIATED WITH CIVIL SERVICES, OHSA
                     AND QUANTITIES (SPECIFIC)

3.1        3.1.1        76 mm x 50 mm                                                        (1)

           3.1.2        Water-logged ground                                                  (1)

           3.1.3        1:90                                                                 (1)

           3.1.4        Spirit level                                                         (1)

           3.1.5        150 mm                                                               (1)

3.2.1      Precautions that are used to safeguard the area around an opened manhole:
            The area must be cordoned off/Use a barrier net/barrier tape 
            Warning signs/safety signs must be posted.
            Warning lights must be placed around the perimeter.
           ANY ONE OF THE ABOVE                                                               (1)

3.2.2      Ways to enter a manhole:
            Step irons 
            Safety harness and rope/rope 
            Ladder
           ANY TWO OF THE ABOVE                                                               (2)

Copyright reserved                                                         Please turn over

### Page 9

Downloaded from hlayiso.com
Civil Technology: Civil Services              9                              DBE/2022
                                   SC/NSC – Marking guidelines

                                                        
3.3                                                                              INLET

                                                                 

                                                           
        BRICK WALL
                                                                                    BRANCH
                                                                                      PIPE
       BENCHING

                                                                 

                                                                                 OUTLET
           Application of 
      scaleMark this drawing with a mask.

                       ASSESSMENT CRITERIA         MARK
                 Correctness of drawing:
                 Thickness of the wall               2
                 Ø110 mm main pipe and channel       1
                 Ø110 mm branch pipe and channel     1
                 Hatching lines of the wall          1
                 Direction of flow                   2
                 Application of scale                1
                                            TOTAL:   8

Copyright reserved                                                       Please turn over

### Page 10

Downloaded from hlayiso.com
Civil Technology: Civil Services                  10                                    DBE/2022
                                       SC/NSC – Marking guidelines

 3.4

   A             B                 C                                 D
                                              Area of walls
  1/      6,82 m                            Centre line of walls = 6,82 m
           1,3 m          8,866 m²          Height of wall for manhole = 1 300 mm      (4)
                                              Area of walls is 8,866 m²

                                              Number of bricks
  2/      8,866                             Area of walls = 8,87 m²
           50             886,6 bricks       Height of wall for manhole = 1 300 mm      (4)
                                              50 bricks per m² for a ½ brick wall
                                              887 bricks are needed 

                 OR
   1/      8,866
           100             886,6 bricks       887 bricks are needed

                 OR
   2/      6,82 m
           1,3 m
           50              886,6 bricks       887 bricks are needed

                 OR
   1/      6,82 m
           1,3 m
           100             886,6 bricks       887 bricks are needed
                                                                                                       (8)

Copyright reserved                                                                  Please turn over

### Page 11

Downloaded from hlayiso.com
Civil Technology: Civil Services                  11                         DBE/2022
                                       SC/NSC – Marking guidelines

3.5

                                                                  
                                                                    

                                         QUEEN CLOSERS

                       ASSESSMENT CRITERIA                 MARK
                     Correctness of drawing:
                     Header course                            2
                     Queen closers                            4
                                           TOTAL:             6
                                                                                            [30]

Copyright reserved                                                       Please turn over

### Page 12

Downloaded from hlayiso.com
Civil Technology: Civil Services               12                                  DBE/2022
                                    SC/NSC – Marking guidelines

QUESTION 4:          COLD- AND HOT-WATER SUPPLY, TOOLS, EQUIPMENT AND
                     MATERIALS (SPECIFIC)

4.1        4.1.1             I                                                                   (1)

           4.1.2             D                                                                   (1)

           4.1.3             J                                                                   (1)

           4.1.4             F                                                                   (1)

           4.1.5             B                                                                   (1)

           4.1.6             A                                                                   (1)

           4.1.7             H                                                                   (1)

           4.1.8             C                                                                   (1)

4.2        4.2.1     Pressure-control valve                                                      (1)

           4.2.2     Hot-water storage tank                                                      (1)

4.3      Fault when cold water flows from hot-water tap:
           Power is off 
           Pipes were incorrectly connected
           Setting of the thermostat may be too low
           Thermostat is malfunctioning
           Element is malfunctioning
         ANY ONE OF THE ABOVE                                                                     (1)

4.4        4.4.1     Step 1: Loosen the compression nut 
                     Step 2: Use a pipe cutter to cut off the piece of pipe containing
                              the compression ring/ferrule 
                     Step 3: Ream the pipe after cutting it 
                     Step 4: Insert compression nut and new ring over pipe and fasten            (4)

           4.4.2     Open the water supply to check for leaks.                                   (1)

4.5        Water-saving wash basin taps:
            Electronic tap/Electric tap/Tap with sensors 
            Metered taps 
            Demand taps
           ANY TWO OF THE ABOVE                                                                   (2)

Copyright reserved                                                             Please turn over

### Page 13

Downloaded from hlayiso.com
Civil Technology: Civil Services                13                                DBE/2022
                                     SC/NSC – Marking guidelines

4.6        4.6.1     Flat plate collector                                                       (1)
           4.6.2     To receive direct sunlight for the entire day                              (1)
           4.6.3     Non-return valve                                                           (1)

          4.6.4      THREE disadvantages of solar heating panels:
                      Can be a safety hazard – the tubes can explode due to build
                        up of heat that cannot be pumped out in time 
                      Heating capacity depends on the sun – in winter the system
                        may not function at full capacity 
                      There is no guarantee that the water will always be hot 
                      Leakage that results when tubes explode can damage ceilings
                        and furniture
                      Corrosion of the components
                      Initially requires high capital investment
                      If one glass tube breaks, the system must be shut down
                      ANY THREE OF THE ABOVE                                                     (3)
4.7        4.7.1 T-junction 90° single reducing                                                 (1)
           4.7.2     uPVC  /unplasticised polyvinyl chloride/PVC                                (1)

           4.7.3     This fitting can be used:
                      For T-shaped connection of soil pipes and waste pipes with a
                         different diameter 
                      To join 110 mm pipes in a straight line and 40/50 mm pipes at 90°
                     ANY ONE OF THE ABOVE                                                        (1)

           4.7.4     The purpose of the inspection eye is for:
                      Inspection and testing purposes 
                      Access to plumbing rods to clear out blockages
                     ANY ONE OF THE ABOVE                                                        (1)

4.8        4.8.1     Capstan head                                                               (1)

           4.8.2     The jumper holds the washer in place.  /moves up and down, and
                     moves washer upwards or downwards.                                          (1)

           4.8.3     If the washer is not fitted:
                      Water will leak from the pillar tap 
                      The inlet water supply will not be sealed
                     ANY ONE OF THE ABOVE                                                        (1)

           4.8.4        The pillar tap can be used for a:
                         Bath 
                         Wash hand basin
                         Sink
                         Wash tub
                        ANY ONE OF THE ABOVE                                                     (1)

Copyright reserved                                                            Please turn over

### Page 14

Downloaded from hlayiso.com
Civil Technology: Civil Services                14                                     DBE/2022
                                     SC/NSC – Marking guidelines

4.9        4.9.1            Drain-cleaning machine/Jetting machine                                  (1)

           4.9.2        The elements that will ensure the efficient removal of blockages:
                         High pressure 
                         Flow rate of the solution 
                         Type of cleaning solution used
                         Heat setting of the machine
                        ANY TWO OF THE ABOVE                                                          (2)

4.10       It is important to clean the drain rods after use in order to remove:
            Harmful bacteria 
            Unpleasant smells
           ANY ONE OF THE ABOVE                                                                       (1)

4.11       To avoid galvanic corrosion                                                               (1)

4.12       A visible sign of dezincification:
            A white powder on the metal surface 
            Brass turns red                                                                         (2)

4.13       Hydrochloric acid                                                                         (1)
                                                                                                      [40]

Copyright reserved                                                                 Please turn over

### Page 15

Downloaded from hlayiso.com
Civil Technology: Civil Services               15                                         DBE/2022
                                    SC/NSC – Marking guidelines

QUESTION 5:          GRAPHICS AS MEANS OF COMMUNICATION, ROOF WORK AND
                     STORMWATER (SPECIFIC)

5.1.1      Pre-fabricated surface channel:
               It is stronger than mass concrete 
               Withstand the force of water flow 
               Handles water flow/large volumes of water flow
           ANY TWO OF THE ABOVE                                                                          (2)

5.1.2      Concrete shoe should have a fall/slope:
           To allow water to flow away from the building.                                               (1)

5.2

                                    FASCIA BOARD

                                                                      
                             SQUARE GUTTER
                                                                 
                                   GUTTER CLIP

                                                                      
                                          OFFSET

                                                                                  
                                           HOLDER BAT

                                              DOWN PIPE
                                                                              

            ASSESSMENT CRITERIA                     MARK
 Correctness of drawing:
 Fascia board                                          1              
 Square gutter                                         1
 Gutter clip/bracket                                   1
 Offset                                                1
 Down pipe                                             1
 Holder bats                                           2                  
 Rainwater shoe                                        1
                                        TOTAL:         8
                                                                                  RAINWATER SHOE

Copyright reserved                                                                    Please turn over

### Page 16

Downloaded from hlayiso.com
Civil Technology: Civil Services                       16                                           DBE/2022
                                            SC/NSC – Marking guidelines
5.3

                                                                       5
                                                                  5
                                                                                           6
                                                            5
                                                       5                             4
                                                  5
                                            5

                                       5

                     1

                             2                                             4
                                                                                      3
      2             2          2

                                                  4

                                                                                 3
                                             6

                             A

           USE A MASK TO MARK DRAWING

          A MAXIMUM OF 17 MARKS WILL BE AWARDED IF THE DEVELOPMENT OF PIPE A WAS
           NOT CORRECTLY PROJECTED.

          A MAXIMUM OF 5 MARKS WILL BE AWARDED IF PIPE A WAS NOT DEVELOPED
           (1 MARK - DIVIDING CIRCLE; 2 MARKS - VERTICAL PROJECTION LINES; 2 MARKS -
            DIVIDING CIRCUMFERENCE)

 NO              ASSESSMENT CRITERIA                        MARK
          Correctness of drawing:
  1       Dividing circle in 12 parts (auxiliary view)       1
  2       Projection lines                                   4
  3       Dividing development into 12 parts (Any
                                                             2
          acceptable method)
  4       Outside lines of base and sides                     3
  5       Outside lines of development (curve)                7
  6       3 mm seam on both sides                             2                                                    (19)
                                              TOTAL:         19                                                    [30]
Copyright reserved                                                                              Please turn over

### Page 17

Downloaded from hlayiso.com
Civil Technology: Civil Services                  17                             DBE/2022
                                       SC/NSC – Marking guidelines

QUESTION 6: SEWERAGE, SANITARY FITTINGS AND JOINING (SPECIFIC)

6.1        6.1.1        C                                                                      (1)

           6.1.2        B                                                                      (1)

           6.1.3        A                                                                      (1)

           6.1.4        B                                                                      (1)

           6.1.5        C                                                                      (1)

6.2        6.2.1        A - Overflow 
                        B - Wiped joint 
                        C - P-trap                                                             (3)

           6.2.2        P-trap:
                         Traps water 
                         To make a seal to keep bad odours out                                (2)

           6.2.3        Overflow:
                         Allows extra water to flow through the waste pipe 
                         Ensures that water does not over flow the hand wash basin
                        ANY ONE OF THE ABOVE                                                    (1)

6.3                                          
                                   
                                                                                                (2)

6.4        60 degrees /60°                                                                     (1)

6.5       Flux:
           To clean the material to be soldered 
           Promotes the flow of solder during soldering
         ANY ONE OF THE ABOVE                                                                   (1)

6.6        French drain:
            Allows the liquid from the septic tank to seep into the ground 
            Grey water channelled to a French drain will seep into the ground
           ANY ONE OF THE ABOVE                                                                 (1)

6.7        The water in the borehole can become contaminated.                                  (1)

Copyright reserved                                                           Please turn over

### Page 18

Downloaded from hlayiso.com
Civil Technology: Civil Services              18                                DBE/2022
                                   SC/NSC – Marking guidelines

6.8
                                               
                                                                

                                                                          

                                                                              
                                                 

                                                                                       (10)

                     ASSESSMENT CRITERIA           MARK
            Correctness of drawing:
            Concrete base                             1
            Outside wall                              1
            Partition wall                            1
            Opening                                   1
            Outlet                                    2
            Concrete slab on top                      1
            Manhole cover                             2
            Hatching (Any ONE wall)                   1
                                        TOTAL:       10

Copyright reserved                                                       Please turn over

### Page 19

Downloaded from hlayiso.com
Civil Technology: Civil Services                      19                                   DBE/2022
                                           SC/NSC – Marking guidelines

6.9

RE          IE                                                         
                            IE        IE
            IE      IE                                                       
  VP                               G                                                      
                                                                                   IE      IE        RE 
                                                                                                      
            HWB                        S                                            IE           
       WC                                                                    RE                 VP
                     SH
                                                                                        HWB
                                                                                                WC

FOR THE JUNCTIONS OF THE TWO MAIN SEWER LINES 45° LINES WILL ALSO
BE ACCEPTED

                    ASSESSMENT CRITERIA          MARK
                    Correctness of drawing:
                    Branch pipes (ANY TWO)         2
                    Vent pipes                     2
                    Gully                          1
                    Junction of two main sewer
                                                   2
                    pipes (curved/45° angle)
                    Rodding eyes                   3
                    Inspection eyes (ANY THREE)    3
                                          TOTAL:  13
                                                                                                      [40]

                                                                                         TOTAL::      200

Copyright reserved

## Related documents

- [Civil Technology May June 2022 (Woodworking) Eng](https://www.hlayiso.com/library/civil-technology-may-june-2022-woodworking-eng/6bfe9199-25cf-4c12-8dc6-817a01e3c184) — Civil Technology · QP · 2022 · Eng
- [Civil Technology May June 2022 (Civil Services) Afr](https://www.hlayiso.com/library/civil-technology-may-june-2022-civil-services-afr/a141cdd2-0859-4ede-bb4e-499b3261db3d) — Civil Technology · QP · 2022 · Afr
- [Civil Technology May June 2022 (Woodworking) Afr](https://www.hlayiso.com/library/civil-technology-may-june-2022-woodworking-afr/b7830db2-93f0-405b-b704-e06c38ed8339) — Civil Technology · QP · 2022 · Afr
- [Civil Technology May June 2022 (Civil Services) Eng](https://www.hlayiso.com/library/civil-technology-may-june-2022-civil-services-eng/97927c67-c7a8-40fb-af20-ad306ca6284c) — Civil Technology · QP · 2022 · Eng
- [Civil Technology May June 2022 (Construction) Afr](https://www.hlayiso.com/library/civil-technology-may-june-2022-construction-afr/c4a7cdae-7306-4e0c-a474-e8856468ab9d) — Civil Technology · QP · 2022 · Afr
- [CIV TECH GR12 MEMO SEPT2022 Civil Services Afrikaans](https://www.hlayiso.com/library/civ-tech-gr12-memo-sept2022-civil-services-afrikaans/e517a483-4536-458b-945a-1e2a6820fc1b) — Civil Technology · Memo · 2022 · Afr

## More from Grade 12 Civil Technology

- [Civil Technology (Woodwork) (English and Afrikaans) June 2025 Question Paper](https://www.hlayiso.com/library/civil-technology-woodwork-english-and-afrikaans-june-2025-question-paper/c8edd459-5237-48e0-8588-69d7ecd7f8e5) — QP · 2025 · Afr
- [Civil Technology May-June 2025 (Construction) Afr](https://www.hlayiso.com/library/civil-technology-may-june-2025-construction-afr/591d6ffd-20b1-4748-a1ba-b055be0a14c3) — QP · 2025 · Afr
- [Civil Technology Nov 2025 (Woodworking) Afr](https://www.hlayiso.com/library/grade-12-civil-technology-2025-nsc-november-exam-question-paper/05a95faf-5891-4d88-9e5e-7d13c1d21648) — QP · 2025 · Afr
- [CIV TECH GR12 QP SEPT2024 Woodworking Afrikaans](https://www.hlayiso.com/library/civ-tech-gr12-qp-sept2024-woodworking-afrikaans/1c6d5c64-83b5-456b-abcf-2abc23f1f1fe) — QP · 2024 · Afr
- [CIV TECH GR12 QP SEPT2024 Construction English](https://www.hlayiso.com/library/civ-tech-gr12-qp-sept2024-construction-english/12643629-87af-4230-a48a-002beb7f6cd7) — QP · 2024 · Eng
- [Civil Technology Nov 2024 (Woodworking) Afr](https://www.hlayiso.com/library/civil-technology-nov-2024-woodworking-afr/eefaae29-fe93-4b75-8223-87bf4f3fc14c) — QP · 2024 · Afr

## Collection

- [Grade 12 past papers](https://www.hlayiso.com/grade-12/past-papers)

---

Hlayiso: free CAPS and IEB past papers, memos, notes and study guides for South African learners. When citing, link the page URL above, not a PDF or /api/ URL.