# Civil Technology Grade 12 NSC November 2015 QP (Eng)

> Grade 12 Civil Technology question paper from the NSC November Exam 2015 (English), 28 pages. Read online or download the free PDF.

- Page: https://www.hlayiso.com/library/civil-technology-nov-2015-eng-r/8e33f148-adde-4af4-be2d-6a45bccfb5d5
- Updated: 2026-09-27
- Subject: Civil Technology
- Grade: Grade 12
- Document type: Question paper
- Year: 2015
- Exam period: NSC November Exam
- Curriculum: CAPS
- Pages: 28

Breadcrumbs: [Home](https://www.hlayiso.com/) › [Library](https://www.hlayiso.com/library) › [Grade 12](https://www.hlayiso.com/library/grade-12) › [Civil Technology](https://www.hlayiso.com/library/grade-12/civil-technology) › [Civil Technology Grade 12 NSC November 2015 QP (Eng)](https://www.hlayiso.com/library/civil-technology-nov-2015-eng-r/8e33f148-adde-4af4-be2d-6a45bccfb5d5)

## About this document

Civil Technology · Grade 12 · NSC November Exam · 2015. Question paper, 28 pages. Read online or download the PDF.

Read it free online on the page above; download the PDF from there.

## Document text

Text extracted from the PDF. Layout, diagrams and tables may not survive extraction.

### Page 1

Downloaded from hlayiso.com

                                 GRAAD 12

                                NATIONAL
                           SENIOR CERTIFICATE

                                 GRADE 12

                             CIVIL TECHNOLOGY

                             NOVEMBER 2015 (R)

MARKS: 200

TIME: 3 hours

  This question paper consists of 19 pages, 8 answer sheets and a formula sheet.

Copyright reserved                                                  Please turn over

### Page 2

Downloaded from hlayiso.com
Civil Technology                             2                       DBE/November 2015 (R)
                                            NSC

REQUIREMENTS:

1.        Drawing instruments

2.        A non-programmable pocket calculator

3.        ANSWER BOOK

INSTRUCTIONS AND INFORMATION

1.        This question paper consists of SIX questions.

2.        Answer ALL the questions.

3.        Answer each question as a whole. Do NOT separate subsections of
          questions.

4.        Start the answer to EACH question on a NEW page.

5.        Do NOT write in the margin of the ANSWER BOOK.

6.        You may use sketches to illustrate your answers.

7.        Write ALL calculations and answers in the ANSWER BOOK or on the
          attached ANSWER SHEETS.

8.        Use the mark allocation as a guide to the length of your answers.

9.        Make drawings and sketches in pencil, fully dimensioned and neatly finished
          off with descriptive titles and notes to conform to the SANS/SABS Code of
          Practice for Building Drawings.

10.       For the purpose of this question paper, the size of a brick should be taken as
          220 mm x 110 mm x 75 mm.

11.       Use your own discretion where dimensions and/or details have been omitted.

12.       Answer QUESTIONS 1.10.1, 1.11.4, 1.11.5, 2.10, 4.3, 5.2, 5.3, 6.1 and 6.2
          on the attached ANSWER SHEETS using drawing instruments, where
          necessary.

13.       Write your CENTRE NUMBER and EXAMINATION NUMBER on every
          ANSWER SHEET and hand them in with your ANSWER BOOK, whether you
          have used them or not.

14.       Due to electronic transfer, drawings in the question paper are NOT to scale.

Copyright reserved                                                            Please turn over

### Page 3

Downloaded from hlayiso.com
Civil Technology                             3                        DBE/November 2015 (R)
                                            NSC

QUESTION 1: CONSTRUCTION, SAFETY AND MATERIALS

1.1       FIGURE 1.1 below shows a building site. Recommend TWO arrangements
          that a safety officer should make to prevent accidents such as those in
          the picture.

                                      FIGURE 1.1                                                (2)

1.2       Describe TWO safety measures that must be adhered to when using a
          crosscut saw.                                                                         (2)

1.3       Explain ONE safety regulation to protect the public when excavations
          are done.                                                                             (1)

1.4       If you want to preserve plastic objects you can either paint them with a brush
          or use spray paint. Recommend the best method to use. Motivate your
          answer.                                                                               (2)

1.5       Differentiate between an I-beam and           an   H-beam     by   drawing    a
          two-dimensional line diagram of each.                                                 (2)

1.6       Describe ONE function of admixtures in concrete.                                      (1)

1.7       Name ONE admixture that can be used in concrete.                                      (1)

1.8       Describe TWO disadvantages of a thatched roof.                                        (2)

1.9       Name TWO types of roof covering that are commonly used, other than
          thatched roof covering.                                                               (2)

Copyright reserved                                                           Please turn over

### Page 4

Downloaded from hlayiso.com
Civil Technology                                  4                       DBE/November 2015 (R)
                                                 NSC

1.10      FIGURE 1.10 below shows a section through a brick parapet wall with
          a lean-to roof.

                                            FIGURE 1.10

          1.10.1         Draw, on ANSWER SHEET 1.10, the flashing where the roof is
                         joined to the wall.                                                         (2)

          1.10.2         Name ONE type of material that can be used as flashing.                     (1)

          1.10.3         Explain the purpose of flashing if installed in FIGURE 1.10.                (1)

1.11      FIGURE 1.11 below shows the front elevation of a one-brick wall. Study the
          drawing and answer the questions that follow.

                     A                                                               A

                                               FIGURE 1.11

          1.11.1         Identify the bond used to build the wall.                                   (1)

          1.11.2         State TWO properties of the bond used to build the wall.                    (2)

          1.11.3         Describe in your own words how a wall can be finished after being
                         plastered.                                                                  (1)

          1.11.4         Draw the end view of this wall on ANSWER SHEET 1.11.                        (2)

          1.11.5         Use ANSWER SHEET 1.11 and project and draw, from the given
                         front elevation, the plan course of a T-junction of course AA. The
                         T-junction is from the fourth brick from the left-hand side of the
                         drawing, as indicated by the cross.                                         (4)

1.12      Name ONE material that can be used as ceiling boards.                                      (1)
                                                                                                     [30]
Copyright reserved                                                                Please turn over

### Page 5

Downloaded from hlayiso.com
Civil Technology                              5                     DBE/November 2015 (R)
                                             NSC

QUESTION 2: ADVANCED CONSTRUCTION AND EQUIPMENT

Start this question on a NEW page.

2.1       FIGURE 2.1 below shows a power tool used on a construction site.

                                         FIGURE 2.1

          2.1.1       Identify the power tool in FIGURE 2.1.                                  (1)

          2.1.2       Explain ONE use of this power tool.                                     (1)

          2.1.3       Justify the use of the equipment in FIGURE 2.1 instead of a
                      hand saw.                                                               (2)

2.2       Explain how you will use a transparent pipe level to transfer levels from one
          point to another.                                                                   (2)

2.3       FIGURE 2.3 below shows a portable generator. Explain, in your own words,
          the purpose of a generator on a building site.

                                       FIGURE 2.3                                             (1)

Copyright reserved                                                         Please turn over

### Page 6

Downloaded from hlayiso.com
Civil Technology                               6                        DBE/November 2015 (R)
                                              NSC

2.4       FIGURE 2.4 below shows a component used in reinforced concrete
          structures.

                                         FIGURE 2.4

          2.4.1       Identify the component in FIGURE 2.4 (NOT the steel bars).                   (1)

          2.4.2       Describe the purpose of the component in FIGURE 2.4 (NOT the
                      steel bars).                                                                 (1)

2.5       FIGURE 2.5 below shows an incomplete elevation of a type of suspended
          floor construction.

              A

                                         FIGURE 2.5

          2.5.1       Name the type of floor construction in FIGURE 2.5.                           (1)

          2.5.2       Block A in this type of floor construction can be made of concrete
                      or polystyrene. Describe TWO advantages of using polystyrene
                      blocks instead of concrete blocks.                                           (2)

          2.5.3       Justify why you would rather use the type of floor construction in
                      FIGURE 2.5 than an in situ cast suspended floor.                             (3)

2.6       Arches can be built in three basic shapes.

          2.6.1       Name any TWO shapes in which arches can be built.                            (2)

          2.6.2       Give the name of the last brick that is laid when building an arch.          (1)

2.7       Differentiate between the purpose of a slump test and that of a cube test.               (2)

Copyright reserved                                                              Please turn over

### Page 7

Downloaded from hlayiso.com
Civil Technology                              7                        DBE/November 2015 (R)
                                             NSC

2.8       FIGURE 2.8 below shows the front elevation of the reinforcement of a beam
          and column.

                                                               A

                                                               B
                                                               C

                                                               D

                                         FIGURE 2.8

          2.8.1       Name parts A to D.                                                           (4)

          2.8.2       Justify why you would use ribbed bars rather than plain round bars
                      as reinforcement.                                                            (1)

2.9       FIGURE 2.9 below shows the formwork for a concrete staircase. Study the
          picture and answer the questions that follow.

                                                                            A

                                                                            B

                                                                            C

                                                                            D

                                         FIGURE 2.9

          2.9.1       Identify part A.                                                             (1)

          2.9.2       Recommend a suitable height for the rise at B.                               (1)

          2.9.3       Identify part C.                                                             (1)

          2.9.4       Identify part D.                                                             (1)
Copyright reserved                                                              Please turn over

### Page 8

Downloaded from hlayiso.com
Civil Technology                             8                       DBE/November 2015 (R)
                                            NSC

2.10      FIGURE 2.10 below shows an incomplete sectional view of a cavity wall with
          a cavity of 50 mm between the walls.

          Use ANSWER SHEET 2.10 to draw the following:

             The symbol for a concrete foundation and concrete floor                          (1)
             The damp-proof course between the walls and the cavity                           (2)
             The damp-proof under the concrete floor                                          (2)
             The weep hole                                                                    (1)
             The concrete in the cavity wall                                                  (1)
             The wall tie                                                                     (1)
             Show the dimension of the total width of the wall.                               (1)

                                          FIGURE 2.10

2.11      Name the type of foundation that will be used when ground conditions are not
          suitable to use normal strip foundation.                                             (1)

2.12      A large open space in a multi-storey building needs to be converted into
          offices. The floor cannot support the load of brick walls. Recommend a type of
          light-weight wall that can be used.                                                  (1)
                                                                                               [40]

Copyright reserved                                                          Please turn over

### Page 9

Downloaded from hlayiso.com
Civil Technology                             9                          DBE/November 2015 (R)
                                            NSC

QUESTION 3: CIVIL SERVICES

Start this question on a NEW page.

3.1       Choose a description from COLUMN B that matches an item in COLUMN A.
          Write only the letter (A–I) next to the question number (3.1.1–3.1.7) in the
          ANSWER BOOK, for example 3.1.8 J.

                           COLUMN A                                 COLUMN B
          3.1.1       Inspection eye             A   it is installed at a water closet at the
                                                     highest point of a site sewerage
          3.1.2       Ventilation pipe               system

          3.1.3       Rodding eye                B   it is installed at points where
                                                     drainpipes change direction and
          3.1.4       Manhole                        where several sewer pipes meet

          3.1.5       French drain               C   a simple removable cover where
                                                     a branch pipe and a main sewer
          3.1.6       Septic tank                    pipe meet

          3.1.7       Conservancy tank           D   a trench filled with stones and
                                                     covered with a layer of sand

                                                 E   it is installed at least every 25 m
                                                     along a site drainage system where
                                                     no manhole is placed

                                                 F   it stores sewage until it can be
                                                     removed by the municipality

                                                 G   the breakdown of solid human
                                                     waste occurs by means of
                                                     anaerobic bacterial action in
                                                     this system

                                                 H   it is placed every 50 m along a
                                                     sewerage system

                                                 I   it should be cleaned regularly with
                                                     chemicals
                                                                                    (7 x 1)         (7)

3.2       Predict the consequence of not installing the following in a sewerage system:

          3.2.1       A gully                                                                       (1)

          3.2.2       A rodding eye or manhole                                                      (1)

3.3       Name TWO methods that can be used to provide hot water to a household.                    (2)

Copyright reserved                                                               Please turn over

### Page 10

Downloaded from hlayiso.com
Civil Technology                              10                      DBE/November 2015 (R)
                                             NSC

3.4       Describe ONE method that is used in South Africa to extract water from
          a borehole.                                                                           (1)

3.5       Name ONE other source that will supply water for human consumption.                   (1)

3.6       FIGURE 3.6 below shows the front elevation of a shower rose without the
          pipes and taps.

          Draw, in your ANSWER BOOK, a single-line diagram to show the basic cold
          and hot water pipe layout for a shower. Show the following in your drawing:

             Cold-water inlet pipe
             Hot-water inlet pipe
             Hot- and cold-water taps (no mixer tap)
             Supply pipe to the shower rose
             Water flow direction from the taps to the shower rose

                                                        Shower rose

                                           FIGURE 3.6                                           (5)

3.7       Identify the following drawing symbols:

          3.7.1
                                                                                                (1)

          3.7.2
                                                                                                (1)

          3.7.3                                                                                 (1)

3.8       Explain how you, as a property owner, will ensure that large quantities of
          storm water are channelled to the municipal connection.                               (2)

Copyright reserved                                                           Please turn over

### Page 11

Downloaded from hlayiso.com
Civil Technology                                11                        DBE/November 2015 (R)
                                               NSC

3.9       FIGURE 3.9 below shows the electrical layout of a house. Study the
          illustration and answer the questions that follow.

                                         A
                                                       D
                                                                        E

                                         B

                                                                        F

                                                   C

                                          FIGURE 3.9

          3.9.1       Name the method that is used to install the conduit indicated at A.           (1)

          3.9.2       Name the electrical fitting that can be installed at B.                       (1)

          3.9.3       Identify parts C, D and E.                                                    (3)

          3.9.4       Explain what the purpose of F is.                                             (1)

          3.9.5       Draw the drawing symbol for E.                                                (1)
                                                                                                    [30]

Copyright reserved                                                               Please turn over

### Page 12

Downloaded from hlayiso.com
Civil Technology                             12                     DBE/November 2015 (R)
                                            NSC

QUESTION 4: QUANTITIES, MATERIALS AND JOINING

Start this question on a NEW page.

4.1       FIGURE 4.1 below shows the front view of a three-panel door. Study the
          drawing and complete the incomplete cutting list below. Write only the answer
          next to the question number (4.1.1–4.1.7) in the ANSWER BOOK.

                                                      114 x 44
                                                      114 x 44

                                                      69 x 44
                                                      32 mm thick

                       2 030
                                                      230 x 44

                                                      32 mm thick

                                                      230 x 44
                                     810

                                        FIGURE 4.1

       MEMBER         QUANTITY   UNIT      LENGTH    WIDTH   THICKNESS     MATERIAL
      Stile            4.1.1      mm        2 032     114         44         Meranti
      Top rail             1      mm        810      4.1.2       4.1.3       Meranti
      4.1.4                1      mm        1 050     69          44         Meranti
      Lock rail            1      mm        4.1.5     230         44         Meranti
      Raised and
      fielded              1      mm        540       630        4.1.6       Meranti
      panel
      Bottom rail          1      mm        810      4.1.7        44         Meranti          (7)

Copyright reserved                                                         Please turn over

### Page 13

Downloaded from hlayiso.com
Civil Technology                                13                      DBE/November 2015 (R)
                                               NSC

4.2       Various options are given as possible answers to the following questions.
          Choose the answer and write only the letter (A–D) next to the question
          number (4.2.1–4.2.8) in the ANSWER BOOK, for example 4.2.9 C.

          4.2.1       The area of a gable wall with a height of 2 000 mm and a width of
                      7 000 mm is …

                      A   28 m²
                      B   18 m²
                      C   7 m²
                      D   21 m²                                                                   (1)

          4.2.2       If the length of a foundation is 6 m, the width 0,6 m and the depth
                      0,3 m, then the volume of concrete needed will be …

                      A   2,1 m3
                      B   1,08 m3
                      C   1,8 m3
                      D   1,5 m3                                                                  (1)

          4.2.3       … is/are used to join wall plates to walls.

                      A   Rawl bolts
                      B   Countersunk screws
                      C   Steel nails
                      D   Hoop iron                                                               (1)

          4.2.4       … is a type of nail used to attach ceiling boards to the brandering.

                      A   Clout nails
                      B   Cut nails
                      C   Wire nails
                      D   Oval wire nails                                                         (1)

          4.2.5       … is a material used to join copper pipes.

                      A   Brazing rod
                      B   Welding rod
                      C   Grease
                      D   Solder                                                                  (1)

          4.2.6       … is/are used to join the members of a timber roof truss.

                      A   Screws
                      B   Clout nails
                      C   Rawl bolts
                      D   Gang nails/A connector plate                                            (1)

Copyright reserved                                                             Please turn over

### Page 14

Downloaded from hlayiso.com
Civil Technology                                      14                      DBE/November 2015 (R)
                                                     NSC

          4.2.7              … are used to attach knotty pine planks to the ceiling battens.

                             A   Panel pins
                             B   Clout nails
                             C   Wire nails
                             D   Cut nails                                                               (1)

          4.2.8              … can be used to join sewer pipes.

                             A   PVC glue
                             B   PVA glue
                             C   A compression joint
                             D   All the above-mentioned                                                 (1)

4.3       FIGURE 4.3 below shows the floor plan of a store room.

                                                           5 240

                     4 040

                                                   FIGURE 4.3

          SPECIFICATIONS:

           Outside measurements of the store room: 5 240 mm x 4 040 mm
           Width of the walls: 220 mm
           Dimensions of a ceiling board: 2 400 mm x 900 mm

          Use ANSWER SHEET 4.3 and calculate the following:

          4.3.1              The internal measurements of the store room                                 (6)

          4.3.2              The internal area of the store room                                         (3)

          4.3.3              The number of ceiling boards needed for the store room                      (6)
                                                                                                         [30]
Copyright reserved                                                                    Please turn over

### Page 15

Downloaded from hlayiso.com
Civil Technology                               15                       DBE/November 2015 (R)
                                              NSC

QUESTION 5: APPLIED MECHANICS

Start this question on a NEW page.

5.1       FIGURE 5.1 below shows a shaped lamina with an isosceles triangular hole.
          All dimensions are in millimetres. Study the lamina and answer the questions
          that follow.

          HINT: Use the formulae on the FORMULA SHEET.

                                               40
                          A

                                               1

                     60                                         30
                                               2

                                               20
                                                                20

                     30                        3

                      B                                                 B
                          A                    80

                                         FIGURE 5.1

          5.1.1       Calculate the area of part 1.                                               (1)

          5.1.2       Calculate the area of part 2.                                               (1)

          5.1.3       Calculate the area of part 3.                                               (1)

          5.1.4       Calculate the total area of the lamina.                                     (1)

          5.1.5       Calculate the position of the centroid of part 2 from A–A.                  (1)

          5.1.6       Calculate the position of the centroid of part 1 from B–B.                  (1)

          5.1.7       Calculate the position of the centroid of part 2 from B–B.                  (1)

          5.1.8       Deduce, from FIGURE 5.1, the position of the centroid of the whole
                      lamina from A–A.                                                            (1)

Copyright reserved                                                             Please turn over

### Page 16

Downloaded from hlayiso.com
Civil Technology                                16                        DBE/November 2015 (R)
                                               NSC

5.2       FIGURE 5.2 below shows the space diagram of a roof frame.

                                               60 N

                                                          30 N
                                                      B

                                     A         F
                                                                 C
                                                      E
                                         45°
                               30°                                45°
                                                D
                                               10 m
                       41 N                                             49 N
                                          FIGURE 5.2
          5.2.1        On ANSWER SHEET 5.2, develop and draw a vector diagram to
                       graphically determine the magnitude and nature of the forces in
                       each member (part) of the frame. Use scale 1 mm = 1 N.                        (8)

          5.2.2        Deduce, from the space and vector diagrams, the nature
                       and magnitude of the members indicated in the table on
                       ANSWER SHEET 5.2.                                                             (4)

5.3       FIGURE 5.3 below shows the space diagram of a beam with a span of
          10 metres with two point loads and a uniformly distributed load. Study the
          diagram and answer the questions that follow.

                                                              10 kN/m
                      10 kN 30 kN

               RL A        B   C                          D                E RR

                      1m 1m                           8m

                   65 kN                                                  55 kN
                                          FIGURE 5.3

          5.3.1        Deduce, from FIGURE 5.3, the value of the shear forces and
                       draw the shear force diagram on ANSWER SHEET 5.3. Use scale
                       1 mm = 2 kN.                                                                  (5)

          5.3.2        The value of the bending moments at A = 0 kN/m, B = 65 kN/m,
                       C = 120 kN/m, D = 140 kN/m and E = 0 kN/m. Use the given
                       information and draw the bending moment diagram on
                       ANSWER SHEET 5.3. Use scale 1 mm = 2 kN/m.                                    (5)
                                                                                                     [30]
Copyright reserved                                                                Please turn over

### Page 17

Downloaded from hlayiso.com
Civil Technology                         17                   DBE/November 2015 (R)
                                        NSC

QUESTION 6: GRAPHICS AND COMMUNICATION

6.1       FIGURE 6.1 below illustrates a detailed sectional view of the foot of
          a king post roof truss. Study the drawing and complete the table on
          ANSWER SHEET 6.1.

                                                                               1
                                         6

                                  7

                                                      10                       2

                                                                               3

                                                                               4

                                                                               5

                          8      9

                                       FIGURE 6.1                                       (15)

Copyright reserved                                                   Please turn over

### Page 18

Downloaded from hlayiso.com
Civil Technology                                                 18                    DBE/November 2015 (R)
                                                                NSC

6.2             FIGURE 6.2 below shows an incomplete floor plan with the roof layout of
                a proposed dwelling.

        220                               5 220                            2 100    2 800         220

220                                                                                                     220

                                                                           W1
1 800
                                                                                                        2 800

1 200   5 240       W2

1 800                                                                                        W1         2 100
                                  W1

220

                                                                                                        3 200

                                                                                                        220
                                                                       220

        220          1 200        2 100           1 200   900      1 200           3 300          220

                                                          10 560

                                                          FIGURE 6.2

                Study FIGURE 6.2 and develop and draw, on ANSWER SHEET 6.2, to
                scale 1 : 50, the SOUTH ELEVATION of the building. Use the specifications
                below and on the next page. (Use the assessment criteria on ANSWER
                SHEET 6.2 as a guideline for your drawing.)

                SPECIFICATIONS:

                        The height between the natural ground level and the top level of the floor
                         slab is 300 mm.
                        The height between the floor slab and the underside of the wall plate
                         is 2 600 mm.
                        The roof is covered with tiles and is finished with 220 mm wide
                         fascia board.
                        Ridge capping is 100 mm high.

Copyright reserved                                                                            Please turn over

### Page 19

Downloaded from hlayiso.com
Civil Technology                             19                         DBE/November 2015 (R)
                                            NSC

              Rain-water down pipes are 75 mm in diameter and 100 mm square
               gutters are used.
              Rain-water down pipes should be placed on every corner of the building.
              The eaves overhang is 500 mm.
              The door opening is 2 100 mm high and 900 mm wide.
              The door step is 150 mm high.
              The building has a hipped roof with a pitch of 30°.

          The following must also be shown on the drawing:

              The method used to determine the roof height
              Window sills
              THREE rain-water down pipes

                                  WINDOW SCHEDULE
                      Window 1 (W1)         Window 2 (W2)

                     Width       Height         Width          Height
                     2 100       1 500          1 200          1 500

          THREE marks will be allocated for the application of the scale.

          Start your drawing from corner A as indicated on the bottom left of
          ANSWER SHEET 6.2.                                                                     (25)
                                                                                                [40]

                                                                                  TOTAL:        200

Copyright reserved

### Page 20

Downloaded from hlayiso.com
Civil Technology                              DBE/November 2015 (R)
                                    NSC

CENTRE NUMBER:

EXAMINATION NUMBER:

ANSWER SHEET 1.10

                                FIGURE 1.10

ASSESSMENT CRITERIA        MARK CANDIDATE'S
                                   MARK
Flashing correctly drawn     2

Copyright reserved

### Page 21

Downloaded from hlayiso.com
Civil Technology                             DBE/November 2015 (R)
                                       NSC

CENTRE NUMBER:

EXAMINATION NUMBER:

ANSWER SHEET 1.11

1.11.4                       1.11.5

                             A                                 A

 ASSESSMENT           MARK    CANDIDATE'S
   CRITERIA                      MARK
Stretcher course       2
Queen closer           1
Header course          1
          TOTAL:       4

Copyright reserved

### Page 22

Downloaded from hlayiso.com
Civil Technology                                           DBE/November 2015 (R)
                                        NSC

CENTRE NUMBER:

EXAMINATION NUMBER:

ANSWER SHEET 2.10

ASSESSMENT CRITERIA                           MARK   CANDIDATE'S
                                                        MARK
Symbol for concrete foundation and concrete
                                               1
floor
Damp-proof course between walls and cavity     2
Damp-proofing under concrete floor             2
Weep hole                                      1
Concrete in cavity wall                        1
Wall tie                                       1
Dimension of total width of wall               1
                                    TOTAL:     9

Copyright reserved

### Page 23

Downloaded from hlayiso.com
Civil Technology                                                           DBE/November 2015 (R)
                                              NSC

CENTRE NUMBER:

EXAMINATION NUMBER:

ANSWER SHEET 4.3

Complete your answers in the spaces indicated with _____ .

            A          B         C                            D
4.3.1                                    Internal measurements of:

                                         Long walls = _______ – ________

                                                     = _______

                                         Short walls = _______ – ________
                                                                                                   (6)
                                                     = _______

4.3.2                                    Internal area of the store room
            1/       _______

                     _____     ____ m2                                                             (3)

4.3.3                                    Number of ceiling boards

                                         Area of one ceiling board (CB):
            1/       _____

                     _____     ______

                                                                  Area of room
                                         Ceilingboards needed 
                                                                   Area of CB

                                         =

                                         = ________
                                                                                                   (6)

Copyright reserved

### Page 24

Downloaded from hlayiso.com
Civil Technology                                                           DBE/November 2015 (R)
                                                NSC

CENTRE NUMBER:

EXAMINATION NUMBER:

ANSWER SHEET 5.2
                                            60 N

                                                       30 N
                                                   B

                                  A         F
                                                              C
                                                   E
                                      45°
                            30°                               45°
                                             D
                                            10 m
                     41 N                                           49 N
                                                                                                   a

MEMBER NATURE FORCE
AF
CE
Tolerance of 1 N to either side
Copyright reserved

### Page 25

Downloaded from hlayiso.com
Civil Technology                                              DBE/November 2015 (R)
                                         NSC

CENTRE NUMBER:

EXAMINATION NUMBER:

ANSWER SHEET 5.3
                                                    10 kN/m
                       10 kN     30 kN

               RL A          B    C            D              E RR

                      1m 1m                    8m

                     65 kN                                    55 kN

5.3.1

                                                                                      (5)

5.3.2

                                                                                      (5)

Copyright reserved

### Page 26

Downloaded from hlayiso.com
Civil Technology                                           DBE/November 2015 (R)
                                               NSC

CENTRE NUMBER:

EXAMINATION NUMBER:

ANSWER SHEET 6.1

NO.                   QUESTIONS                      ANSWERS            MARKS
1       Identify the type of eave construction
                                                                           1
        used in the drawing.

2       State the minimum pitch (slope) of
                                                                           1
        number 1.

3       State the standard dimension of
                                                                           1
        number 2.
4       State the centre-to-centre spacing
        between the brandering of the ceiling                              1
        construction.

5       State the purpose of number 3.                                     1

6       Draw the drawing symbol for
                                                                           1
        number 4.
7       State the width of the external wall
        indicated by number 5, excluding                                   1
        plaster.
8       Name the colour coding that should be
                                                                           1
        used for number 6.

9       As a draughtsperson, recommend a
                                                                           1
        type of roof sheeting for number 7.

10      Name ONE material that can be used
                                                                           1
        for number 8.

11      Identify number 9.                                                 1

12      What is the standard dimension of
                                                                           1
        number 10?
13      Draw a neat freehand line diagram of
        a kingpost roof truss.
                                                                           3

                                                               TOTAL:     15
Copyright reserved

### Page 27

Civil Technology
                        Downloaded from hlayiso.com                                 DBE/November 2015 (R)
                                   NSC

 CENTRE NUMBER:                               ASSESSMENT                               ASSESSMENT
                                                                      MARKS   LM                              MARKS   LM
                                                CRITERIA                                 CRITERIA
                                          External walls                3          Ridge capping                1
 EXAMINATION NUMBER:                      NGL (correctly indicated)     1          Determine roof height        1
                                          FFL (correctly indicated)     1          Any two labels               2
   ANSWER SHEET 6.2                       Window                        1          Application of scale
                                          Window sill                   1          One or two incorrect = 3
                                          Door opening                  1          Three or four incorrect
                                          Step                          1          =2                           3
                                          Fascia board                  1          More than five incorrect
                                                                                   =1
                                          Rain-water down pipes         3
                                                                                   No measurement correct
                                          Roof (correctly drawn)        4          =0
                                          Gutter                        1                           TOTAL:     25

         A
   Copyright reserved

### Page 28

Downloaded from hlayiso.com
Civil Technology                                                             DBE/November 2015 (R)
                                               NSC

                                      FORMULA SHEET

IMPORTANT ABBREVIATIONS

SYMBOL         DESCRIPTION        SYMBOL         DESCRIPTION           SYMBOL DESCRIPTION
   c             Centroid            b           Breadth/Width            r      Radius
   ℓ              Length             s               Side                 A       Area

FORMULAE

   AREA OF              FORMULA             FORMULA                    FORMULA FOR THE
                        (in words)         (in symbols)              POSITION OF CENTROIDS
                                                                       X-axis       Y-axis
                                                                         s            s
Square                  side × side              s×s
                                                                         2            2
                                                                          ℓ           b
Rectangle             length × breadth           ℓ×b
                                                                         2            2
Right-angled                                                             b            h
                     ½ × base × height          ½b × h
triangle                                                                 3            3
Equilateral
triangle/                                                                b                h
                     ½ × base × height          ½b × h
Isosceles                                                                2                3
triangle

                                               (A1  d)  (A2  d)
                      Position of centroid =
                                                  Total area

                                               OR

                                          Y
                                                 Ay
                                                A

                                               OR

                                          X
                                                 Ax
                                                A

Copyright reserved

## Related documents

- [Civil Technology Nov 2015 Memo Eng](https://www.hlayiso.com/library/civil-technology-nov-2015-memo-eng/0b040a57-1607-42d5-971a-bf01f012786c) — Civil Technology · Memo · 2015 · Eng
- [CVLTECH GR12 QP SEPT2015 AFR](https://www.hlayiso.com/library/cvltech-gr12-qp-sept2015-afr/869b47f0-5b29-46c7-9698-b96a272efdd8) — Civil Technology · QP · 2015 · Afr
- [Civil Technology Feb March 2015 Eng](https://www.hlayiso.com/library/civil-technology-feb-march-2015-eng/4f802241-70af-400c-8dcb-c98316a539e7) — Civil Technology · QP · 2015 · Eng
- [Civil Technology Nov 2023 (Construction) Eng](https://www.hlayiso.com/library/civil-technology-nov-2023-construction-eng/e6743728-8140-42ae-838d-282654a975a5) — Civil Technology · QP · 2023 · Eng
- [Civil Technology Nov 2023 (Civil Services) Afr](https://www.hlayiso.com/library/civil-technology-nov-2023-civil-services-afr/b820ac91-947c-4aed-821f-256aa13aabe1) — Civil Technology · QP · 2023 · Afr
- [Civil Technology Nov 2023 (Woodworking) Afr](https://www.hlayiso.com/library/civil-technology-nov-2023-woodworking-afr/f6f7ac38-fb55-4d61-bc66-5441e4cbcee0) — Civil Technology · QP · 2023 · Afr

## More from Grade 12 Civil Technology

- [Civil Technology (Woodworking) (Afrikaans) June 2025 Possible Answers](https://www.hlayiso.com/library/civil-technology-woodworking-afrikaans-june-2025-possible-answers/c0a65d19-28ca-4ac3-8c61-d4627d2a3133) — Memo · 2025 · Afr
- [Civil Technology Nov 2025 (Construction) MG Eng](https://www.hlayiso.com/library/grade-12-civil-technology-2025-nsc-november-exam-memorandum/0e265899-dc44-4809-aabf-8f374f1af392) — Memo · 2025 · Eng
- [CIV TECH GR12 MEMO SEPT2024 Construction Afrikaans](https://www.hlayiso.com/library/civ-tech-gr12-memo-sept2024-construction-afrikaans/162bcc65-80ad-4384-b293-36da22468b06) — Memo · 2024 · Afr
- [CIV TECH GR12 MEMO SEPT2024 Civil Services English](https://www.hlayiso.com/library/civ-tech-gr12-memo-sept2024-civil-services-english/c1f2441d-22ba-4ae6-9e56-137cc442080c) — Memo · 2024 · Eng
- [CIV TECH GR12 MEMO SEPT2024 Construction English](https://www.hlayiso.com/library/civ-tech-gr12-memo-sept2024-construction-english/4d9c54ef-f526-46ad-82d4-8dd419eafb50) — Memo · 2024 · Eng
- [CIV TECH GR12 MEMO SEPT2024 Woodworking English](https://www.hlayiso.com/library/civ-tech-gr12-memo-sept2024-woodworking-english/6e7f4be5-4ffb-4654-b98b-b4cc4dfc4cc7) — Memo · 2024 · Eng

## Collection

- [Grade 12 past papers](https://www.hlayiso.com/grade-12/past-papers)

---

Hlayiso: free CAPS and IEB past papers, memos, notes and study guides for South African learners. When citing, link the page URL above, not a PDF or /api/ URL.