# Civil Technology Grade 12 NSC November 2015 Memo (English)

> Grade 12 Civil Technology memorandum from the NSC November Exam 2015 (English), 18 pages. Read online or download the free PDF.

- Page: https://www.hlayiso.com/library/civil-technology-nov-2015-memo-eng/0b040a57-1607-42d5-971a-bf01f012786c
- Updated: 2026-09-27
- Subject: Civil Technology
- Grade: Grade 12
- Document type: Memorandum
- Year: 2015
- Exam period: NSC November Exam
- Curriculum: CAPS
- Pages: 18

Breadcrumbs: [Home](https://www.hlayiso.com/) › [Library](https://www.hlayiso.com/library) › [Grade 12](https://www.hlayiso.com/library/grade-12) › [Civil Technology](https://www.hlayiso.com/library/grade-12/civil-technology) › [Civil Technology Grade 12 NSC November 2015 Memo (English)](https://www.hlayiso.com/library/civil-technology-nov-2015-memo-eng/0b040a57-1607-42d5-971a-bf01f012786c)

## About this document

Civil Technology · Grade 12 · NSC November Exam · 2015. Memorandum, 18 pages. Read online or download the PDF.

Read it free online on the page above; download the PDF from there.

## Document text

Text extracted from the PDF. Layout, diagrams and tables may not survive extraction.

### Page 1

Downloaded from hlayiso.com

                                  GRAAD 12

                                 NATIONAL
                            SENIOR CERTIFICATE

                                  GRADE 12

                              CIVIL TECHNOLOGY

                                NOVEMBER 2015

                                 MEMORANDUM

MARKS: 200

                       This memorandum consists of 18 pages.

Copyright reserved                                             Please turn over

### Page 2

Downloaded from hlayiso.com
Civil Technology                              2                            DBE/November 2015
                                      NSC – Memorandum

QUESTION 1:          CONSTRUCTION, SAFETY AND MATERIALS

1.1           •    Someone should have held the ladder. √
              •    Catch nets should be installed to prevent tools and materials from
                   falling on people below. √
              •    The visitor should wear a hard hat.
              •    The worker should wear a tool belt.
              •    A scaffold could be built.
              •    Meeting to be moved to a safer area.                                           (2)

          ANY TWO OF THE ABOVE OR ANY OTHER ACCEPTABLE ANSWER

1.2           •    Always ensure that saw is sharp. √
              •    Use saws only for the purposes for which they were designed. √
              •    Safety rules for the saw must be strictly adhered to.
              •    Do not work with a saw with a loose or broken handle.
              •    Report all defects and damages immediately.
              •    Always keep your hands away or behind the cutting surface of the saw.
              •    Maintain the correct cutting direction.
              •    Do not bend the blades/points of saw when you are using them.
              •    Blunt saws require more force and may lead to unnecessary accidents.
              •    The work piece must be securely clamped to prevent it from moving.             (2)
              •    Do not test the sharpness of the teeth with your fingers
                                      ANY TWO OF THE ABOVE

1.3           • Trenches that are excavated must be protected with a fence. √
              • Red warning lights or warning signs should be placed at intervals and
                must be clearly visible to warn the public of the danger.                         (1)

                                     ANY ONE OF THE ABOVE

1.4           •    Spray painting. √
              •    Spray painting is a better option because plastics commonly have very
                   smooth surfaces, so spray painting is a better option. √
              •    Is easy to apply.
              •    It is quicker.                                                                 (2)

                                     ANY TWO OF THE ABOVE

1.5
                      √                         √

              I-beam                   H-beam
                                                                                                  (2)
          THREE DIMENSIONAL DRAWINGS CAN ALSO BE ACCEPTED

Copyright reserved                                                             Please turn over

### Page 3

Downloaded from hlayiso.com
Civil Technology                                 3                           DBE/November 2015
                                         NSC – Memorandum

1.6       Admixtures are used to:
            • change the property of the concrete mix. √
            • increase the workability.
            • increase or reduce the setting time.
            • increase the strength.
            • increases the durability.
            • reducing cost.
            • reduce water content.
            • improve pump ability
            • shorten curing time.
            • change the temperature range.
            • change the colour of concrete.                                                        (1)

                                        ANY ONE OF THE ABOVE

1.7                •     Plasticisers √
                   •     Accelerators
                   •     Retarders
                   •     Air entrainers/entrapment admixtures
                   •     Corrosion inhibitors
                   •     Damp proofing
                   •     Water-reducing admixtures
                   •     Anti-washout admixtures
                   •     Bonding admixtures
                   •     Colouring admixtures/oxides                                                (1)

                                        ANY ONE OF THE ABOVE

1.8                  •    Not fire resistant and therefore it must be treated/burns easily. √
                     •    It is more expensive than ordinary roof coverings/insurance is
                          more expensive. √
                     •    A lot of maintenance is required/easily damaged.
                     •    Thatch is an organic material and can rot easily.
                     •    The thatch at the ridge capping needs to be re-thatched regularly.
                     •    Durability is more or less between 25 and 30 years if properly
                          maintain.
                     •    Ideal breeding place for Insects and dust                                 (2)

                                       ANY TWO OF THE ABOVE

1.9                  •    Corrugated iron sheeting/galvanised sheeting √
                     •    IBR sheeting √
                     •    Concrete/clay roof tiles/tiles
                     •    Slate
                     •    Fibre cement sheeting
                     •    Fibre glass sheeting
                     •    Transparent IBR sheeting
                     •    Perspex sheeting
                                                                                                    (2)
                                       ANY TWO OF THE ABOVE
Copyright reserved                                                               Please turn over

### Page 4

Downloaded from hlayiso.com
Civil Technology                                4                               DBE/November 2015
                                        NSC – Memorandum

1.10      1.10.1                                       Assessment                Candidate's
                                                                         Mark
                                                       criteria                  mark
                                                       Flashing
                                                       correctly drawn
                                                                          2

                                          √

                                              √

                                                                                                      (2)

          1.10.2            •   Waterproofing membrane with a sealing compound √
                            •   Bituminous felt
                            •   Plastic
                            •   Copper sheet
                            •   Galvanised sheet metal
                            •   Lead sheet                                                            (1)
                            •   Aluminium sheet

                                              ANY ONE OF THE ABOVE

          1.10.3         •      It is to seal off the gap between the wall and the roof. √
                         •      To prevent rain from entering the roof.
                                                                                                      (1)
                         •      To prevent unwanted elements from entering the ceiling.

                                              ANY ONE OF THE ABOVE

1.11      1.11.1      English bond √                                                                  (1)

          1.11.2         • The English bond can only be built as a single brick wide
                            wall.√
                         • One course will be a stretcher course followed by a header
                            course.
                         • The second and second-last bricks will a queen closer in the
                            header course. √
                         • If the course in a quoin on the front elevation is a stretcher
                            course then the same course around the corner will be a
                            course of headers.
                         • It is one of the strongest bond.                                           (2)

          1.11.3        •       The wall can be painted √
                        •       The wall can be tiled
                        •       The wall can be cladded (wood/stone/brick)                            (1)

                                              ANY ONE OF THE ABOVE
Copyright reserved                                                                 Please turn over

### Page 5

Downloaded from hlayiso.com
Civil Technology                                5               DBE/November 2015
                                        NSC – Memorandum

1.11.4    End view

                     √
                     √                    A                                    A
                                                                                      (2)

1.11.5       ASSESSMENT           MARK        CANDIDATE'S
               CRITERIA                          MARK
           Stretcher course         2
           Queen closer             1
           Header course            1
                         TOTAL:     4

          Plan course of T junction

                                                     √
                                              √             √
                                                    √
                                                                                      (4)

1.12          •    Cement fibre ceiling board √
              •    Match board ceilings
              •    Sheet metal ceilings
              •    Knotty pine ceiling
              •    Gypsum board/Rhino board
              •    Plastic ceilings.
              •    Polystyrene ceilings
              •    Styrofoam                                                          (1)

                                      ANY ONE OF THE ABOVE
                                                                                      [30]

Copyright reserved                                                 Please turn over

### Page 6

Downloaded from hlayiso.com
Civil Technology                               6                             DBE/November 2015
                                       NSC – Memorandum

QUESTION 2: ADVANCED CONSTRUCTION AND EQUIPMENT

2.1       2.1.1        Electric mitre saw √                                                          (1)

          2.1.2           •   The mitre saw can be used to make accurate cross cuts at
                              different angles. √
                          •   The mitre saw can be used to cut angles or compound
                              angles on roof truss members
                          •   The mitre saw can be used to saw mitres of skirtings.                  (1)

                                              ANY ONE OF THE ABOVE

          2.1.3           •   The mitre saw enables precision cutting. √
                          •   It will save time. √                                                   (2)

2.2           •    Start by filling the pipe with water. Bring the water level in the
                   transparent pipe in line with the first level. √
              •    Take the other end of the pipe to the other position where the level
                   must be transferred, maintaining the first level. Make a mark next to the
                   water level at this point. √                                                      (2)

2.3           •    It will be used to provide electricity to all portable electrical equipment
                   on the building site where no electricity is available. √
              •    To provide electricity for the site office.                                       (1)

                                      ANY ONE OF THE ABOVE

2.4       2.4.1        Concrete spacer/Spacer/cover depth block √                                    (1)

          2.4.2           •   It is used to keep reinforcement bars away from soil and
                              sides of trenches or shuttering (formwork). √
                          •   It is used to maintain cover depth of concrete/to keep
                              reinforcement bars in position.                                        (1)

                                              ANY ONE OF THE ABOVE

2.5       2.5.1        Rib and block floor √                                                         (1)

          2.5.2           •   It is cheaper. √
                          •   It is lighter and easy to work with. √
                          •   It is quicker to install.
                          •   It has a lighter load on foundations.                                  (2)
                          •   Easy to trim around edges.

                       ANY TWO OF THE ABOVE OR ANY OTHER ACCEPTABLE
                       ANSWER

Copyright reserved                                                                Please turn over

### Page 7

Downloaded from hlayiso.com
Civil Technology                               7                            DBE/November 2015
                                       NSC – Memorandum

          2.5.3          •   It is more economical than in situ concrete floors. √
                         •   Very little or no shuttering is required. √
                         •   They provide superior sound and thermal insulation. √
                         •   It can be erected a lot quicker than in situ slabs.
                         •   Highly skilled labour is unnecessary.
                         •   No heavy lifting equipment is required.                               (3)
                         •   It is easier to install conduits.
                         •   The load of the building will be lighter on the foundation.

                      ANY THREE OF THE ABOVE OR ANY OTHER ACCEPTABLE
                      ANSWER

2.6       2.6.1          •   Flat √
                         •   Semi-circular √
                         •   Circular
                         •   Segmental arch                                                        (2)

                                          ANY TWO OF THE ABOVE

          2.6.2       Key brick √                                                                  (1)

2.7       Slump test – Test the workability and consistency of the concrete mix. √
          Cube test – Test the compressive strength of concrete. √                                 (2)

2.8       2.8.1       A - Anchor bar √
                      B - Shear bar √
                      C - Stirrup/Binder √
                      D - Main bars of column √                                                    (4)

          2.8.2       Ribbed bars create a better bond with the concrete due to the
                      rough surface of the bar. √                                                  (1)

                                     OR ANY OTHER ACCEPTABLE ANSWER

2.9       2.9.1       A – Landing / Floor √                                                        (1)

          2.9.2       B – Between 75 mm and 200 mm. √                                              (1)

          2.9.3       C – Tread/Going √                                                            (1)

          2.9.4       D - String √                                                                 (1)

Copyright reserved                                                              Please turn over

### Page 8

Downloaded from hlayiso.com
Civil Technology                            8                         DBE/November 2015
                                    NSC – Memorandum

2.10
                                        270
                                              √

                                         √

                                                  √
                                         √
                               √                                 √√

                                         √
                                                      √

           ASSESSMENT CRITERIA                            MARK   CANDIDATE'S
                                                                    MARK
           Symbol for concrete foundation and
                                                           1
           concrete floor
           Damp-proof course between walls and             2
           cavity
           Damp-proofing under concrete floor              2
           Weep hole                                       1
           Concrete in cavity wall                         1
           Wall tie                                        1
           Dimension of total width of wall                1
                                                                                            (9)
                                            TOTAL:         9

2.11      Pile foundations/raft foundations √                                               (1)

2.12      Dry wall √                                                                        (1)
                                                                                            [40]

Copyright reserved                                                       Please turn over

### Page 9

Downloaded from hlayiso.com
Civil Technology                               9                           DBE/November 2015
                                       NSC – Memorandum
QUESTION 3: CIVIL SERVICES

3.1       3.1.1        C/B √                                                                      (1)

          3.1.2        A√                                                                         (1)

          3.1.3        E√                                                                         (1)

          3.1.4        B√                                                                         (1)

          3.1.5        D√                                                                         (1)

          3.1.6        G√                                                                         (1)

          3.1.7        F√                                                                         (1)

3.2       3.2.1        If there is no gully and the sewerage system is blocked sewage will
                       flow out through the bath outlet/shower outlet/water closet into the
                       house. √                                                                   (1)

          3.2.2        If there is a blockage in the sewerage system there will be no
                       access to remove the blockage. √                                           (1)

3.3           •    By using an electric geyser. √
              •    By using a gas geyser. √
              •    By using a solar geyser.
              •    By using fire to heat the water.
              •    Electricity
              •    Gas
              •    Wood/fire/donkey                                                               (2)
              •    Heat pump

          ANY TWO OF THE ABOVE OR ANY OTHER ACCEPTABLE ANSWER

3.4           •    Wind pump/mill√
              •    Hand pump
              •    A submersible pump
              •    Motorised/solar pump                                                           (1)

          ANY ONE OF THE ABOVE OR ANY OTHER ACCEPTABLE ANSWER

3.5           •    Shallow wells √
              •    Sea water (desalination)
              •    Rain water
              •    Dams
              •    Rivers
              •    Lakes                                                                          (1)
              •    Tanks/reservoirs/purchased water
              •    Recycled water

                                      ANY ONE OF THE ABOVE
Copyright reserved                                                             Please turn over

### Page 10

Downloaded from hlayiso.com
Civil Technology                              10                          DBE/November 2015
                                       NSC – Memorandum

3.6
                                                         Shower
                                                          rose

                                                 √

                                            √        √
                                            H        C

                           Hot-water                         Cold-water
                            inlet √                            inlet √

                                                 OR
                                                         Shower
                                                          rose

                                Hot-water                Cold-water
                                 inlet √         √         inlet √

                                            √        √
                                                     C
                                            H
                                                                                                  (5)

              ANY ONE OF THE ABOVE OR ANY OTHER ACCEPTABLE LAYOUT

3.7       3.7.1       Single-bowl sink √                                                          (1)

          3.7.2       Gully √                                                                     (1)

          3.7.3       Water meter √                                                               (1)

3.8       •        By using roof gutters rainwater will be channelled to an exit point. √
          •        By using surface channels leading rainwater to exit point. √
          •        By using hard surfaces rain water will be channelled to exit point.
          •        By using grid-top manholes rain water will be channelled into the storm
                   water pipe network.                                                            (2)

          ANY TWO OF THE ABOVE OR ANY OTHER ACCEPTABLE ANSWER

3.9       3.9.1       Conduits are chased into the wall. √                                        (1)

          3.9.2        •   A light switch/switch/isolator √ OR
                       •   Socket outlet/switched socket outlet/power point/plug.                 (1)

          3.9.3       C    Socket outlet/Power point √                                            (1)

                      D    Distribution board/box/Prepaid meter √                                 (1)

                      E    Meter box √                                                            (1)

Copyright reserved                                                             Please turn over

### Page 11

Downloaded from hlayiso.com
Civil Technology                          11                            DBE/November 2015
                                   NSC – Memorandum

          3.9.4       •   The kick pipe is used to protect the electrical cable from
                          damage. √
                      •   To enable the installation of the electrical cable to the meter
                          box.
                      •   Easy replacement of electrical cables.
                      •   Electricity supply to the building.
                      •   Safety/neatness                                                       (1)

          3.9.5
                                 W         OR             M      √
                                                                                                (1)
                                                                                                [30]

Copyright reserved                                                           Please turn over

### Page 12

Downloaded from hlayiso.com
Civil Technology                        12           DBE/November 2015
                                 NSC – Memorandum

QUESTION 4 QUANTITIES AND CALCULATIONS AND JOINING

4.1       4.1.1       2√                                                   (1)

          4.1.2       114 mm √                                             (1)

          4.1.3       44 mm √                                              (1)

          4.1.4       Muntin √                                             (1)

          4.1.5       810 mm √                                             (1)

          4.1.6       32 mm √                                              (1)

          4.1.7       230 mm √                                             (1)

4.2       4.2.1       C√                                                   (1)

          4.2.2       B√                                                   (1)

          4.2.3       D√                                                   (1)

          4.2.4       A√                                                   (1)

          4.2.5       D√                                                   (1)

          4.2.6       D√                                                   (1)

          4.2.7       A√                                                   (1)

          4.2.8       A√                                                   (1)

Copyright reserved                                      Please turn over

### Page 13

Downloaded from hlayiso.com
Civil Technology                        13                            DBE/November 2015
                                 NSC – Memorandum

4.3.1        A          B          C                         D
                                            Internal measurements of:
                                            Long walls = 5 240 √ – 2/220 mm √
                                                       = 4 800 mm √
                                            Short walls = 4 040 √ – 2/220 mm √
                                                       = 3 600 mm √                          (6)

             1/       4, 8 √                Internal area of the store room.
4.3.2                 3, 6 √           2
                               17, 28 m √                                                    (3)

                                            Number of ceiling boards.
             1/       2, 4 √                Area of one ceiling board (CB):
                      0, 9 √   2, 16 m2 √   One ceiling board is
                                            2 400 mm x 900 mm
4.3.3                                       Area is 2, 16 m2

                                                                      Area of room
                                            Ceiling boards needed =
                                                                       Area of CB
                                              17,28
                                             =       √√
                                               2,16
                                            = 8 Ceiling boards are needed √                  (6)
                                                                                             [30]

Copyright reserved                                                        Please turn over

### Page 14

Downloaded from hlayiso.com
Civil Technology                          14                       DBE/November 2015
                                   NSC – Memorandum

QUESTION 5: APPLIED MECHANICS

5.1       5.1.1       60 mm x 40 mm = 2 400 mm² √                                        (1)

          5.1.2       ½ x 20 x 30 mm = 300 mm² √                                         (1)

          5.1.3       80 mm x 30 mm = 2 400 mm² √                                        (1)

          5.1.4       2 400 mm + 2 400 mm – 300 mm = 4 500 mm² √                         (1)

          5.1.5       40 mm √                                                            (1)

          5.1.6       60 mm √                                                            (1)

          5.1.7       60 mm √                                                            (1)

          5.1.8       40 mm √                                                            (1)

Copyright reserved                                                    Please turn over

### Page 15

Downloaded from hlayiso.com
Civil Technology                             15                             DBE/November 2015
                                      NSC – Memorandum

5.2                                                60 N

                                                             B 30 N

                                  A           F

                                                                      C

                                        45°
                                                         E
                            30°                                       45°
                                                     D
                                                  10 m
                     41 N                SPACE DIAGRAM                        49 N

                                                                      a

                                                              √

                                              f
                                        √
                             e                                √       d √

                                                                  √

                                                                      b √

                                                    √

                                                                                                  (8)
                                                                      c√
                                        VECTOR DIAGRAM
                                  NOT ACCORDING TO SCALE
                           USE A MASK TO MARK THIS QUESTION
           MEMBER NATURE MAGNITUDE
           AF          Strut √     42,4 N √
           CE          Strut √     69,2 N √                                                       (4)
          Tolerance of 1 N to either side

Copyright reserved                                                             Please turn over

### Page 16

Downloaded from hlayiso.com
Civil Technology                                    16                      DBE/November 2015
                                             NSC – Memorandum

                               10 kN 30 kN                              10 kN/m
                                                          80 kN

                           A     B    C                     D                     E
                           1m 1m                           8m
                         65 kN                                              55 kN
                                               SPACE DIAGRAM

5.3.1        65 kN                √
                                          55 kN

                     √
                                       √ 25 kN

                                                                           0 kN

                         0 kN                                   √

                                                                              √
                                           SHEAR FORCE DIAGRAM
                                                                              -55 kN                 (5)

5.3.2                                                   140 kN/m
                                                  √
                               120 kN/m                             √

                                  √

                   65 kN/m

                          √

                                                                             √

                     0 kN/m                                               0 kN/m                     (5)
                                       BENDING MOMENT DIAGRAM
                                                                                                     [30]

Copyright reserved                                                                Please turn over

### Page 17

Downloaded from hlayiso.com
Civil Technology                           17                             DBE/November 2015
                                    NSC – Memorandum

ANSWER SHEET 6.1

NO.                     QUESTIONS                            ANSWERS                  MARKS
 1      Identify the type of eave construction used   Closed eave/concealed
                                                      eave                              1
        in the drawing.
  2     State the minimum pitch (slope) of number     5° to10°
                                                                                        1
        1.
  3                                                   114 mm x 38 mm
        State the standard dimension of number 2.                                       1
                                                      300 mm/400 mm/
        State the centre-to-centre spacing between
  4                                                   450 mm                            1
        the brandering of the ceiling construction.
                                                      Any ONE of the above
                                                      To cover the opening
                                                      between the ceiling and
  5     State the purpose of number 3.                the wall. To prevent              1
                                                      unwanted elements
                                                      entering the ceiling.
  6     Draw the drawing symbol for
                                                                                        1
        number 4.
  7                                                   220 mm
        State the width of the external wall
                                                                                        1
        indicated by number 5, excluding plaster.
  8     Name the colour coding that should be         Yellow
                                                                                        1
        used for number 6.
                                                      Corrugated galvanised
                                                      sheeting/IBR
                                                      sheeting/Cement fibre
  9     As a draughtsperson, recommend a type of
                                                      sheet/Chromadeck/fibre            1
        roof sheeting for number 7.
                                                      glass
                                                      Or any other acceptable
                                                      answer
                                                      Fibre cement, Knotty pine,
 10     Name ONE material that can be used for        chicken mesh and soffit
                                                                                        1
        number 8.                                     laggings, soffit board, slats
                                                      Any ONE of the above
                                                      Quarter round mould/
 11     Identify number 9.                            Quadrant                          1

 12     What is the standard dimension of number      114 mm x 38 mm
                                                                                        1
        10?
 13     Draw a neat freehand line diagram of a
        kingpost roof truss.
                                                            √                           3
                                                                  √
                                                                      √

                                                                          TOTAL:        15

Copyright reserved                                                            Please turn over

### Page 18

Civil Technology
                           Downloaded from hlayiso.com
                                                    18                                                                                 DBE/November 2015
                                             NSC – Memorandum
                                                                             ASSESSMENT                                       ASSESSMENT
                                                                                                        MARKS       LM                                MARKS        LM
                                                                               CRITERIA                                          CRITERIA
  QUESTION 6: GRAPHICS AND COMMUNICATION                                External walls                      3            Ridge capping                    1
                                                                        NGL (correctly indicated)           1            Determine roof height            1
                                                                        FFL (correctly indicated)           1            Any two labels                   2
  ANSWER SHEET 6.2                                                      Window                              1            Application of scale
                                                                        Window sill                         1            One or two incorrect = 3
                                                                        Door opening                        1            Three or four incorrect
                                                                        Step                                1            =2
                                                                        Fascia board                        1            More than five incorrect =       3
                                                                        Rain-water down pipes               3            1
                                                                                                                         No measurement correct
                                                                        Roof (correctly drawn)              4            =0
                                                                        Gutter                              1                               TOTAL:        25
                                                                    √
                                                                                                    √

                                                    Clay Tiles √
                       √
                                            √                                                       √
                                                                                                                                                      √

                                                                                                        √           √

                                                                                                                                                          √
         √                   √                                  √                      √                        Plaster and paint √
                                                                                                                                                               √
     √
                                        √                                        √
                                                                                                                                            FFL
                                                                                                                                                      √
                                                                √                                                                                                  √

NOT TO SCALE: USE A MASK TO MARK THIS QUESTION                                       Application of scale √ √ √

                                                                                                                                                      [40]
                                                                                                                                  TOTAL:              200
  Copyright reserved

## Related documents

- [Civil Technology Nov 2015 Eng (R)](https://www.hlayiso.com/library/civil-technology-nov-2015-eng-r/8e33f148-adde-4af4-be2d-6a45bccfb5d5) — Civil Technology · QP · 2015 · Eng
- [CVLTECH GR12 MEMO SEPT2015 AFR](https://www.hlayiso.com/library/cvltech-gr12-memo-sept2015-afr/499243c3-9639-46d0-90f2-d372f7df4e7e) — Civil Technology · Memo · 2015 · Afr
- [CVLTECH GR12 MEMO SEPT2015 ENG](https://www.hlayiso.com/library/cvltech-gr12-memo-sept2015-eng/734f23d1-2b96-4108-8dba-99cd5a8e7a89) — Civil Technology · Memo · 2015 · Eng
- [Civil Technology Feb March 2015 Memo Eng](https://www.hlayiso.com/library/civil-technology-feb-march-2015-memo-eng/aedf8743-b698-4a4c-b0c6-791f5a20e050) — Civil Technology · Memo · 2015 · Eng
- [Civil Technology Nov 2022 (Civil Services) MG Afr](https://www.hlayiso.com/library/civil-technology-nov-2022-civil-services-mg-afr/42b5315c-825c-40e3-b394-85e0253fc0fb) — Civil Technology · Memo · 2023 · Afr
- [Civil Technology Nov 2020 (Construction) Memo Eng](https://www.hlayiso.com/library/civil-technology-nov-2020-construction-memo-eng/f06cef7f-235e-45f7-9f9b-f8e6a2b0c0ca) — Civil Technology · Memo · 2020 · Eng

## More from Grade 12 Civil Technology

- [CVLT Woodworking Eng watermark](https://www.hlayiso.com/library/cvlt-woodworking-eng-watermark/8e178c6e-fa7b-40f4-8a2c-936e0bee3b38) — QP · 2025 · Eng
- [Civil Technology (Woodwork) (English and Afrikaans) June 2025 Question Paper](https://www.hlayiso.com/library/civil-technology-woodwork-english-and-afrikaans-june-2025-question-paper/c8edd459-5237-48e0-8588-69d7ecd7f8e5) — QP · 2025 · Afr
- [Civil Technology May-June 2025 (Construction) Afr](https://www.hlayiso.com/library/civil-technology-may-june-2025-construction-afr/591d6ffd-20b1-4748-a1ba-b055be0a14c3) — QP · 2025 · Afr
- [Civil Technology Nov 2025 (Woodworking) Afr](https://www.hlayiso.com/library/grade-12-civil-technology-2025-nsc-november-exam-question-paper/05a95faf-5891-4d88-9e5e-7d13c1d21648) — QP · 2025 · Afr
- [CIV TECH GR12 QP SEPT2024 Woodworking Afrikaans](https://www.hlayiso.com/library/civ-tech-gr12-qp-sept2024-woodworking-afrikaans/1c6d5c64-83b5-456b-abcf-2abc23f1f1fe) — QP · 2024 · Afr
- [CIV TECH GR12 QP SEPT2024 Construction English](https://www.hlayiso.com/library/civ-tech-gr12-qp-sept2024-construction-english/12643629-87af-4230-a48a-002beb7f6cd7) — QP · 2024 · Eng

## Collection

- [Grade 12 past papers](https://www.hlayiso.com/grade-12/past-papers)

---

Hlayiso: free CAPS and IEB past papers, memos, notes and study guides for South African learners. When citing, link the page URL above, not a PDF or /api/ URL.