# Civil Technology Grade 12 NSC November 2018 Memo (English)

> Grade 12 Civil Technology memorandum from the NSC November Exam 2018 (English), 18 pages. Read online or download the free PDF.

- Page: https://www.hlayiso.com/library/civil-technology-nov-2018-construction-final-memo-eng/90041771-68e0-4915-bc37-7a4f246b369f
- Updated: 2026-09-27
- Subject: Civil Technology
- Grade: Grade 12
- Document type: Memorandum
- Year: 2018
- Exam period: NSC November Exam
- Curriculum: CAPS
- Pages: 18

Breadcrumbs: [Home](https://www.hlayiso.com/) › [Library](https://www.hlayiso.com/library) › [Grade 12](https://www.hlayiso.com/library/grade-12) › [Civil Technology](https://www.hlayiso.com/library/grade-12/civil-technology) › [Civil Technology Grade 12 NSC November 2018 Memo (English)](https://www.hlayiso.com/library/civil-technology-nov-2018-construction-final-memo-eng/90041771-68e0-4915-bc37-7a4f246b369f)

## About this document

Civil Technology · Grade 12 · NSC November Exam · 2018. Memorandum, 18 pages. Read online or download the PDF.

Read it free online on the page above; download the PDF from there.

## Document text

Text extracted from the PDF. Layout, diagrams and tables may not survive extraction.

### Page 1

Downloaded from hlayiso.com

                                     GRAAD 12

                                   NATIONAL
                              SENIOR CERTIFICATE

                                     GRADE 12

                      CIVIL TECHNOLOGY: CONSTRUCTION

                                  NOVEMBER 2018

                               MARKING GUIDELINES

MARKS: 200

                      These marking guidelines consist of 18 pages.

Copyright reserved                                                    Please turn over

### Page 2

Downloaded from
Civil Technology: Construction     2
                                       hlayiso.com
                                                 DBE/ November 2018
                                      NSC – Marking Guidelines

QUESTION          1:   OHSA, MATERIALS,           TOOLS,      EQUIPMENT     AND     JOINING
                       (GENERIC)

1.1
          1.1.1         F                                                                           (1)

          1.1.2         A                                                                           (1)

          1.1.3         G                                                                           (1)

          1.1.4         E                                                                           (1)

          1.1.5         B                                                                           (1)

1.2           •    Do not throw any tools or materials from a scaffold. 
              •    Never jump on to and off a scaffold. 
              •    Never overload a scaffold.
              •    Remove or cover sharp edges or corners.
              •    Always attach free-standing scaffoldings to a building.
              •    Use a ladder to get on and off a scaffold.
              •    Keep free of waste or any other obstruction.
              •    Never jump on a scaffold while working on it.
              •    Responsible/qualified person must ensure that scaffolding is safe,
                   rigid, stable and firm or has no defects.
              •    Scaffold must be supplied with guard rails/toe boards.
              •    Scaffolds must be levelled on uneven ground.
              •    Do not work on a scaffold in bad weather.
              •    Wear a safety harness when working on scaffolding.
              •    Do not throw tools on/off a scaffold.

          ANY TWO OF THE ABOVE                                                                       (2)

1.3           •      It prevents workers from falling off the scaffold. 
              •      It is used as a handrail. 
              •      It is used to strap on safety harnesses.
              •      To protect the worker working on the scaffold.

          ANY TWO OF THE ABOVE                                                                       (2)
1.4       •        The primary purpose of painting is to protect metals, wood and other
                   material against corrosion and decay. 
          •        Provides a decorative/aesthetic appearance/finishing. 
          •        Protects surfaces from moisture penetration.
          •        Protects surfaces from rust/uv rays.

          ANY TWO OF THE ABOVE                                                                       (2)

Copyright reserved                                                                Please turn over

### Page 3

Downloaded from
Civil Technology: Construction   3
                                     hlayiso.com
                                               DBE/November 2018
                                    NSC – Marking Guidelines

1.5       The curing of concrete:
          •     Increases the strength of concrete. 
          •     Decreases the permeability of hardened concrete.
          •     Improves durability of concrete by reducing cracks.
          •     Makes concrete more watertight.
          •     Minimises shrinkage cracks in concrete.
          •     Provides volume stability.
          •     Cured concrete can carry more weight without breaking/crumbling
                than uncured concrete.
          •     Prevents rapid drying of concrete.
          •     Curing ensures that the hydration process continues.

          ANY ONE OF THE ABOVE                                                                     (1)

1.6

          1.6.1        Multi detector                                                             (1)

          1.6.2        Tool A is used:
                       •      to detect materials found in/behind walls, ceilings and
                              underneath floors, including ferrous and non-ferrous metals,
                              electrical wiring, wood and metal studs. 
                       •      to locate steel bars and copper pipes. 
                       •      in carpentry, plumbing, and construction.
                       •      to measure the distance to/from covered objects.

                       ANY TWO OF THE ABOVE                                                        (2)

          1.6.3        The batteries must be removed from the tool:
                       •     to prevent the battery from running flat/battery can die. 
                       •     to prevent acid leaks from batteries damaging the tool.

                       ANY ONE OF THE ABOVE                                                        (1)

1.7

          1.7.1        A – Bolt and nut/Bolt 
                       B – Rawl bolt                                                              (2)

          1.7.2        Bolt and nut
                       •      Bolts and nuts are used to secure pipe supports to metal
                              parts. 
                       •      To join components together.
                       Rawl bolt
                       •      A Rawl bolt is used to fix a truss hanger to a wall. 
                       •      To fix brackets/structures/panels to a wall/concrete.
                       •      For construction, renovation and industrial work

                       ANY TWO OF THE ABOVE                                                        (2)
                                                                                                   [20]

Copyright reserved                                                              Please turn over

### Page 4

Downloaded from
Civil Technology: Construction   4
                                     hlayiso.com
                                               DBE/November 2018
                                    NSC – Marking Guidelines

QUESTION 2: GRAPHICS AS METHOD OF COMMUNICATION (GENERIC)

ANSWER SHEET 2
NO.                    QUESTIONS                                  ANSWERS                    MARKS

  1     Identify FIGURE A.                           South Elevation/Elevation                     1

  2     Identify FIGURE B.                           Ground floor plan/floorplan                   1

                                                     First floor level/Second floor
  3     Identify number 4.                           level/Suspended floor/Floor level/             1
                                                     dash line/ FFL/Expansion joint 

  4     Identify number 5.                           Window Sill                                   1

                                                     Hand wash basin/Wash
  5     Identify number 9.                                                                          1
                                                     basin/Washing basin/HWB/basin 

  6     Identify number 10.                          Water closet/WC/Toilet pan                    1

  7     Identify number 11.                          Bath/B                                        1

  8     On what date was the plan printed?           2018/10/02                                    1

  9     Who drew the building plan?                  JP Maloi                                      1

        Name the feature in the column for the
 10     notes in FIGURE 2 that must be          Ramp                                               1
        installed in front of the sliding door.

        Name the feature in the column for the
 11     notes in FIGURE 2 that must give                                                            1
                                               Staircase/Stairs/Stairway
        access to the first floor.

        Identify the type of roof that is used for
 12                                                  Gable roof                                    1
        the building in FIGURE A.

                                                     To cover the opening/close the gap
                                                     between the two slopes of the roof.
                                                     
 13     Explain the purpose of number 1.             Prevent water and other elements               1
                                                     from entering the roof.
                                                     ANY ONE OF THE ABOVE

Copyright reserved                                                               Please turn over

### Page 5

Downloaded from
Civil Technology: Construction   5
                                     hlayiso.com
                                               DBE/November 2018
                                  NSC – Marking Guidelines

                                                  •   To prevent water from falling
                                                      onto the ground 
                                                  •   To collect rainwater
                                                  •   To channel the rainwater into
                                                      the downpipe
 14     Explain the purpose of number 2.          •   To protect the wall from water               1
                                                  •   To hide the rafters/finish off the
                                                      roof
                                                  ANY ONE OF THE ABOVE

        Explain the abbreviation FFL at
 15                                               Finished floor level                            1
        number 6.

                                                  To channel the water from the gutter
 16     Explain the purpose of number 7.                                                           1
                                                  to the ground. 

        Explain the meaning of the arrow on
                                                  It indicates the direction of the slope
 17     the feature that must be installed in                                                      1
                                                  of the ramp/it indicates the slope. 
        front of the sliding door.

                                                  It indicates the slope or the gradient
        Explain what is meant by 1:10             of the ramp/for every 10 metres
 18                                                                                                1
        indicated on the symbol in the notes.     horizontally rises 1 metre
                                                  vertically.

 19     Which room will feature 15 serve?         The bathroom.                                   1

                                                  •   Indicates what direction the
                                                      window is opening/window
                                                      opening. 
                                                  •   Indicates the location of the
        Explain the short dash lines on the           hinges.
 20                                                                                                1
        windows.                                  •   Indicates the location of the
                                                      casement stay.
                                                  ANY ONE OF THE ABOVE

        Deduce the height of window 2 from
 21                                               1,2 m or 1 200 mm (Ignore units)                1
        the window schedule.

        Deduce the width of window 3 from
 22                                               2 m or 2 000 mm (Ignore units)                  1
        the window schedule.

        On what elevation of the building is
 23                                               Western elevation/Western side                  1
        the bathroom window situated?

Copyright reserved                                                              Please turn over

### Page 6

Downloaded from
Civil Technology: Construction   6
                                     hlayiso.com
                                               DBE/November 2018
                                   NSC – Marking Guidelines

                                                   3 – window/window frame/reveal
                                                   frame stile/casement stile 
        Differentiate between component
 24                                                                                                   2
        number 3 and component number 8.
                                                   8 – sliding door /door frame/
                                                   door/reveal /sliding door stile 

                                                   The light in the lounge is a
                                                   fluorescent light/1 x 40W/2x40/3x40
        Differentiate between the light in the
 25                                                fluorescent light  and the light in               2
        lounge and the light in the bathroom.
                                                   the bathroom is a normal ceiling
                                                   light 

                                                   Tile/ Vinyl flooring (Novilon)/
                                                   Coloured screed/Polished or stained
        Recommend a suitable floor covering        concrete flooring/Water proof
 26                                                                                                   1
        for the bathroom.                          laminated floor/carpet. 
                                                   ANY ACCEPTABLE ANSWER

        Recommend an appropriate scale to
 27     which FIGURE A should be drawn,            1:50/100/200                                      1
        according to SANS.

        Recommend an alternative sanitary
 28     fitment to replace number 11 that will     Shower                                            1
        serve a similar purpose.

        Calculate the internal area of the office 4 m  x 3 m  = 12 m²  OR 12
 29                                                                                                   3
        in m² Show ALL calculations.              4 000 X 3 000 = 12 000 000mm2
                                                   Positive marking

                                                    (220 + 3 000 + 110 + 2 800 + 220)  x 2 

                                                   = 6 350 x 2

                                                   =12 700 mm 

        Calculate the perimeter of the building. (220 + 4 000 + 110 + 2 000 + 220)  x 2 
 30                                                = 6 550 x 2
                                                                                                      7
        Show ALL calculations.
                                                   = 13 100 mm 

                                                   12 700 + 13 100 mm

                                                   = 25 800 mm  OR

                                                   = 25,8 m

                                                                                    TOTAL             40

Copyright reserved                                                                 Please turn over

### Page 7

Downloaded from
Civil Technology: Construction   7
                                     hlayiso.com
                                               DBE/November 2018
                                  NSC – Marking Guidelines

QUESTION 3: ROOFS, STAIRCASES AND JOINING (SPECIFIC)

3.1       5°/10/30°                                                                            (1)

3.2       1 400 mm                                                                             (1)

3.3

                             
          (Square)                                    (Rectangular)
          Batten

                             

          Purlin

          ANY ONE OF THE ABOVE                                                                  (2)

3.4       50 mm x 76 mm/ 76 mm x 50 mm  OR 76 mm x 76 mm                                       (1)

3.5
           Clay roof tiles                         Fibre cement tiles
                                                                                                (2)
           650 mm/closer together                 760 mm/ further apart 

3.6       A - Ridge capping/Ridge plate/Roof capping 
          B - Roof covering/Corrugated iron roof/IBR iron roof/roof sheeting 
          C - Gang nail/Nail plate/Connector plate/Joining piece 
          D - King post                                                                        (4)

Copyright reserved                                                           Please turn over

### Page 8

Downloaded from
Civil Technology: Construction   8
                                     hlayiso.com
                                               DBE/November 2018
                                     NSC – Marking Guidelines

3.7
                                                    

                                       
                                                   
                                                                    

                                                                           
                                                2 800 mm

                                                                        
                          

            ASSESSMENT CRITERIA                             MARK    CANDIDATE'S
                                                                       MARK
            Walls                                               2
            Wall plates (Wrong position – 1 mark)               2
            Rafters                                             2
            Collar beam/Collar tie                              1
            Ridge beam correctly drawn                          1
                                             TOTAL:             8
                                                                                                   (8)

3.8

          3.8.1        Riser                                                                      (1)

          3.8.2        Balusters                                                                  (1)

          3.8.3        Going/Tread                                                                (1)

          3.8.4        Landing                                                                    (1)

          3.8.5        Run                                                                        (1)

3.9                                               

                                 AND
                                      OR                                                           (2)
ANY TWO OF THE ABOVE OR ANY OTHER SHAPE RESEMBLING A SQUARE OR
ROUND SHAPE/ 2 AND 3 DIMENSIONAL DRAWINGS ACCEPTABLE

Copyright reserved                                                              Please turn over

### Page 9

Downloaded from
Civil Technology: Construction   9
                                     hlayiso.com
                                               DBE/November 2018
                                    NSC – Marking Guidelines

3.10          •   Screwed on to the face of the wall. 
              •   By means of a bracket.
              •   Fixed to face of wall using Rawl bolts or sleeved anchors by means of
                  a bracket.

          ANY ONE OF THE ABOVE                                                                     (1)

3.11          •   Timber that is bolted to the top of the wall.
              •   Nailed or screwed to the wall. 
              •   A galvanised strap/hoop iron nailed or built into the wall.
              •   Tie with roof wire built into wall.

          ANY TWO OF THE ABOVE                                                                     (2)

3.12          •   Supports the steel and withstands the loads. 
              •   The pin serves as a pivoting point to adjust the angle or to lower the
                  steel section.
              •   The pin can be removed to separate the steel section from the base.
              •   To keep the steel section attached to the base plate/concrete base.

          ANY ONE OF THE ABOVE                                                                     (1)
                                                                                                   [30]

Copyright reserved                                                              Please turn over

### Page 10

Downloaded from
Civil Technology: Construction   10
                                     hlayiso.com
                                               DBE/November 2018
                                  NSC – Marking Guidelines

QUESTION 4:          EXCAVATIONS, FORMWORK, TOOLS AND EQUIPMENT AND
                     MATERIALS (SPECIFIC)
4.1       4.1.1 C 
          4.1.2 D 
          4.1.3 F 
          4.1.4 E 
          4.1.5 A                                                                               (5)

4.2.1     •    Keep excavated soil away from edge at least 600 mm. 
          •    Identify any equipment that will affect trench stability. 
          •    Trenches should be inspected at the start of each shift. 
          •    Trenches should be inspected after a rain storm.
          •    No worker will be allowed to work or move in trenches deeper then
               1,5 metres if the sides are not protected by formwork or braced.
          •    Test for atmospheric hazards (low oxygen, hazardous fumes and
               toxic gases) when trenches are more than 1,3 metres deep.
          •    No load vehicle or plant equipment should be used, placed driven or
               used on or near the edge of any excavation where it is likely to
               cause a collapse and endanger workers lives.
          •    A warning system for mobile equipment should be provided.
          •    Always protect workers from loose rock or soil that could fall or roll from
               an excavation by installing protective barricades at appropriate intervals.
          •    Prohibit workers from working on faces of slopes or benched
               excavations at levels above other workers, unless workers at a
               lower level is protected against hazards of falling or sliding material
               or equipment.
          •    Members/parts of the support system (formwork or shuttering) should
               be securely connected to prevent sliding, falling material.
          •    Avoid overloading members of support systems.
          •    Formwork/shuttering should be removed in a manner that will protect
               workers from cave-ins.
          •    Before temporary removal of individual formwork members/parts,
               additional precautions should be in place, installing other structural
               members.
          •    Backfilling should always progress with the removal of the support
               system (formwork from the excavation).
          •    The area should be cordoned off and warning signs must be posted
               and must be clearly visible.
          •    Cover the entire work area after hours, especially if children might
               gain entry to the site.
          •    A suitable barrier(fence) must be provided where any excavation is
               more than 2 metres deep.
          •    Excavation sites should be well lit at night.
          •    Red warning lights should be placed strategically to warn the public.
          •    Workers should not work under suspended or raised loads of materials.
          •    Always start dismantling the formwork from the bottom of the formwork.
          •    Never work alone in deep excavations.

          ANY THREE OF THE ABOVE                                                                 (3)

Copyright reserved                                                            Please turn over

### Page 11

Downloaded from
Civil Technology: Construction   11
                                     hlayiso.com
                                               DBE/November 2018
                                     NSC – Marking Guidelines

4.2.2      •     The site must be levelled. 
           •     The site must be cleared properly, and all loose soil must be removed.
           •     A baseline must be established.                                                (3)

4.3
                                                 Poling boards 

                                                   Folding wedges
                                                  Struts
                                                  Walling boards 

                      
                                                       Wedge pair also accepted
          Shuttering correctly drawn      
           ASSESSMENT CRITERIA                              MARK      CANDIDATE'S
                                                                         MARK
           Folding wedges                                       1
           Walling boards                                       1
           Poling boards                                        2
           Struts                                               1
           Shuttering correctly drawn                           1
           Any TWO labels                                       2
                                                TOTAL:          8                                (8)

4.4       Good formwork should be:
            • made accurately to the dimensions. 
            • stable enough to bear the load of wet concrete.
            • bear the mass of workers on it.
            • able to withstand the vibrating and tamping of concrete.
            • strong enough to provide enough support, without too much deflection,
                until the concrete has set and cured.
            • easy to repair on site.
            • secured with wire nails so that it can be easily dismantled.
            • secured with bolts and nuts ranging from 13 mm to 19 mm in diameter.
            • should be sealed properly.
            • should be free of dirt such as saw dust.
            • quick and simple to erect to ensure the correct cover depth for the
                reinforcing.
            • removed only when concrete has cured.
            • close-fittings along seams and joints.
            • made of recyclable components.
            • fitted with plywood laggings for a smooth finish.
            • ensure the correct cover depth for the reinforcing in order to prevent
                structural failure.
            • sealed properly so that the concrete does not leak and form a
                honeycomb effect.
          ANY ONE OF THE ABOVE                                                                   (1)

Copyright reserved                                                            Please turn over

### Page 12

Downloaded from
Civil Technology: Construction   12
                                     hlayiso.com
                                               DBE/November 2018
                                       NSC – Marking Guidelines

4.5
          4.5.1        Beam formwork/Formwork for beams                                             (1)

          4.5.2        A - Tie 50 mm x 25 mm at 600 mm centres 
                       B - Cleat 76 mm x 50 mm 
                       C - Fixing plate/Kicker plate 76 mm x 50 mm 
                       D - Brace/Strut 76 mm x 25 mm                                                (4)

          4.5.3            •      The shape of folding wedges simplifies the erecting and
                                  dismantling of formwork. 
                           •      Folding wedges can easily be removed by knocking one
                                  away from the other.
                           •      Folding wedges help to keep formwork components
                                  sturdy/secured/stable.
                           •      Folding wedges play an important role in the levelling of
                                  formwork for beams, floor slabs and columns.
                           •      Folding wedges facilitate the raising or lowering of the
                                  formwork to the required height.
                           •      Folding wedges are used as pins to strengthen adjoining
                                  concrete formwork                                                  (1)

          ANY ONE OF THE ABOVE

4.6           •      Sturdy/Rigid enough to bear the mass of wet concrete without
                     collapsing.
              •      Stronger than wood and timber board products. 
              •      Easily removed when the concrete has set.
              •      Not as adaptable as timber shuttering.
              •      More expensive than timber.
              •      Will last longer than timber.
              •      Can be used repeatedly.
              •      Tight along the seams and joints so that concrete does not leak.
              •      It’s prone to rust.
                                                                                                     (2)
          ANY TWO OF THE ABOVE

4.7       4.7.1            •     Operate with care and wear appropriate personal protective
                                 equipment. 
                           •     Check the controls for proper response before use.
                           •     Check the condition of the machine at the start and end of
                                 each shift.
                           •     Never use a faulty machine.
                           •     Never lay the machine on its side.
                           •     Do not allow the vibrating pipe to make contact with any part
                                 of the body or formwork.
                           •     Switch of the machine when it is left unattended.
                           •     Long use of the machine exposes the operator to vibrations.
                                 Stop if you feel numbness.
                           •     Switch off the machine and wait for all moving parts to stop
                                 before adjusting, repairing, inspecting or cleaning it.
                           •     Must be operated by a qualified person.                             (2)

Copyright reserved                                                                Please turn over

### Page 13

Downloaded from
Civil Technology: Construction    13
                                      hlayiso.com
                                                DBE/November 2018
                                       NSC – Marking Guidelines

          ANY TWO OF THE ABOVE

          4.7.2            •     Maintain like all machinery. Lubricate and adjust according
                                 to the manufacturer’s instruction. 
                           •     Clean after use and store in a safe dry place. 
                           •     Service the concrete vibrator regularly.
                           •     Repair or replace damaged electric cords.                           (2)

          ANY TWO OF THE ABOVE

4.8           •      Service the tamping rammer/plate compactor regularly. 
              •      Remove loose dirt and soil after use. 
              •      Maintain like all machinery, lubricate and adjust according to the
                     manufacturers instruction.
              •      Clean after use.
              •      Store in a safe dry place.
              •      Ensure that all parts are firmly attached to the machine.
              •      Repair or replace damaged electric cords.
                                                                                                     (2)
          ANY TWO OF THE ABOVE

4.9       Ready-mix concrete:
            • is very expensive. 
            • delivery and pouring delays may affect the quality of the concrete. 
            • site batching in residential areas raises concerns about noise levels
            • must be poured within a specified time.
            • trucks may damage or soil house frontages and sidewalks.
            • contaminations of storm-water drains.

          ANY TWO OF THE ABOVE                                                                       (2)

4.10      The purpose of the slump test:
             • is to test the density of the concrete before it is placed by determining
                the percentage of water it contains. 
             • Is to determine the workability and consistency of the batches that are
                mixed. 
             • To determine the slump of the mixture.

          ANY TWO OF THE ABOVE                                                                       (2)

4.11          •   Water – hosepipe or continuous spraying 
              •   Water- retaining substances, such as damp sand, damp sacking,
                  straw, hessian and canvas. 
              •   Plastic membranes and plastic sheeting
              •   Chemical curing products

          ANY TWO OF THE ABOVE                                                                       (2)
                                                                                                     [40]

Copyright reserved                                                                Please turn over

### Page 14

Downloaded from
Civil Technology: Construction   14
                                     hlayiso.com
                                               DBE/November 2018
                                     NSC – Marking Guidelines

QUESTION 5:          PLASTER AND SCREED, BRICKWORK AND GRAPHICS AS
                     MEANS OF COMMUNICATION (SPECIFIC)

5.1

          5.1.1        A - Wet the wall thoroughly 
                       B - Apply plaster 
                       C - Scrape the plaster to obtain a flat surface/levelling 
                       D - Float to smooth the surface                                             (4)

          5.1.2        Straight edge                                                               (1)

5.2                                                                     
                                                                              

                                                        

                                            LEFT VIEW INCORRECTLY DRAWN -1
          CRITERIA ASSESSMENT                            MARK CANDIDATE'S
                                                                  MARK
          Full bricks and ½ brick every alternate course   4
          on front view
          Left view full brick every course                1
          Left view ¼ brick every course                   1
                                                 TOTAL:    6                                        (6)

5.3

          5.3.1        A- Herring bone paving pattern 
                       B- Basket-weave paving pattern                                              (2)

          5.3.2            •     Dry-laid or sand-set 
                           •     Bitumen-set
                           •     Mortar-set

                       ANY ONE OF THE ABOVE                                                         (1)

          5.3.3            • River/Plaster sand is used to grout between paving bricks.
                           • Sand mixed with cement is used to grout between paving
                             bricks 
                       ANY ONE OF THE ABOVE                                                         (1)

Copyright reserved                                                               Please turn over

### Page 15

Downloaded from
Civil Technology: Construction   15
                                     hlayiso.com
                                               DBE/November 2018
                                 NSC – Marking Guidelines

5.4

                                                                                ROOF COVERING 

                                                                                PURLIN 76 X 50 
                                                          

                                                                               RAFTER 114 X 38

                                                                               BEAM FILLING
                                                                               TIE BEAM 114 X 38
                                               
                                                                                WALL PLATE 114 X 38
                     

                                                                                WALL
           
                                                   

                                                                                FASCIA BOARD 230 X 30

                                               SCALE: 1:10 
          NOT DRAWN TO SCALE                                           APPLICATION OF SCALE  

          USE A MASK TO MARK THIS QUESTION ACCEPT ANY ANGLE
          BETWEEN 30° AND 45°.

           ASSESSMENT CRITERIA                             MARK          CANDIDATE'S
                                                                            MARK
           Wall: 220 mm wide face brick                        1
           Beam filling                                        1
           Wall plate 114 mm x 38 mm                           1
           Tie beam 114 mm x 38 mm                             1
           Rafter 114 mm x 38 mm                               1
           Purlins 76 mm x 50 mm                               2
           Corrugated iron roof covering                       1
           Fascia board 230 mm x 38 mm                         1
           Any TWO labels                                      2
           Print the scale below the drawing                   1
           Application of scale
           One or two incorrect          =3
           Three or four incorrect       =2                    3
           More than five incorrect      =1
           No measurement correct        =0
           TOTAL                                               15                                   (15)
                                                                                                    [30]

Copyright reserved                                                               Please turn over

### Page 16

Downloaded from
Civil Technology: Construction    16
                                      hlayiso.com
                                                DBE/November 2018
                                 NSC – Marking Guidelines

QUESTION 6:           REINFORCEMENT IN CONCRETE, FOUNDATIONS, CONCRETE
                      FLOOR AND QUANTITIES (SPECIFIC)

6.1

          6.1.1        B                                                                       (1)

          6.1.2        D                                                                       (1)

          6.1.3        D                                                                       (1)

          6.1.4        B                                                                       (1)

          6.1.5        A                                                                       (1)

6.2
                                                            Minimum concrete cover
                                       

                                                           Stirrups 

                                                            Main bars 
                                             

                                                           Proportion 

              ASSESSMENT CRITERIA            MARK CANDIDATE'S
                                                     MARK
           Column                              2
           8 Main bars                         2
           Binders/Stirrups                    2
           Min concrete cover                  1
           Any TWO Labels                      2
           Proportion                          1
           TOTAL                              10                                                (10)

Copyright reserved                                                           Please turn over

### Page 17

Downloaded from
Civil Technology: Construction   17
                                     hlayiso.com
                                               DBE/November 2018
                                      NSC – Marking Guidelines

6.3       Pile foundations:
              •     can be used in poor/unstable/soft/loose soil. 
              •     can be used anywhere even in water. 
              •     the larger base ensures stability. 
              •     is relatively quick to install if the equipment is available.
              •     where pre-fabricated piles are used, much time is saved.
              •     resists tensile stress well.
              •     is quick and less expensive to produce.
              •     can be manufactured and transported elsewhere.
              •     can be installed in poor weather conditions.
              •     the length can easily be adjusted.
              •     offers good resistance against moving soil.

          ANY THREE OF THE ABOVE                                                                   (3)

6.4           •   Metal pipes that contain a dry concrete mix (gravel plug) are driven into
                  a drilled hole in the ground. 
              •   The pipe is held firmly in position while a drop hammer is used to drive
                  the pre-filled dry concrete mix (gravel plug) out of the pipe to form an
                  extended base (toe) at the bottom of the hole. 
              •   Concrete is now poured into the pipe and compacted, using an internal
                  drop hammer, until the pipe is filled to the top. 
              •   The steel pipe is slowly extracted as the concrete is poured into the
                  pipe.

          ANY THREE OF THE ABOVE                                                                   (3)

6.5       6.5.1        Hollow-core concrete block/Concrete block/Block                            (1)

          6.5.2       •   Used for the placement of the conduit pipes. 
                      •   Serves as insulation.
                      •   Reduce the weight.

                       ANY ONE OF THE ABOVE                                                        (1)

          6.5.3        Reinforced ribs/Ribs/Pre-stressed concrete ribs                            (1)

          6.5.4            •     Ribs (pre-stressed reinforced ribs) 
                           •     Hollow-core blocks (polystyrene blocks can also be used) 
                           •     Steel mat/Mesh/Steel/Reinforcement 
                           •     In-situ cast concrete/Concrete
                           •     Spacers

                       ANY THREE OF THE ABOVE                                                      (3)

Copyright reserved                                                              Please turn over

### Page 18

Downloaded from
Civil Technology: Construction   18
                                     hlayiso.com
                                               DBE/ November 2018
                                   NSC – Marking Guidelines

          6.5.5       After the installation of a rib-and-block floor:
                      • Ensure that the correct curing procedure is followed for 7 days
                         to ensure a well-set slab. 
                      • allow 28 days for setting of the concrete slab.
                      • temporary props can be removed after the concrete slab has
                         reached a crushing strength of 17 MPa.

                       ANY ONE OF THE ABOVE                                                 (1)

          6.5.6       •   Because the units are precast, mechanical handling is required
                          on site. 
                      •   The placing of the blocks between the ribs requires manual
                          labour.                                                          (2)

6.6

ANSWER SHEET 6.6

 A          B              C                                    D
                                   Skirting: Inside length of building
                                               = 8 000 mm – 440 mm  OR – 2(220)
                                               = 7 560 mm                            (2)
                                   Skirting: Inside width of the building
                                            = 5 000 mm – 440 mm  OR – 2(220)
                                            = 4 560 mm                               (2)
                                   Total length = 7 560 + 4 560 x 2
                                                =12,12 x 2
                                                = 24,24  meter skirting needed
                                                – 0,900 m for the door.
                                                = 23,34 m                            (2)

1/
                                   Screed: Inside area of building
         7,56 
         4,56 
        0,025         0,86 m³            = 0,86 m³ screed is needed                (4)

                                                                                            (10)
                                                                                            [40]

                                                                                  TOTAL:    200

Copyright reserved

## Related documents

- [Civil Technology Nov 2018 (Woodworking) Memo FINAL Eng](https://www.hlayiso.com/library/civil-technology-nov-2018-woodworking-memo-final-eng/2cdca6a9-a7a6-411c-9a30-4575c8e6a5cf) — Civil Technology · Memo · 2018 · Eng
- [Civil Technology Nov 2018 (Civil Services) FINAL Memo Eng](https://www.hlayiso.com/library/civil-technology-nov-2018-civil-services-final-memo-eng/f4e1d2a3-db17-47d5-8ae8-6332d121a6d3) — Civil Technology · Memo · 2018 · Eng
- [Civil Technology Nov 2018 (Construction) Afr](https://www.hlayiso.com/library/civil-technology-nov-2018-construction-afr/be54c81a-cc52-4da7-a74c-ec3f0bddf626) — Civil Technology · QP · 2018 · Afr
- [Civil Technology Nov 2018 (Woodworking) Afr](https://www.hlayiso.com/library/civil-technology-nov-2018-woodworking-afr/8a4b5aba-d78e-4505-aae9-e127ef45df85) — Civil Technology · QP · 2018 · Afr
- [CVLT GR12 MEMO ENG SEPT2018 CONSTRUCTION](https://www.hlayiso.com/library/cvlt-gr12-memo-eng-sept2018-construction-1/b6d609b6-89a5-4b39-a9b7-0d878af45cd4) — Civil Technology · Memo · 2018 · Eng
- [CVLT GR12 MEMO AFR SEPT2018 SIVIELE DIENSTE D](https://www.hlayiso.com/library/cvlt-gr12-memo-afr-sept2018-siviele-dienste-d/f328c182-752d-488c-88b6-f2a5cadcbcf2) — Civil Technology · Memo · 2018 · Afr

## More from Grade 12 Civil Technology

- [CVLT Woodworking Eng watermark](https://www.hlayiso.com/library/cvlt-woodworking-eng-watermark/8e178c6e-fa7b-40f4-8a2c-936e0bee3b38) — QP · 2025 · Eng
- [Civil Technology (Woodwork) (English and Afrikaans) June 2025 Question Paper](https://www.hlayiso.com/library/civil-technology-woodwork-english-and-afrikaans-june-2025-question-paper/c8edd459-5237-48e0-8588-69d7ecd7f8e5) — QP · 2025 · Afr
- [Civil Technology May-June 2025 (Construction) Afr](https://www.hlayiso.com/library/civil-technology-may-june-2025-construction-afr/591d6ffd-20b1-4748-a1ba-b055be0a14c3) — QP · 2025 · Afr
- [Civil Technology Nov 2025 (Woodworking) Afr](https://www.hlayiso.com/library/grade-12-civil-technology-2025-nsc-november-exam-question-paper/05a95faf-5891-4d88-9e5e-7d13c1d21648) — QP · 2025 · Afr
- [CIV TECH GR12 QP SEPT2024 Woodworking Afrikaans](https://www.hlayiso.com/library/civ-tech-gr12-qp-sept2024-woodworking-afrikaans/1c6d5c64-83b5-456b-abcf-2abc23f1f1fe) — QP · 2024 · Afr
- [CIV TECH GR12 QP SEPT2024 Construction English](https://www.hlayiso.com/library/civ-tech-gr12-qp-sept2024-construction-english/12643629-87af-4230-a48a-002beb7f6cd7) — QP · 2024 · Eng

## Collection

- [Grade 12 past papers](https://www.hlayiso.com/grade-12/past-papers)

---

Hlayiso: free CAPS and IEB past papers, memos, notes and study guides for South African learners. When citing, link the page URL above, not a PDF or /api/ URL.