# Civil Technology Grade 12 NSC November 2019 QP (Eng)

> Grade 12 Civil Technology question paper from the NSC November Exam 2019 (English), 22 pages. Read online or download the free PDF.

- Page: https://www.hlayiso.com/library/civil-technology-nov-2019-civil-services-eng/52c5e936-0c5c-4ea4-8929-a76fdaa48f02
- Updated: 2026-09-27
- Subject: Civil Technology
- Grade: Grade 12
- Document type: Question paper
- Year: 2019
- Exam period: NSC November Exam
- Curriculum: CAPS
- Pages: 22

Breadcrumbs: [Home](https://www.hlayiso.com/) › [Library](https://www.hlayiso.com/library) › [Grade 12](https://www.hlayiso.com/library/grade-12) › [Civil Technology](https://www.hlayiso.com/library/grade-12/civil-technology) › [Civil Technology Grade 12 NSC November 2019 QP (Eng)](https://www.hlayiso.com/library/civil-technology-nov-2019-civil-services-eng/52c5e936-0c5c-4ea4-8929-a76fdaa48f02)

## About this document

Civil Technology · Grade 12 · NSC November Exam · 2019. Question paper, 22 pages. Read online or download the PDF.

Read it free online on the page above; download the PDF from there.

## Document text

Text extracted from the PDF. Layout, diagrams and tables may not survive extraction.

### Page 1

Downloaded from hlayiso.com

~Y,
. $ basic education

, \

=
raat Department:
AG) Basic Education
Sad REPUBLIC OF SOUTH AFRICA

NATIONAL
SENIOR CERTIFICATE
GRADE 12

PA iieielaieialel hike ee

*

1 CIVIL TECHNOLOGY: CIVIL SERVICES "

i a

" NOVEMBER 2019 ;

Tre rrrrrrrerrT TTT Trrrr reer rrr errr reer errr sd
MARKS: 200
TIME: 3 hours

This question paper consists of 15 pages and 5 answer sheets.

Copyright reserved Please turn over

### Page 2

Downloaded from hlayiso.com

Civil Technology: Civil Services 2 DBE/November 2019
NSC

REQUIREMENTS:

1. Drawing instruments
2. A non-programmable calculator
3. ANSWER BOOK

INSTRUCTIONS AND INFORMATION

1. This question paper consists of SIX questions.

2. Answer ALL the questions.

3. Answer each question as a whole. Do NOT separate subsections of
questions.

4. Start the answer to EACH question on a NEW page.

5. Do NOT write in the margins of the ANSWER BOOK.

6. You may use sketches to illustrate your answers.

7. Write ALL calculations and answers in the ANSWER BOOK or on the
attached ANSWER SHEETS.

8. Use the mark allocation as a guide to the length of your answers.

9. Make drawings and sketches in pencil, fully dimensioned and neatly finished

off with descriptive titles and notes to conform to the SANS/SABS Code of
Practice for Building Drawings.

10. For the purpose of this question paper, the size of a brick should be taken as
220 mm x 110 mm x 75 mm.

11. Use your own discretion where dimensions and/or details have been omitted.

12. Answer QUESTIONS 2, 3.6, 5.4, 6.8 and 6.9 on the attached ANSWER
SHEETS using drawing instruments where necessary.

13. Write your CENTRE NUMBER and EXAMINATION NUMBER on every
ANSWER SHEET and hand them in with your ANSWER BOOK, whether you
have used them or not.

14. Drawings in the question paper are NOT to scale due to electronic transfer.

15. Google Images was used as the source of all photographs and pictures.

Copyright reserved Please turn over

### Page 3

Downloaded from hlayiso.com

Civil Technology: Civil Services 3 DBE/November 2019
NSC

QUESTION 1: OHSA, SAFETY, MATERIALS, TOOLS, EQUIPMENT AND JOINING
(GENERIC)

Start this question on a NEW page.

1.4 Choose a description from COLUMN B that matches an item in COLUMN A.

Write only the letter (A—K) next to the question numbers (1.1.1 to 1.1.8) in the
ANSWER BOOK, e.g. 1.1.9 L.

COLUMN A COLUMN B
1.1.1 PVA paint A method of finishing metal exposed to
heavy wear and tear conditions

1.1.2 Guard rail

B can be applied to walls
1.1.3. Powder coating

C__ keeps rungs free from oil and grease
1.1.4 Builder's hoist

D light material used in the
1.1.5 Ladder manufacturing of door and window

frames
1.1.6 Diagonal brace

| E used as a means to dispose of waste
1.1.7 Galvanising material and debris from elevated

areas in the fastest possible way
1.1.8 Chute

keeps scaffolds stable when erected

G __ transports workers, materials and
equipment between ground and
upper levels

H gates should always be kept shut
when the device is being used

I prevents people from falling off the
scaffolds

J zinc coating applied to the base of
metal

K__used to delay the drying time of paint
(8 x 1)

1.2 Explain TWO advantages of electroplating.

1.3 Name the process when freshly cast concrete is kept moist for a specific
period of time.

Copyright reserved Please turn over

(8)
(2)

(1)

### Page 4

Downloaded from hlayiso.com

Civil Technology: Civil Services 4 DBE/November 2019
NSC
1.4 Explain the purpose of keeping freshly cast concrete moist for a certain period
of time after the concrete has been cast. (1)
1.5 You are transporting material on a construction site from one place to
another. Describe TWO safety precautions that you will adhere to while
transporting the material. (2)
1.6 Describe ONE safety factor that must be considered when using scaffold
planks to erect a scaffold platform. (1)
1.7 FIGURE 1.7 below shows a surveying tool used on a building site.
—_———
G
oe .
FIGURE 1.7
1.7.1 Identify the tool above. (1)
1.7.2 Predict ONE consequence if the instrument is NOT set level. (1)
1.8 FIGURE 1.8 below shows a joining fixture that is used on building sites and in
workshops.
Sa
~~
FIGURE 1.8
1.8.1 Identify the joining fixture above. (1)

1.8.2 Name the fixing agent that should be used with this joining fixture. (1)

1.8.3 Explain ONE use of this joining fixture. (1)
[20]

Copyright reserved Please turn over

### Page 5

Downloaded from hlayiso.com

Civil Technology: Civil Services 5 DBE/November 2019
NSC

QUESTION 2: GRAPHICS AS MEANS OF COMMUNICATION (GENERICS)

Start this question on a NEW page.

FIGURE 2 on the next page shows different drawings that appear on a building plan.
Analyse the drawings and complete the table on ANSWER SHEET 2.

Copyright reserved Please turn over

### Page 6

Downloaded from hlayiso.com

Civil Technology: Civil Services

NSC

DBE/November 2019

FIGURE A
SCALE 1 : 100

NGE=-——{@)

BATHROOM

2100
fo}

ic

3 400

BEDROOM

KITCHEN

©

LOUNGE

)

Wi

wi

y

—

wi

FIGURE B

SCALE 1 : 100

©

NOTE:

Contractors must verify all
dimensions and levels on site before
commencing work. Architects must
be notified of any discrepancies
immediately.

Wail thickness: External = 220 mm
Internal = 110 mm

ARCHITECT'S SIGNATURE
CLIENT'S SIGNATURE

The following electrical installation
should be installed in the kitchen:

Ww

The following symbol shows the type
of brick finishing that will be used for
the building:

REVISION DATE DESCRIPTION

PRINTED BY:
DLAMINI PRINTERS

DATE OF PRINT.
2019/04/01

DRAWING TITLE:
SITE PLAN STAND 502

PROJECT:
PROPOSED DWELLING ON STAND 502,
DEO PARK

PROJECT NO.
GR 228-201

DRAWING NR.
339P9

DATE
16/4/2019

DRAWN
JP MBALI

CHECKED
P CARTER

SCALE
1: 100

REFERENCE CODE
QP 2-2019

WINDOW 1 WINDOW 2

1 800
4.200

Copyright reserved

FIGURE 2

[40]
Please turn over

### Page 7

Downloaded from hlayiso.com

Civil Technology: Civil Services 7 DBE/November 2019
NSC
QUESTION 3: CONSTRUCTION ASSOCIATED WITH CIVIL SERVICES, OHSA,

AND QUANTITIES (SPECIFIC)

Start this question on a NEW page.

3.1

3.2

3.3

Copyright reserved

Complete the following sentence by filling in the TWO missing accessories
for manholes. Write only the word(s) next to the question numbers
(3.1.1 to 3.1.2) in the ANSWER BOOK.

The accessories used for a manhole are (3.1.1) ..., cover slabs, reducing
slabs and (3.1.2) ... (2)

FIGURE 3.2 below shows shoring used in a wet area. Study the drawing and
answer the questions that follow.

A

FIGURE 3.2
3.2.1 Identify A. (1)
3.2.2 State the depth at which the sides of an excavation in saturated
ground will start to cave in. (1)

FIGURE 3.3 below shows an incomplete drawing of the layout of a drainage
system for a house. Study the drawing and answer the questions that follow.

ig LA
P|

FIGURE 3.3

3.3.1 Use the drawing and deduce the number of sanitary fixtures
needed for this house. (1)

Please turn over

### Page 8

Downloaded from hlayiso.com

Civil Technology: Civil Services 8 DBE/November 2019
NSC
3.3.2 Use the drawing and deduce the number of waste-water fixtures
that will be needed for the drainage system. (1)
3.3.3 The internal measurement of the sides of a cubical water reservoir
is 2 700 mm.

Calculate the following:

e Volume of the tank in m? (4)
e Volume of the tank in litres (2)

Show ALL calculations.

3.4 Give ONE word/term for each of the following descriptions by choosing
a word/term from the list below. Write only the word/term next to the question
numbers (3.4.1 to 3.4.5) in the ANSWER BOOK, e.g. 3.4.6 road kerb.

D-clip; breathing apparatus; manhole; steel ruler; tape measure;
transparent pipe level; rope grab; slope; folding rule

3.4.1 Attached to the safety harness and lifeline (1)
3.4.2 Helps the worker to move down the lifeline at his/her own pace (1)
3.4.3 Must be worn when working in a deep manhole or confined spaces (1)
3.4.4 Can be used to transfer levels over long distances (1)
3.4.5 When the cover is removed, the area must be cordoned off and
warning signs must be posted (1)

3.5 FIGURE 3.5 below shows the layout to determine the route and fall of
a trench. Study the drawing and identify A, B and C.

fe) oO} A
B
c

FIGURE 3.5 (3)

3.6 ANSWER SHEET 3.6 shows the top view of a corner (quoin) of a wall with
a T-junction (1* course). Use ANSWER SHEET 3.6 to project and draw the
consecutive layer of this brick wall (2" course).

Use the assessment criteria on the ANSWER SHEET as a guide. (10)
[30]

Copyright reserved Please turn over

### Page 9

Civil Technology: Civil Services

QUESTION 4:

Downloaded from hlayiso.com

9 DBE/November 2019
NSC

HOT- AND COLD-WATER SUPPLY, TOOLS, EQUIPMENT AND
MATERIALS (SPECIFIC)

Start this question on a NEW page.

41

42
43
44

4.5

Copyright reserved

FIGURE 4.1 below shows a water-heating system.

4.1.1

4.1.2

4.13

FIGURE 4.1
Identify the water-heating system above.

What will be the result of continuous use of hot water from this
system?

Why must the glass panel of this system be cleaned regularly?

Briefly explain what an airlock in a hot-water system is.

State TWO causes of water hammer in pipes.

Identify the following symbols:

4.41

4.4.2

B

WW

Draw the following symbols:

4.5.1

4.5.2

Mixer (single manual control, single lever)

Vacuum relief valve combined with an air release valve

Please turn over

(1)

(1)
(1)
(3)
(2)

(1)

(1)

(2)
(2)

### Page 10

Downloaded from hlayiso.com

Civil Technology: Civil Services 10 DBE/November 2019
NSC
46 FIGURE 4.6 below shows a water trap that can be used under a washbasin.
=)
es
* ? 1
oi v
1]

FIGURE 4.6
4.6.1 Identify the type of water trap. (1)
4.6.2 Name the minimum diameter of the waste pipe that connects to the
water trap. (1)

47 A and B below show two different types of pipe fittings.

ee

A B
4.7.1 Identify the pipe fittings in A and B above. (2)

4.7.2 State where you would install EACH of the pipe fittings in A and B. (2)

4.8 Recommend ONE tool that can be used:
4.8.1 To thread and cut pipes (1)
4.8.2 For pressure testing of water systems (1)
4.8.3 To clean and unblock drains using high water pressure (1)
4.9 Describe TWO functions of a centrifugal pump. (2)

4.10 Explain why it is NOT recommended to connect copper pipes to galvanised
pipes. (2)

Copyright reserved Please turn over

### Page 11

Downloaded from hlayiso.com

Civil Technology: Civil Services 11 DBE/November 2019

4.11

4.12

4.13

4.14

NSC

FIGURE 4.11 below shows a tap.

FIGURE 4.11
4.11.1 Identify the tap in FIGURE 4.11 above.

4.11.2 Recommend TWO places where you could use this tap.

FIGURE 4.12 below shows a typical cold-water installation in a house. Study
the drawing and answer the questions that follow.

meter box

A B

water main

FIGURE 4.12

4.12.1 Local authorities use A to determine the water usage of
a household. What is this fitting called?

4.12.2 Identify B and explain what the function of this fitting is.
4.12.3 Name the type of tap that is used at C.

4.12.4 Predict if a chemical reaction will take place if a high-density
polyethylene pipe is connected to A.

4.12.5 | What is the electrochemical reaction called when zinc is selectively
leached from copper alloy?

Name TWO water-saving devices that can reduce water waste due to taps
that are left open when water supply is shut down and restored later.

Differentiate between a pressure-control valve and temperature and pressure
Safety valve in terms of its use.

Copyright reserved Please turn over

(1)
(2)

(1)
(2)
(1)

(1)

(1)

(2)

(2)
[40]

### Page 12

Downloaded from hlayiso.com

Civil Technology: Civil Services 12 DBE/November 2019

NSC

QUESTION 5: GRAPHICS AS MEANS OF COMMUNICATION, ROOF WORK AND

STORM WATER (SPECIFIC)

Start this question on a NEW page.

5.1

5.2

5.3

5.4

FIGURE 5.1 below shows different parts for the installation of a PVC gutter.
Study the drawing and answer the questions that follow.

_ 4 A

(ATTA [a ay

° 6

FIGURE 5.1

5.1.1 Sketch, in good proportion, a neat pictorial view of a square gutter
outlet in the ANSWER BOOK.

5.1.2 A indicates a bracket. To which part of the roof construction is this
bracket attached?

Give ONE word/term for each of the following descriptions of disposing
of storm water. Write only the word/term next to the question numbers
(5.2.1 to 5.2.4) in the ANSWER BOOK.

5.2.1 Channels constructed from precast concrete with the main function
of routing storm water to rivers or dams

5.2.2 An object that can be placed underneath a down pipe to channel
water from the roof away from the house

5.2.3 An object that is used on the edge of a road to channel storm water
towards a manhole

5.2.4 A method that can be used to waterproof roofs at junctions of walls

Name the authority that is responsible for all public storm-water pipes and
systems in a town.

ANSWER SHEET 5.4 shows the front view and top view of a square-based
truncated pyramid that is cut parallel to the horizontal plane.

Use the drawing and information on ANSWER SHEET 5.4 and draw the
development of the pyramid by using the radial-line method. Start the
development at A showing the 3 mm seam on both sides.

Show ALL construction lines. Do NOT redraw the given views. Project the
development from the given views.

Use the assessment criteria on the ANSWER SHEET as a guide.

Copyright reserved Please turn over

(4)

(1)

(1)

(1)

(1)
(1)

(1)

(20)
[30]

### Page 13

Downloaded from hlayiso.com

Civil Technology: Civil Services 13

NSC

DBE/November 2019

QUESTION 6: SEWERAGE, SANITARY FITTINGS AND JOINING (SPECIFIC)

Start this question on a NEW page.

6.1 Various options are given as possible answers to the following questions.
Choose the answer and write only the letter (A-D) next to the question
numbers (6.1.1 to 6.1.5) in the ANSWER BOOK, e.g. 6.1.6 C.

6.1.1

One can use ... to secure galvanised pipes to different surfaces.

A
B
Cc
D

pipe flanges

steel hangers
perforated straps

All the above-mentioned

When one needs to cut uPVC pipes to a specific length, one will
use a ...Saw.

A
B
Cc
D

hack-

crosscut

coping

All the above-mentioned

A property of solder:

A
B
Cc
D

Bluish in colour
Non-elastic modulus
Low strain rate
Ductile

Flux is used to ...

A
B
Cc
D

solder two pieces of pipes together.

assist with cleaning the material to be soldered.
enhance oxidation and stop the flow of solder.
form the oxide film to prevent corrosive action.

Pop rivets are divided into two groups, namely ... rivets.

900On0>Y

blind and open
hollow and solid
blind and solid
hollow and open

6.2 When soldering two tin plates together, a cover strip can be used to assist
with joining them. Draw, in good proportion, a simple lapped joint with a cover
strip in the ANSWER BOOK.

Copyright reserved

Please turn over

(1)

(1)

(1)

(1)

(1)

(3)

### Page 14

Civil Technology: Civil Services 14 DBE/November 2019
NSC
6.3 Copy the following table into the ANSWER BOOK and tabulate the symbols

6.3.2 6.3.4
= SS >

6.4 FIGURE 6.4 below shows a pipe fitting. Study the drawing and answer the

following questions.
A
FIGURE 6.4
6.4.1 Give the angle for the bend of the fitting.
6.4.2 Explain the purpose of A.

6.5 Describe TWO aspects that fittings in a drainage system should comply with.

6.6 Name TWO methods of ventilating a drainage system to prevent syphonage.

6.7 Describe the difference between septic tanks and vacuum tanks in terms of
the removal of the sewage.

6.8 ANSWER SHEET 6.8 shows the front elevation of a shower rose without the
pipes and taps. Use ANSWER SHEET 6.8 and draw a line diagram to show
the cold- and hot-water pipe layout for the shower.

Use the assessment criteria on the ANSWER SHEET as a guide.
Copyright reserved Please turn over

Downloaded from hlayiso.com

under the correct headings. Write only the question numbers (6.3.1 to 6.3 4)
under the correct heading in the ANSWER BOOK.

DRAINAGE ABOVE GROUND DRAINAGE BELOW GROUND

6.3.4 Ok 6.3.3 (ie)

(4)

(1)
(1)
(2)
(2)

(4)

(5)

### Page 15

Downloaded from hlayiso.com

Civil Technology: Civil Services 15 DBE/November 2019
NSC

6.9 ANSWER SHEET 6.9 shows a line diagram of a part of a house with a granny
flat and an incomplete sewerage layout. Use ANSWER SHEET 6.9 and
design and draw the complete sewerage layout.

Use the assessment criteria on the ANSWER SHEET as a guide. (13)
[40]

TOTAL: 200

Copyright reserved

### Page 16

Downloaded from hlayiso.com

Civil Technology: Civil Services

[ CENTRE NUMBER: [TT TT TT Ty

DBE/November 2019

[EXAMINATIONNUMBER: | | | | |

ANSWER SHEET 2
NO. QUESTION ANSWER MARKS
1 Identify the elevation in FIGURE A. 4
2 Identify the type of roof that is used on 1
the building in FIGURE A.
3 Identify number 1. 1
4 Identify number 4. 1
5 Identify number 5. 4
6 Identify number 7. 1
7 Identify number 8. 1
8 Identify number 12. 4
9 Identify number 13. 4
10 Identify number 15. 1
1 Identify the company that printed the 4
building plan.
Name a suitable material that can
12 be used for the manufacturing of 4
number 2.
Name the drawing symbol in the
13 column for the notes in FIGURE 2 that 1
must be installed in the kitchen.
Name the drawing symbol in the
14 column for the notes in FIGURE 2 that 4
indicates the type of bricks for the
building.
Name a material that should NOT be
15 used to manufacture the frame of 1
number 9 for coastal areas.

Copyright reserved

### Page 17

Downloaded from hlayiso.com

Civil Technology: Civil Services DBE/November 2019
NSC

Name a material that can be used to
16 manufacture the sanitary fitting
indicated by number 11.

17 Who checked the building plan?

How many types of windows are used

18 | in FIGURE B?

What does the abbreviation NGL at

19 number 6 stand for?

20 Give the reference code for this plan.

Which room will electrical symbol 16

21 serve?

22 Describe the purpose of number 3.

Explain what the curved lines
23 between the electrical installations in
FIGURE B indicate.

Explain why the light switch is
24 mounted on the outside of the
bathroom.

Identify in FIGURE 2 which elevation

25 does NOT have windows.

26 Identify the thickness of the internal
wall in FIGURE 2.

27 Differentiate between symbols 13 and
15 in terms of their purpose.

Justify why FIGURE B is a ground

28 floor plan.

Copyright reserved

### Page 18

Downloaded from hlayiso.com

Civil Technology: Civil Services

NSC

DBE/November 2019

Predict what will happen if number 10

29 | is NOT installed.
Redraw the staircase in FIGURE B in
30 =| the adjacent column and indicate the
direction of the flight with arrows.
Calculate the total length of the wall
31 on the eastern side of the building.

Show ALL calculations.

TOTAL:

Copyright reserved

### Page 19

Downloaded from hlayiso.com

paesal jysuAdoy

6102 Jequisaon/3gd

OF | sIWLOL
L Bulmeip Jo ssaujoao5
- L uojoun-| ye 401g IN
| 2 __| syoug % Jo apis yoke uo syoudq Ing
v SHOUG % XZ
K
z [}091J09 UMBIP JOUIOO ye SOG BSINOO yZ
wavil
S.ALVGIGNVO | WYV VIMSLIND LNSWSSASSV
8S1NOD ,.|
9°¢ LASHS YSMSNV
ry | | [| [| [| J J [ J] | [[ ‘a3eiinn NOLLVNINVYa |
[fl | [ | [ J] [ J TMSEINNN SYLNAD |
OSN

SBDIAIBS |IAIQ :ABQOUYIE | [IAI

### Page 20

Downloaded from hlayiso.com

Civil Technology: Civil Services DBE/November 2019
NSC
[ CENTRE NUMBER: LTT TT I [|
| EXAMINATION NUMBER: |__| [ [| | l | | | |
ANSWER SHEET 5.4
|
|
NO. | ASSESSMENT MARK | CANDIDATE'S
CRITERIA MARK
1 | Projection lines to
determine the apex
2 | Determine true length 4
3 | Top and bottom arc of 2
> Z pyramid |
A 4 | Development of base 5
of pyramid
5 | Development of top of 5
pyramid
6 | 3mm seams 2
TOTAL: | 20

Copyright reserved

### Page 21

Downloaded from hlayiso.com

Civil Technology: Civil Services DBE/November 2019

[ CENTRE NUMBER: LT] |] TT J J

[EXAMINATION NUMBER: | | | | | | | | |

ANSWER SHEET 6.8

ASSESSMENT CRITERIA MARK | CANDIDATE'S
MARK

Cold water inlet
Hot water inlet

Cold water tap (NO mixer taps)
Hot water tap (NO mixer taps)

Flow direction on mixed pipe
TOTAL:

aja)a)aja/o

Copyright reserved

### Page 22

Downloaded from hlayiso.com

Civil Technology: Civil Services DBE/November 2019
NSC

[CENTRENUMBER: | | | | | | | | 4

[EXAMINATIONNUMBER: [| | | | | | | [ [| | | | J |
ANSWER SHEET 6.9
I
Oe On
|
CT] 3° !
|
| GRANNY
| P | FLAT
|
| °
<
PART OF |
HOUSE l
I
(| |
I
|
I
l
l
|
A, !
FIGURE 6.9
ASSESSMENT CRITERIA MARK | CANDIDATE'S
MARK
Branch pipes 3
Vent pipe 1
Gulleys 2
| Junction of two main sewer pipes 1
Rodding eyes 2
Inspection eyes 3
Gradient 1
TOTAL: 13

Copyright reserved

## Related documents

- [Civil Technology Nov 2019 (Woodworking) Eng](https://www.hlayiso.com/library/civil-technology-nov-2019-woodworking-eng/b6e1822a-1416-45e5-97a8-13da0db177cd) — Civil Technology · QP · 2019 · Eng
- [Civil Technology Nov 2019 (Civil Services) Afr](https://www.hlayiso.com/library/civil-technology-nov-2019-civil-services-afr/560716c2-e3ed-412e-90e8-42d36162ee0d) — Civil Technology · QP · 2019 · Afr
- [Civil Technology Nov 2019 (Woodworking) Afr](https://www.hlayiso.com/library/civil-technology-nov-2019-woodworking-afr/1a837a2b-2575-4096-939a-dd10f12a0bf9) — Civil Technology · QP · 2019 · Afr
- [Civil Technology Nov 2019 (Civil Services) Memo Afr](https://www.hlayiso.com/library/civil-technology-nov-2019-civil-services-memo-afr/13c03cd5-cfa4-42cf-9a7c-5d7b0e1069f0) — Civil Technology · Memo · 2019 · Afr
- [Civil Technology Nov 2019 (Civil Services) Memo Eng](https://www.hlayiso.com/library/civil-technology-nov-2019-civil-services-memo-eng/53bd979c-a0bb-411f-960b-1f8755cd4874) — Civil Technology · Memo · 2019 · Eng
- [CIVIL TECH GR12 QP Eng SEPT2019 CIVIL SERVICES](https://www.hlayiso.com/library/civil-tech-gr12-qp-eng-sept2019-civil-services/24d2e0b8-d851-4c36-a274-0e7449793231) — Civil Technology · QP · 2019 · Eng

## More from Grade 12 Civil Technology

- [Civil Technology (Woodworking) (Afrikaans) June 2025 Possible Answers](https://www.hlayiso.com/library/civil-technology-woodworking-afrikaans-june-2025-possible-answers/c0a65d19-28ca-4ac3-8c61-d4627d2a3133) — Memo · 2025 · Afr
- [Civil Technology Nov 2025 (Construction) MG Eng](https://www.hlayiso.com/library/grade-12-civil-technology-2025-nsc-november-exam-memorandum/0e265899-dc44-4809-aabf-8f374f1af392) — Memo · 2025 · Eng
- [CIV TECH GR12 MEMO SEPT2024 Construction Afrikaans](https://www.hlayiso.com/library/civ-tech-gr12-memo-sept2024-construction-afrikaans/162bcc65-80ad-4384-b293-36da22468b06) — Memo · 2024 · Afr
- [CIV TECH GR12 MEMO SEPT2024 Civil Services English](https://www.hlayiso.com/library/civ-tech-gr12-memo-sept2024-civil-services-english/c1f2441d-22ba-4ae6-9e56-137cc442080c) — Memo · 2024 · Eng
- [CIV TECH GR12 MEMO SEPT2024 Construction English](https://www.hlayiso.com/library/civ-tech-gr12-memo-sept2024-construction-english/4d9c54ef-f526-46ad-82d4-8dd419eafb50) — Memo · 2024 · Eng
- [CIV TECH GR12 MEMO SEPT2024 Woodworking English](https://www.hlayiso.com/library/civ-tech-gr12-memo-sept2024-woodworking-english/6e7f4be5-4ffb-4654-b98b-b4cc4dfc4cc7) — Memo · 2024 · Eng

## Collection

- [Grade 12 past papers](https://www.hlayiso.com/grade-12/past-papers)

---

Hlayiso: free CAPS and IEB past papers, memos, notes and study guides for South African learners. When citing, link the page URL above, not a PDF or /api/ URL.