# Civil Technology Grade 12 NSC November 2020 Memo (English)

> Grade 12 Civil Technology memorandum from the NSC November Exam 2020 (English), 20 pages. Read online or download the free PDF.

- Page: https://www.hlayiso.com/library/civil-technology-nov-2020-construction-memo-eng/f06cef7f-235e-45f7-9f9b-f8e6a2b0c0ca
- Updated: 2026-09-27
- Subject: Civil Technology
- Grade: Grade 12
- Document type: Memorandum
- Year: 2020
- Exam period: NSC November Exam
- Curriculum: CAPS
- Pages: 20

Breadcrumbs: [Home](https://www.hlayiso.com/) › [Library](https://www.hlayiso.com/library) › [Grade 12](https://www.hlayiso.com/library/grade-12) › [Civil Technology](https://www.hlayiso.com/library/grade-12/civil-technology) › [Civil Technology Grade 12 NSC November 2020 Memo (English)](https://www.hlayiso.com/library/civil-technology-nov-2020-construction-memo-eng/f06cef7f-235e-45f7-9f9b-f8e6a2b0c0ca)

## About this document

Civil Technology · Grade 12 · NSC November Exam · 2020. Memorandum, 20 pages. Read online or download the PDF.

Read it free online on the page above; download the PDF from there.

## Document text

Text extracted from the PDF. Layout, diagrams and tables may not survive extraction.

### Page 1

Downloaded from hlayiso.com

                                     GRAAD 12

                          SENIOR CERTIFICATE/
                      NATIONAL SENIOR CERTIFICATE

                                     GRADE 12

                      CIVIL TECHNOLOGY: CONSTRUCTION

                                  NOVEMBER 2020

                               MARKING GUIDELINES

MARKS: 200

                      These marking guidelines consist of 20 pages.

Copyright reserved                                                    Please turn over

### Page 2

Downloaded from hlayiso.com
Civil Technology: Construction                    2                         DBE/November 2020
                                      SC/NSC – Marking Guidelines

INSTRUCTIONS FOR THE MARKERS

   1.     Markers should:
           Familiarise themselves with the question and answer before evaluating the
             responses of candidates.
           Always interpret the responses of the candidates within the context of the
             question.
           Consider any relevant and acceptable answer during pre-marking but
             should strictly adhere to the answers after finalisation of the marking
             guideline.
           There are two approaches to answering questions, these are (1) to describe
             and (2) to explain.
             If a candidate is required to explain e.g., a process in 4 steps, only the first 4
             responses should be considered.
             If, however a candidate is required to e.g., explain or describe how to
             transfer heights from one point to another using a transparent pipe level we
             need to consider that candidates may write a long description not
             necessarily well organised as an intellectual response may do. In this case
             the marker needs to evaluate the complete statement to judge if the
             candidate explained the required outcome satisfactorily and allocate marks
             on merit. The marker should apply his/her professional judgement with
             these types of questions.
           Mark what the candidate wrote and do not award marks for answers that the
             marker thinks the candidate meant with what was written.
           Indicate the tick or cross right at the position where the mark needs to be
             awarded or where the candidate made the error.
           Accept the letter corresponding with the correct answer as well as the
             answer written in full in multiple-choice questions.
           Accept incorrect spelling in one-word answers unless the spelling changes
             the meaning of the answer.

   2.     For calculations:
           A mark is only awarded if the correct unit is written next to the answer.
           If TWO marks are awarded ONE mark is awarded for the answer and ONE
              mark for the correct unit.
           Where the candidate made a principle error e.g. added instead of
              multiplying, no marks will be awarded for the steps. If the answer is correct
              according to what the candidate did, the mark for the answer can be
              awarded for the application of skills.
           Where an incorrect answer could be carried over to the next step, the first
              answer will be deemed incorrect. However, should the incorrect answer be
              carried over correctly, the marker has to recalculate the values, using the
              incorrect answer from the first calculation. If correctly used, the candidate
              should receive the full marks for subsequent calculations.
           Markers should consider when and where a candidate has rounded off in a
              calculation, as well as the subsequent effect it has on the final answer
              obtained. The calculation should therefore be awarded marks on merit.
           Alternative methods of calculations must be considered, provided that the
              correct answer is obtained.

Copyright reserved                                                              Please turn over

### Page 3

Downloaded from hlayiso.com
Civil Technology: Construction                 3                        DBE/November 2020
                                 SC/NSC – Marking Guidelines

   3.     When marking drawings:
           The member for which the mark should be awarded should be drawn
             correctly in the correct position to receive a mark.
           A member incorrectly drawn but wrongfully repeated in another position will
             be awarded the mark for the repeated incorrect member provided that the
             marking guideline provide for TWO or more marks for that member (positive
             marking).
           Marks can only be awarded for a label if the label is correctly indicating the
             correct member.
           Scale drawings should always be marked using an appropriate mask.

          When a candidate drew the wrong drawing e.g.:
           A horizontal section instead of a vertical section, no marks will be allocated
             to the drawing as the candidate did not respond to the expected outcome.
           An orthographic view instead of sectional view, no marks will be allocated to
             the drawing as the candidate did not respond to the expected outcome.
           An orthographic view instead of an isometric view, no marks will be
             allocated to the drawing as the candidate did not respond to the expected
             outcome.
           If the incorrect drawing was drawn, the candidate can be awarded for only
             what was asked but mark/s for the correctness of the drawing will not be
             awarded e.g., if a King Post roof truss was asked in the question, and
             candidate drew SA-Howe Truss

Copyright reserved                                                          Please turn over

### Page 4

Downloaded from hlayiso.com
Civil Technology: Construction                 4                         DBE/November 2020
                                 SC/NSC – Marking Guidelines

QUESTION 1: OHSA, SAFETY, MATERIALS, TOOLS, EQUIPMENT AND JOINING
            (GENERIC)

1.1       1.1.1        E                                                                      (1)

          1.1.2        C                                                                      (1)

          1.1.3        D                                                                      (1)

          1.1.4        H                                                                      (1)

          1.1.5        B                                                                      (1)

          1.1.6        F                                                                      (1)

          1.1.7        A/I                                                                    (1)

          1.1.8        G/K                                                                    (1)

1.2       Galvanising:
           Adds strength to the original, uncoated metal. 
           Make it last longer/Preservation/Durable.
           Decorative/Enhance appearance.
           Makes metal thicker than the uncoated metal.
           Nails and screws prevent staining.
           Prevent the material from rusting/corroding.
          ANY ONE OF THE ABOVE                                                                 (1)

1.3        Material safety data sheet. 
           Sufficient information regarding the protection of health and safety.
          ANY ONE OF THE ABOVE                                                                 (1)

1.4           Materials can be moved manually/by means of a wheelbarrow/trolley. 
              Materials can be moved by means of machinery/builders hoist/truck/
               crane/tractor/conveyor/fork lift.                                              (2)

1.5       Water-based paint:
           Dry quickly. 
           Allows marks/smudges to be easily cleaned with water. 
           Give an elastic flexible finish.
           Durable
           Gives a decorative finish.
           Enhances the appearance.
           Resistant to cracking.
           Cost effective/Cheaper
           Easy to apply.
          ANY TWO OF THE ABOVE                                                                 (2)

Copyright reserved                                                          Please turn over

### Page 5

Downloaded from hlayiso.com
Civil Technology: Construction                 5                          DBE/November 2020
                                 SC/NSC – Marking Guidelines

1.6       1.6.1        Multi detector                                                          (1)

          1.6.2        Care of the multi detector:
                        Place the multi-detector in its holder directly after use. 
                        Do not bump the instrument against objects or drop it. 
                        Protect the multi-detector against moisture and direct sunlight.
                        If the measuring tool is not used for a long period, remove the
                           battery.
                        Wipe away dirt or spots with a dry, soft cloth.
                        Switch off the device before storing.
                       ANY TWO OF THE ABOVE                                                     (2)

1.7           Drill a hole in the wall. 
              Insert the plastic plug into the hole. 
              Align the hole in the bracket with the hole in the wall and fasten the
               screw.                                                                          (3)
                                                                                                [20]

Copyright reserved                                                           Please turn over

### Page 6

Downloaded from hlayiso.com
    Civil Technology: Construction               6                             DBE/November 2020
                                      SC/NSC – Marking Guidelines

    QUESTION 2: GRAPHICS AS MEANS OF COMMUNICATION (GENERIC)

    NO.                  QUESTION                                   ANSWER                      MARKS
            Identify the elevation in FIGURE
1                                                South Elevation                                    1
            A.

            Describe the type of house that is   Double-storey house/Building/Multi-storey
2                                                                                                    1
            indicated in FIGURE A.               building 

                                                 Ridge Capping/Ridge tile/Ridge
3           Identify number 1.                                                                       1
                                                 plate/Ridge 

4           Identify number 3.                   Fascia board                                       1

5           Identify number 4.                   Overhang/Eave/Dimension line                       1

            Identify the fastener indicated by
6                                                Holder bat/Clamp/Clip                              1
            number 5.
                                                 Window/Window frame/Casement/
7           Identify number 6.                                                                       1
                                                 Casement frame 
                                                 Shoe/Down pipe outlet/
8           Identify number 7.                                                                       1
                                                 Spout 
9           Identify number 8.                   Natural ground level/NGL                           1
            What does DPM stands for, as
10                                               Damp proof membrane                                1
            indicated in the notes?
11          Identify number 10.                  Built-in cupboard/BIC                              1
            Recommend a suitable material        Fibre cement/Galvanised sheeting/Sheet
            that can be used for the             metal/Timber/Wood/Plastic/Fibre
12                                               glass/Aluminium sheeting                           1
            manufacturing of number 2 in
            FIGURE A.
            Name the TWO elevations on           West elevation 
13                                                                                                   2
            which number 2 is installed.         East elevation 
                                                 The gutter is fixed against it. 
            Describe the purpose of number
14                                               It finishes off the roof.                           1
            3.
                                                 Protect roofs/rafters from rainwater.
            Deduce ONE feature that has          Step missing at the door 
15          been omitted from the elevation in                                                       1
            FIGURE A.                            Sill missing at the window

            Recommend any TWO sanitary           Hand basin/Wash hand basin/Hand
            fitments carrying waste water        basin/Basin/WB/WHB/HB 
16          other than a bath that can be                                                            2
                                                 Shower/SH 
            installed in the room indicated by
            number 11.

    Copyright reserved                                                            Please turn over

### Page 7

Downloaded from hlayiso.com
 Civil Technology: Construction               7                              DBE/November 2020
                                   SC/NSC – Marking Guidelines

         What sanitary fixture carrying soil   Water closet/WC 
17       water can be installed in the room                                                        1
         indicated by number 12?               Bidet/BT

                                               The two side windows are opening to the
         Describe the error that appears at    wrong sides/No window sill/The window
18       number 6 in the elevation in                                                              1
                                               drawn in FIGURE A is not the same as that
         FIGURE A.                             in the window schedule/Window opening.

         State the reference code for this
19                                             QP 4 - 2020                                        1
         plan.

20       Which room will number 13 serve? Bedroom 2                                               1
                                               Electrical wiring/cable/connection
21       What does the line between            Wiring/Wiring from light switch to
                                                                                                   1
         numbers 13 and 14 represent?          light/Shows which switch operates which
                                               electrical fitting
                                               15: Single tube fluorescent light/
                                               17: Double/ tube fluorescent light.
         Differentiate between number 15       15: Will use less electricity/Watt than 17/
22       in FIGURE B and number 17 in          15: Will provide less light than 17/                2
         the notes.                            15: Running cost will be cheaper than 17.
                                               15: Has one tube/1 x 40 Watt. 
                                               17: Has two tubes/2 x 40 Watt. 
         Explain the installation of brick
                                             Brick force must be installed between
         force from the top of the window to
23                                           every course above the window up to wall              1
         the wall plate, as indicated by the
                                             plate. 
         architect.
                                               Face bricks 
                                               Plaster and paint/Plaster/Paint/Plaster
         Recommend a possible finish for
24                                             finish (Smooth finish/Splatter finish/Wavy          1
         the outside walls of the house.
                                               finish/Bagging finish)
                                               Cladding/Tiling

         Deduce from FIGURE 2 which
25       elevation does NOT have               East elevation                                     1
         windows.

         Deduce the thickness of the
26                                             220 mm                                             1
         external wall from FIGURE 2.
         Name a material that can be used
                                               Wood/Timber/Stainless steel/Mild
27       to close the open sides of number                                                         1
                                               steel/Steel/Aluminium/Glass/Perspex 
         16.
         Name the town in which the
28                                             Cradock                                            1
         proposed dwelling will be build.

 Copyright reserved                                                             Please turn over

### Page 8

Downloaded from hlayiso.com
 Civil Technology: Construction               8                          DBE/November 2020
                                   SC/NSC – Marking Guidelines

         Calculate the area of the              ℓxb             ℓxb
         bathroom. Show ALL calculations.
29       Give your answer in m².              = 2 m x 2 m OR 2 000 mm x 2 000 mm              3
                                              = 4 m²         = 4 m²

30       Calculate the total length of the    220 + 3 000  + 110
         wall on the eastern side of the
         building. Show ALL calculations.     + 1 400 + 110 + 2 000 +220
         The length must be indicated in      = 7 060 mm
         metres.
                                              = 7,06 m 
                                                                                                6
                                              OR

                                              220 + 3 000 + 110 + 3 510 + 220
                                              = 7 060 mm
                                              = 7,06 m
                                                                                TOTAL:          40

 Copyright reserved                                                          Please turn over

### Page 9

Downloaded from hlayiso.com
Civil Technology: Construction               9                         DBE/November 2020
                                  SC/NSC – Marking Guidelines

QUESTION 3: ROOFS, STAIRCASES AND JOINING (SPECIFIC)

3.1.1     760 mm                                                                           (1)

3.1.2     Sisalation/Fire-proof material                                                   (1)

3.1.3     300 mm                                                                           (1)

3.1.4     Fibre cement tiles                                                               (1)

3.1.5     76 x 50 mm/38 x 38 mm                                                            (1)

3.2       3.2.1        750 mm                                                              (1)

          3.2.2        1,5 m/2 m/2,1 m                                                     (1)

          3.2.3          All stairs must have handrails/Stairs must be secured. 
                         The regulations as stipulated by local authorities or SANS
                          should be met when stairs are built or cast.
                       ANY TWO OF THE ABOVE                                                 (1)

3.3       Rise: vertical distance between two consecutive threads. 
          Riser: vertical member between two consecutive threads.                          (2)

3.4       Pitch board                                                                      (1)

3.5       Balustrades:
           hold up the handrail. 
           fills the space between the handrail and string on the open side of a
              staircase. 
           prevent people from falling off the staircase.
          ANY TWO OF THE ABOVE                                                              (2)

Copyright reserved                                                       Please turn over

### Page 10

Downloaded from hlayiso.com
Civil Technology: Construction               10                     DBE/November 2020
                                   SC/NSC – Marking Guidelines

3.6

                                                                RAFTER
                                                                 CLOUT NAILS
                                    
                                  
                                                               TIE-BEAM

                                                                 WALL PLATE
                                          
                                                                 HOOP-IRON STRAP
                                   
                                                                 WALL
                                          

                                 CORRECTNESS OF DRAWING 

           ASSESSMENT CRITERIA           MARK
           Brick wall                      1
           Wall plate                      1
           Tie beam                        1
           Rafter                          1
           Hoop-iron strap                 3
           Clout nails                     1
           Correctness of drawing          1
                                  TOTAL:   9
                                                                                           (9)

Copyright reserved                                                      Please turn over

### Page 11

Downloaded from hlayiso.com
Civil Technology: Construction                 11                    DBE/November 2020
                                     SC/NSC – Marking Guidelines

3.7
                                                                   KING POST 114 X 38 MM

                                         

                                                                   STRUTS 114 X 38 MM
                                                   
                                                                                 
                                                                  TIE-BEAM 114 X 38 MM

                JUNCTION AT THE TIE-BEAM, KING POST AND STRUTS
                SCALE 1:10

                APPLICATION OF SCALE 
                CORRECTNESS OF DRAWING 

              (USE A MASK TO MARK THIS QUESTION)

           ASSESSMENT CRITERIA            MARK
           Tie beam                         1
           King post                        1
           Struts                           2
           Any ONE label with dimensions    2
           Application of scale             1
           Correctness of drawing           1
                                   TOTAL:   8
                                                                                          (8)
                                                                                          [30]

Copyright reserved                                                     Please turn over

### Page 12

Downloaded from hlayiso.com
Civil Technology: Construction                12                            DBE/November 2020
                                    SC/NSC – Marking Guidelines

QUESTION 4:          EXCAVATIONS, FORMWORK,                  TOOLS,     EQUIPMENT    AND
                     MATERIALS (SPECIFIC)

4.1       Removal of soil/earth.                                                                (1)

4.2       The sides of the excavations can collapse/crack.                                      (1)

4.3       Tension cracks will appear/collapse.                                                  (1)

4.4       Start at the bottom of the excavation.                                                (1)

4.5         A fence/suitable barrier/warning signs must be provided 
            The working edge of each ditch deeper than 2 m must be inspected by a
             competent person before the start of each shift.
          ANY ONE OF THE ABOVE                                                                   (1)

4.6       4.6.1        Location of the following services:
                        Electric cables 
                        Water pipes 
                        Gas lines
                        Communication line
                        Sanitation services
                       ANY TWO OF THE ABOVE                                                      (2)

          4.6.2        Trenches should be inspected:
                        before workers working in it. 
                        at the start of each shift.
                        following rainfall or other water intrusion.
                       ANY ONE OF THE ABOVE                                                      (1)

4.7       4.7.1        Safety precautions to be considered:
                        Operate with care. 
                        Wear appropriate personal equipment e.g., gloves and
                           boots.
                        Avoid making any adjustments while the machine is vibrating.
                        Never use a faulty machine.
                        Never lay the machine on its side.
                        Do not place your hands and feet near the moving parts.
                        Switch off the machine when it is left unattended.
                        Use both hands to operate the machine.
                        Ensure a firm and well-balanced stance.
                        Check the controls for proper response before use.
                        Check the condition of the machine at the start and end of
                           every shift.
                        Report any defects.
                       ANY TWO OF THE ABOVE                                                      (2)

Copyright reserved                                                            Please turn over

### Page 13

Downloaded from hlayiso.com
Civil Technology: Construction                 13                            DBE/November 2020
                                     SC/NSC – Marking Guidelines

          4.7.2        Stored in a safe, dry place to:
                        prevent corrosion/rust. 
                        protect the machine
                        prevent machine from being damaged by moisture.
                       ANY ONE OF THE ABOVE                                                       (1)

4.8       4.8.1        Cube test                                                                 (1)

          4.8.2        A - Tamping rod/Steel rod 
                       B – Mould/Cube                                                            (2)

          4.8.3         7 days 
                        14 days 
                        28 days
                       ANY TWO OF THE ABOVE                                                       (2)

          4.8.4        Compressive strength                                                      (1)

4.9       Properties of ductile cast iron:
           Excellent ability to withstand blows and knocks. 
           Very good fatigue strength/limit. 
           Elasticity makes it ideal for casting.
          ANY TWO OF THE ABOVE                                                                    (2)

4.10      Material to fix cladding to a wall:
           Silicon 
           Cement based mixture
           Colour matching screws/Face fixings
           Tile adhesive
           Proprietary fixings
          ANY ONE OF THE ABOVE                                                                    (1)

4.11      Poling boards are used to:
           keep the soil from entering the excavation. 
           prevent soil from falling into the trench/collapse.
          ANY ONE OF THE ABOVE                                                                    (1)

4.12          To keep the poling boards in place. 
              To keep the struts in place.                                                      (2)

4.13      One/Two                                                                                (1)

4.14          Poling boards for firm soil are spaced further apart. 
              Polling boards for loose soil are spaced closer together.                         (2)

Copyright reserved                                                             Please turn over

### Page 14

Downloaded from hlayiso.com
    Civil Technology: Construction             14                             DBE/November 2020
                                     SC/NSC – Marking Guidelines

    4.15

                                                                   WALL 220 mm

                                                                    LANDING
                                     WALL
                                     STRING
                                                       
                  SHUTTERBOARD

                    BEVELLED
                    RISER
                 CLEAT                                              PROP
                                                     
                                               
          BEARER                                                                    
          JOIST                                              
CROSS                                            
                    
BEARERS
                                                                                     
                                       FOLDING WEDGES
                                       CLEAT
                                                    SOLE PLATE
               CORRECTNESS OF DRAWING 
               ASSESSMENT CRITERIA                          MARK
               Cross bearers                                  1
               Bearer/Joist                                   1
               Props                                          3
               Folding wedges                                 2
               Cleats to support props                        1
               Wall string                                    1
               Bevelled riser                                 2
               Cleats                                         2
               Correctness of drawing                         1
                                                TOTAL:       14                                     (14)
                                                                                                    [40]

    Copyright reserved                                                           Please turn over

### Page 15

Downloaded from hlayiso.com
Civil Technology: Construction                      15                       DBE/November 2020
                                          SC/NSC – Marking Guidelines

QUESTION 5: PLASTER AND SCREED, BRICKWORK AND GRAPHICS AS
            MEANS OF COMMUNICATION (SPECIFIC)

5.1       5.1.1        Splatter finish/Splatter dash finish/Roughcast finish                       (1)

          5.1.2        Bagging finish                                                              (1)

5.2       Purpose of screed:
           To provide a smooth/level/neat/flat surface. 
           To increase the structural depth and strength of the base slab. 
           To prepare floor for floor covering.                                                    (2)

5.3       Preparing a smooth concrete floor to receive the screed:
           Chip the surface with a sharp tool to remove the surface skin and expose
              the hard, clean concrete. 
           Wet the surface.
          ANY ONE OF THE ABOVE                                                                      (1)

5.4       Builders' lime                                                                           (1)

5.5       Rough arch - the mortar joint will be wedge shaped/triangular shaped. 
          Gauged arch - the mortar joint will be uniform/rectangular shape.                        (2)

5.6

                                             
                                  
                                           
                                                    
                                                  

                                  FIRST COURSE

                                      
                                                    
                                            
                                  
                                                

                                 SECOND COURSE

            ASSESSMENT CRITERIA                                  MARK
            Stretcher bond - first course                          5
            Stretcher bond - second course                         5
                                                        TOTAL:    10                                (10)

Copyright reserved                                                               Please turn over

### Page 16

Downloaded from hlayiso.com
Civil Technology: Construction               16                      DBE/November 2020
                                   SC/NSC – Marking Guidelines

5.7

                           
                                                 PLASTER 
                                                EXTERIOR REVEAL
                                       
                                              DOOR FRAME 110 mm X 70 mm
                                   
                                                 DPC ATTACHED TO THE DOOR FRAME
                                           
                                                QUARTER ROUND
                          

  CORRECTNESS OF                              220 mm BRICK WALL
  DRAWING
   (USE A MASK TO MARK THIS QUESTION)
 ASSESSMENT CRITERIA               MARK
 Wall 220 mm                         2
 Plaster 12 mm                       2
 Exterior reveal                     1
 Door frame 110 mm x 70 mm           2
 DPC attached to door frame          1
 Quarter rounds                      2
 Any ONE label                       1
 Correctness of drawing              1
                            TOTAL:  12                                                    (12)
                                                                                          [30]

Copyright reserved                                                     Please turn over

### Page 17

Downloaded from hlayiso.com
Civil Technology: Construction             17                            DBE/November 2020
                                 SC/NSC – Marking Guidelines

QUESTION 6:          REINFORCEMENT IN CONCRETE, FOUNDATIONS, CONCRETE
                     FLOORS AND QUANTITIES (SPECIFIC)

6.1       6.1.1        A                                                                     (1)

          6.1.2        C                                                                     (1)

          6.1.3        B                                                                     (1)

          6.1.4        D                                                                     (1)

          6.1.5        D                                                                     (1)

6.2       Reasons for the installation of pile foundations:
           Poor soil conditions 
           Soft soil 
           Unstable soil
           Loose soil
           Non-cohesive soil
           Where there is soil movement.
           Constantly wet areas.
           Ground conditions are not stable enough to support ordinary, shallow
             foundations.
           Foundation piles distribute the load to more stable ground and can be
             used as underground or underwater supports.
           Piles provide stability when a raft or floating foundation is used.
           When structures are subjected to horizontal forces, pile foundations resist
             bending stress while still lending vertical support, e.g., multi storey
             buildings.
           Where soils are prone to swelling and shrinking according to the moisture
             content, e.g., for clay soil, shallow foundations cannot be used.
           When the superstructure is exposed to uplifting forces, e.g., offshore
             platforms.
           Where soil erosion is possible, piles should be used to carry the load of
             the superstructure, e.g., for bridges and piers.
          ANY TWO OF THE ABOVE                                                                (2)

Copyright reserved                                                         Please turn over

### Page 18

Downloaded from hlayiso.com
Civil Technology: Construction                 18                          DBE/November 2020
                                     SC/NSC – Marking Guidelines

6.3
                             
                                         STEEL CABLE
                                 

                                         STEEL PIPE CASING 

                                         DROP HAMMER
                             

                             CORRECTNESS OF DRAWING 

           ASSESSMENT CRITERIA                              MARK
           Steel cable                                        1
           Steel pipe-casing                                  1
           Drop hammer                                        1
           Any ONE label                                      1
           Correctness of drawing                             1
                                                TOTAL:        5                                    (5)

          6.4.1        Consequences:
                        Block will not be supported/fall through/collapse. 
                        No bonding between the rib and block. 
                        Installation will not be successful.
                        The block will be heavy as there is no holes in it.
                        Service pipes may not be able to be laid.
                       ANY TWO OF THE ABOVE                                                        (2)

          6.4.2

                                                             
                                                             

                                                                    
                                                                       
                                                                                
                                          
                                                                                

                        ASSESSMENT CRITERIA                         MARK
                        Hollow block                                  2
                        Rebates in block                              2
                        Reinforcement in ribs                         2
                                                           TOTAL:     6                            (6)

Copyright reserved                                                              Please turn over

### Page 19

Downloaded from hlayiso.com
Civil Technology: Construction              19                        DBE/November 2020
                                  SC/NSC – Marking Guidelines

          6.4.3        220 mm                                                             (1)

6.5
                                  

                                                        8 MAIN BARS
                                                
                                                    COLUMN

                                                      STIRRUP
                                                   COVER DEPTH
                                      

                                          CORRECTNESS OF DRAWING 

           ASSESSMENT CRITERIA                           MARK
           Column                                          2
           Stirrup                                         1
           Main bars                                       2
           Cover depth indicated                           1
           Correctness of drawing                          1
                                             TOTAL:        7
                                                                                           (7)

Copyright reserved                                                      Please turn over

### Page 20

Downloaded from hlayiso.com
Civil Technology: Construction                20                           DBE/November 2020
                                    SC/NSC – Marking Guidelines

6.6         A          B            C                             D
                                             Internal measurement of floor:
                                             4 500 – 440 = 4 060 (4,06 m) 
                                             6 500 – 440 = 6 060 (6,06 m) 

                                             Area of floor:
           1/        4,06 
                     6,06       24,6 m2 
                                                                                               (5)
                                             Volume of concrete for the
                                             floor:
                24,6
                0,075           1,85 m3 
                OR
                4,06
                6,06
                                                                                               (2)
                0,075             1,85 m3

                                             Number of tiles to cover the floor:
           1/        0,35                   One tile is 350 mm x 350 mm
                     0,35       0,12 m2    Area of one tile = 0,12 m²
                                             24,6 m² 
                                             0,12 m²
                                             = 205 tiles                                      (5)
                                                                                               [40]

                                                                                   TOTAL:      200

Copyright reserved

## Related documents

- [Civil Technology Nov 2020 (Civil Services) Memo Afr](https://www.hlayiso.com/library/civil-technology-nov-2020-civil-services-memo-afr/8cffc125-69c0-44e9-b0eb-88ae7e930363) — Civil Technology · Memo · 2020 · Afr
- [Civil Technology Nov 2020 (Civil Services) Afr](https://www.hlayiso.com/library/civil-technology-nov-2020-civil-services-afr/b796705a-6588-4c35-a6ed-9d9659bce995) — Civil Technology · QP · 2020 · Afr
- [Civil Technology Nov 2020 (Woodworking) Eng](https://www.hlayiso.com/library/civil-technology-nov-2020-woodworking-eng/f45b898c-a9ab-4069-ae4b-2b730f88cf1b) — Civil Technology · QP · 2020 · Eng
- [Civil Technology Nov 2020 (Construction) Eng](https://www.hlayiso.com/library/civil-technology-nov-2020-construction-eng/6e24138d-3f1b-42f9-8076-7ae0b7db457a) — Civil Technology · QP · 2020 · Eng
- [Civil Technology Nov 2020 (Civil Services) Eng](https://www.hlayiso.com/library/civil-technology-nov-2020-civil-services-eng/8ecb8551-97e5-4a57-8187-0130f8d158da) — Civil Technology · QP · 2020 · Eng
- [Civil Technology Nov 2020 (Construction) Afr](https://www.hlayiso.com/library/civil-technology-nov-2020-construction-afr/7e3d3218-d564-4a19-b535-b7ed8a417256) — Civil Technology · QP · 2020 · Afr

## More from Grade 12 Civil Technology

- [CVLT Woodworking Eng watermark](https://www.hlayiso.com/library/cvlt-woodworking-eng-watermark/8e178c6e-fa7b-40f4-8a2c-936e0bee3b38) — QP · 2025 · Eng
- [Civil Technology (Woodwork) (English and Afrikaans) June 2025 Question Paper](https://www.hlayiso.com/library/civil-technology-woodwork-english-and-afrikaans-june-2025-question-paper/c8edd459-5237-48e0-8588-69d7ecd7f8e5) — QP · 2025 · Afr
- [Civil Technology May-June 2025 (Construction) Afr](https://www.hlayiso.com/library/civil-technology-may-june-2025-construction-afr/591d6ffd-20b1-4748-a1ba-b055be0a14c3) — QP · 2025 · Afr
- [Civil Technology Nov 2025 (Woodworking) Afr](https://www.hlayiso.com/library/grade-12-civil-technology-2025-nsc-november-exam-question-paper/05a95faf-5891-4d88-9e5e-7d13c1d21648) — QP · 2025 · Afr
- [CIV TECH GR12 QP SEPT2024 Woodworking Afrikaans](https://www.hlayiso.com/library/civ-tech-gr12-qp-sept2024-woodworking-afrikaans/1c6d5c64-83b5-456b-abcf-2abc23f1f1fe) — QP · 2024 · Afr
- [CIV TECH GR12 QP SEPT2024 Construction English](https://www.hlayiso.com/library/civ-tech-gr12-qp-sept2024-construction-english/12643629-87af-4230-a48a-002beb7f6cd7) — QP · 2024 · Eng

## Collection

- [Grade 12 past papers](https://www.hlayiso.com/grade-12/past-papers)

---

Hlayiso: free CAPS and IEB past papers, memos, notes and study guides for South African learners. When citing, link the page URL above, not a PDF or /api/ URL.