# Civil Technology Grade 12 NSC November 2022 Memo (English)

> Grade 12 Civil Technology memorandum from the NSC November Exam 2022 (English), 21 pages. Read online or download the free PDF.

- Page: https://www.hlayiso.com/library/civil-technology-nov-2022-woodworking-mg-eng/cd7a6f11-8877-4a3e-ade2-94e34657eb4c
- Updated: 2026-10-29
- Subject: Civil Technology
- Grade: Grade 12
- Document type: Memorandum
- Year: 2022
- Exam period: NSC November Exam
- Curriculum: CAPS
- Pages: 21

Breadcrumbs: [Home](https://www.hlayiso.com/) › [Library](https://www.hlayiso.com/library) › [Grade 12](https://www.hlayiso.com/library/grade-12) › [Civil Technology](https://www.hlayiso.com/library/grade-12/civil-technology) › [Civil Technology Grade 12 NSC November 2022 Memo (English)](https://www.hlayiso.com/library/civil-technology-nov-2022-woodworking-mg-eng/cd7a6f11-8877-4a3e-ade2-94e34657eb4c)

## About this document

Civil Technology · Grade 12 · NSC November Exam · 2022. Memorandum. Read online or download the PDF.

Read it free online on the page above; download the PDF from there.

## Document text

Text extracted from the PDF. Layout, diagrams and tables may not survive extraction.

### Page 1

Downloaded from hlayiso.com

                                     GRAAD 12

                                    NATIONAL
                               SENIOR CERTIFICATE

                                       GRADE 12

                       CIVIL TECHNOLOGY: WOODWORKING

                                   NOVEMBER 2022

                                MARKING GUIDELINES

MARKS: 200

                      These marking guidelines consist of 21 pages.

Copyright reserved                                                    Please turn over

### Page 2

Downloaded from hlayiso.com
Civil Technology: Woodworking                 2                           DBE/November 2022
                                   NSC – Marking Guidelines

INSTRUCTIONS FOR THE MARKERS

1.       Markers should:
          Familiarise themselves with the question and answer before
            evaluating responses from candidates.
            Always interpret the responses of the candidates within the context of
             the question.
            Consider any relevant and acceptable answer during pre-marking but
             should strictly adhere to the answers after finalisation of the marking
             guideline.
            There are TWO approaches to answering questions; these are (1) to
             explain and (2) to describe.
             1. If a candidate is required to explain a process in a specific number
                of steps, only the first required number of responses should be
                considered.
             2. However, if for example a candidate is required to explain or
                describe a process, we need to consider that candidates may write
                a long description, not necessarily well organised. In this case the
                marker needs to evaluate the complete statement to judge if the
                candidate explained the required outcome satisfactorily and
                allocate marks on merit.

            Mark what the candidate wrote and do not interpret or predict
             responses.

            Indicate the tick or cross right at the position where the mark needs to
             be awarded or where the candidate made the error.

            Accept the letter corresponding with the correct answer as well as the
             answer written in full in multiple-choice or similar questions.

            Accept incorrect spelling in answers unless the spelling changes the
             meaning of the answer.

            If a learner writes two or more answers separated by a slash (/) mark
             only the first response, unless the additional answer/s are different
             names for the same item e.g., Yale lock/Night latch. In this case, the
             answer for the response should be awarded and the slash (/) should
             NOT be considered as an additional answer.

2.       For calculations:
          A mark is only awarded if the correct unit is written next to the
             answer. If the question states that the answer must be in a specific
             unit, a mark will ONLY be awarded if the answer has the correct unit
             as indicated in the question.
            Marks will only be allocated for the correct values if the candidates
             add are instead of multiply. NO marks will be awarded for the
             calculations and the answer.

Copyright reserved                                                            Please turn over

### Page 3

Downloaded from hlayiso.com
Civil Technology: Woodworking                3                           DBE/November 2022
                                  NSC – Marking Guidelines

            Where an incorrect answer is correctly carried over, the marker must
             recalculate the values, using the incorrect answer from the first
             calculation. If correctly used, the candidate should receive the full
             marks for subsequent calculations.

            Alternative methods of calculations must be considered, provided that
             the correct answer is obtained.

            For the calculation of quantities marks will be awarded for the correct
             use of the dimension paper.

3.       When marking drawings:

            The member for which the mark should be awarded must be drawn
             correctly in the correct position to receive a mark.

            A member incorrectly drawn but wrongfully repeated in another
             position will be awarded the mark for the repeated incorrect member
             provided that the marking guideline provide for TWO or more marks
             for that member (positive marking).

            Marks can only be awarded for a label if the label is correctly
             indicating the correct member that was drawn. Do not consider labels
             for members that were provided with labels on the answer sheet.

            Scale drawings should always be marked using an appropriate mask.

            If the incorrect/wrong drawing was drawn, the candidate can be
             awarded for only what was provided for on the marking guideline.

            If a two-dimensional drawing is required and a line
             diagram/pictorial/isometric drawing is drawn, members will be marked
             according to the assessment criteria and no marks will be awarded
             for the correctness of the drawing.

            If candidates draw/give more information than what is required, mark
             strictly according to the assessment criteria.

            The marks for the correctness of the drawing will only be awarded if
             the entire drawing with all members/parts is correctly drawn.

4.       Incorrect numbering of questions:

            If a candidate numbered an answer incorrectly, but the answer is in
             the correct position according to the sequence of the questions in the
             question paper, circle the incorrect numbering and mark the
             response.

            If questions were answered randomly not following the same
             sequence as in the question paper and the learner numbered
             incorrectly, the response should NOT be marked.

Copyright reserved                                                           Please turn over

### Page 4

Downloaded from hlayiso.com
Civil Technology: Woodworking                 4                          DBE/November 2022
                                   NSC – Marking Guidelines

5.       Duplication of responses and questions answered in the incorrect
         place:

            If a question is answered twice, mark the first response.

            If a question should be answered on an answer sheet and the
             candidate answered it on both the answer sheet and in the answer
             book, mark the response on the answer sheet and cancel the
             response in the answer book.

            If the question was answered in the answer book instead of on the
             answer sheet, mark the response in the answer book according to the
             assessment criteria on the marking guideline.

Copyright reserved                                                          Please turn over

### Page 5

Downloaded from hlayiso.com
Civil Technology: Woodworking                     5                       DBE/November 2022
                                       NSC – Marking Guidelines

QUESTION 1:          OHSA, MATERIALS,            TOOLS,      EQUIPMENT   AND     JOINING
                     (GENERIC)

1.1       1.1.1       Oil or water-based paint                                                   (1)

          1.1.2       Increases the strength of concrete                                         (1)

          1.1.3       Electrolysis                                                               (1)

          1.1.4       Plastic                                                                    (1)

          1.1.5       Zinc                                                                       (1)

1.2       1.2.1            50º/50 degrees 
                           38°/38 degrees
                           42°/42 degrees
                      ANY ONE OF THE ABOVE                                                        (1)

          1.2.2         Ensures stair rails/handrails/railings and or balustrades
                         are in place 
                       Keep treads free of dangerous obstacles
                       Keep treads free of protruding nails
                       Post warning signs
                       Ensure there is sufficient lighting
                       Ensure the surface is not slippery
                      ANY ONE OF THE ABOVE                                                        (1)

          1.2.3        To keep concrete in position 
                       To enable the filling of concrete
                       To act as formwork
                       To shape the treads
                      ANY ONE OF THE ABOVE                                                        (1)

1.3       When transporting/carrying long ladders:
           Ensure that it does not protrude excessively 
           Tie a red or orange flag/warning signs to the end of the ladder 
           Ensure that the ladder is firmly secured to the vehicle
           Protect the ladder during transportation or while carrying it
           Two people should carry the ladder
           It should be carried horizontally and on the same side
          ANY TWO OF THE ABOVE                                                                    (2)

1.4        Safety net/Net 
           Catch platform
          ANY ONE OF THE ABOVE                                                                    (1)

1.5       Brace/Strut                                                                            (1)

Copyright reserved                                                             Please turn over

### Page 6

Downloaded from hlayiso.com
Civil Technology: Woodworking                  6                          DBE/November 2022
                                    NSC – Marking Guidelines

1.6       If the scaffold planks protrude more than 230 mm beyond the last support:
            The scaffold planks might tilt if worker steps on it 
            The worker might fall from scaffold
            It might be hazardous to workers working around the scaffold
           ANY ONE OF THE ABOVE                                                                 (1)

1.7       3 m/3 000 mm                                                                         (1)

1.8
                                         
                            
                                                 OR

                                                 OR

                                                HOOK
                                     
                          

                                                 OR

                                                EYE                                             (4)

1.9       1.9.1       Multi-detector                                                           (1)

          1.9.2       Laser level/Spirit level/Transparent pipe level                          (1)
                                                                                                [20]

Copyright reserved                                                           Please turn over

### Page 7

Downloaded from hlayiso.com
Civil Technology: Woodworking                7                          DBE/November 2022
                                  NSC – Marking Guidelines

QUESTION 2: GRAPHICS AS MEANS OF COMMUNICATION (GENERIC)

NO.                   QUESTIONS                               ANSWERS                  MARKS
                                                 Ground floor: B/FIGURE B 
                                                 FIGURE B shows: No roofline/
       Name the FIGURE that represents the       Roofline in FIGURE A/
  1    ground floor. Give ONE reason for         Garage/Arrows on the                         2
       your answer.                              staircase/Ramp/Door at
                                                 lounge/Entrance door/Garage door/
                                                 Balcony in FIGURE A 
       Deduce the scale that was used to
  2    draw the floor plan of the house from     1:100                                       1
       the given building plan.

  3    Identify number 1.                        Landing                                     1

  4    Identify number 4.                        Balcony/Cantilever                          1

  5    Identify number 5.                        Shower                                      1

                                                 Wash hand basin/Wash
  6    Identify number 6.                                                                     1
                                                 basin/Basin/WHB 

       Give the abbreviation for the symbol at
  7                                            WC                                            1
       number 7.

  8    Identify number 8.                        Ramp                                        1

  9    Identify number 9.                        Roll-up door/Garage door                    1

 10    Identify number 10.                       Fluorescent light                           1

       Identify the number that indicates the
 11                                              No 11/11                                    1
       wall mounted light.

       Give the abbreviations for the
       following:                                FFL 
 12                                                                                           2
         Finished floor level                   NGL 
         Natural ground level
       Name a suitable material that can be      Concrete/Wood/Aluminium/Steel/
 13                                                                                           1
       used for constructing number 2.           Masonry/Bricks/Glass 

Copyright reserved                                                         Please turn over

### Page 8

Downloaded from hlayiso.com
Civil Technology: Woodworking                 8                            DBE/November 2022
                                   NSC – Marking Guidelines

                                                  Coffee nook/Kitchen/Playroom/
                                                  Private lounge/Office/TV room/
       Recommend ONE use for the area
 14                                               Bar/Dining room/Storage space/Any                1
       indicated by number 3.
                                                  use with utility value 

       Recommend ONE permanent fixture            Built-in cupboard/BIC/Cupboard/
 15    for bedroom 1 that can be used for         Closet/Bookshelf/Desk/                           1
       storage.                                   Drawer unit 

       Who is the architect that was
 16                                               HB Nel                                          1
       responsible for the drawing?

       Describe what is indicated by the
 17                                               Direction of the rise of the stairs             1
       arrows on the staircase in FIGURE B.

                                                  Revision 1 – Drawing of sanitary
       State what was done during revision 1                   fitments 
 18                                                                                                2
       and revision 2 of the house plan.
                                                  Revision 2 – Drawing of staircase 

       Deduce the reference code from the
 19                                               QP 6 – 2022                                     1
       building plan.
       Who must be notified when a
 20    contractor sets out levels on a site and Architect/HB Nel                                  1
       there are variances?
                                                  Ceiling light/Light/Light switch/
       Identify ONE important fixture that is
 21                                               Switch/Fan light/Extractor fan/                  1
       omitted in the bathroom.
                                                  Bath/Bidet/Socket outlet/Cabinet 

 22    Draw the symbol for face brick.                                                           2

 23    Draw the electrical symbol for earth.                                                     2

Copyright reserved                                                              Please turn over

### Page 9

Downloaded from hlayiso.com
Civil Technology: Woodworking                  9                               DBE/November 2022
                                    NSC – Marking Guidelines

 24    Draw the symbol for a grease trap.                                                            2

                                                     Total vertical dimensions:
                                                    Control test left    Control test right
                                                    220                 2 960 
                                                    5 450               110 
                                                    220                 2 820 
                                                    5 890               = 5 890 

       Prove by means of a control test that
       the total vertical dimensions on the left                        OR
 25                                                Left side:                                          7
       and right of the plan in FIGURE B are
       equal.                                        220 + 5 450 + 220 = 5 890 mm
                                                   Right side:
                                                     2 960 + 110 + 2 820
                                                     = 5 890 mm
                                                    Note: If the alternative method is
                                                           used, one mark should be
                                                           allocated if both totals are
                                                           the same.
                                                   = 5,89  m x 8,11 m
                                                   = 47,77 m²
       Calculate the area of the first floor.      OR
 26    Show ALL calculations. Give your                                                                3
       answer in m².                               = 5 890 mm x 8 110 mm
                                                   = 47,77 m²
                                                   (47,7679 m2/47,8 m2/48,0 m2)
                                                                                    TOTAL:             40

Copyright reserved                                                                  Please turn over

### Page 10

Downloaded from hlayiso.com
Civil Technology: Woodworking                   10                            DBE/November 2022
                                     NSC – Marking Guidelines

QUESTION 3: CUPBOARDS, CASEMENTS, WALL-PANELLING AND
            QUANTITIES (SPECIFIC)

3.1                                                                       REBATE
               MOULDING

                                                                      3
                                      4

                                                    2

                                                                DRIP GROOVE
                          CORRECTNESS OF TRANSOM:               1

                                NO   ASSESSMENT CRITERIA MARK
                                 1   Correctness of transom    1
                                 2   Rebate                    1
                                 3   Drip groove               1
                                 4   Hatching                  1
                                                        TOTAL: 4                                    (4)

3.2                  CORRECT USE OF DIMENSION PAPER:                                                (1)

                      A     B             C                        D
          3.2.1                                 Number of roof trusses
                                                Internal dimension______
                                                                                +1
                                                Distance between centres
                                                    6,56 
                                                =             +1
                                                     1
                                                = 6,56 + 1
                                                = 7 +1
                                                = 8 roof trusses                                   (3)

          3.2.2                                 Total length of bargeboard needed
                     4/  2,525  10,1 m       Length of bargeboard = Length of rafter +
                                                diameter of gutter + 50 mm
                                                = 2 400 + 75 + 50 
                                                = 2 525 mm
                                                = 2,525 m 
                                                10,1 m bargeboard needed                            (6)

Copyright reserved                                                               Please turn over

### Page 11

Downloaded from hlayiso.com
Civil Technology: Woodworking                   11                          DBE/November 2022
                                     NSC – Marking Guidelines

3.3                                                                         FRONT RAIL
                                                2
                                                                3           TOP

                                                                            TOP UNIT

                                                      5                     UPPER SHELVE

                                                     10                     OVAL HANGING RAIL

                                7
                                                                            INTERMEDIATE SIDE

                                8
                                                                            SHELFS SPACING

                                                                        4
                                                                            SIDE

                                        6

                                7                                           SHELVES

                                                                            BOTTOM
                                            9
                                                                            BASE

                          CORRECTNESS OF CUPBOARD:                  1   1

                            NO.     ASSESSMENT CRITERIA        MARK
                             1      Correctness of cupboard      2
                             2      Front rail                   1
                             3      Top                          1
                             4      Sides                        1
                             5      Upper shelve                 1
                             6      Intermediate side            1
                             7      Three shelves                2
                             8      Shelves equally spaced       1
                             9      Base                         1
                            10      Oval hanging rail            1
                                                        TOTAL:  12                                   (12)

Copyright reserved                                                                Please turn over

### Page 12

Downloaded from hlayiso.com
Civil Technology: Woodworking                   12                     DBE/November 2022
                                     NSC – Marking Guidelines

3.4
                                                                      CEILING BOARD
                                                        CORNICE
                                         4
                                                      CAPPING
                                                      ROUGH GROUND
                                 2

                                     3

                                                      PANEL

                     CORRECTNESS OF TOP PART OF THE WALL PANELLING: 1

                       NO   ASSESSMENT CRITERIA                       MARK
                        1   Correctness of top part of wall panelling   1
                        2   Rough ground                                1
                        3   Panel                                       1
                        4   Capping (any shape)                         1
                                                             TOTAL:     4                       (4)
                                                                                                [30]

Copyright reserved                                                           Please turn over

### Page 13

Downloaded from hlayiso.com
Civil Technology: Woodworking                  13                           DBE/November 2022
                                    NSC – Marking Guidelines

QUESTION 4: ROOFS, CEILINGS, TOOLS, EQUIPMENT AND MATERIALS
            (SPECIFIC)

4.1       4.1.1       H                                                                           (1)

          4.1.2       D                                                                           (1)

          4.1.3       B                                                                           (1)

          4.1.4       G                                                                           (1)

          4.1.5       C                                                                           (1)

          4.1.6       F                                                                           (1)

          4.1.7       A                                                                           (1)

          4.1.8       E                                                                           (1)

4.2       4.2.1       A – Radial arm saw 
                      B – Table saw                                                               (2)

          4.2.2       When doing cross-cutting on the radial arm saw:
                       The work must be held firmly on the table 
                       Grip the handle with your right/left hand 
                       Move the saw behind the guide fence when moving the
                         stock
                       Always start the cut from behind the guide fence
                       Keep the stock steady when sawing is started
                       The saw has to be pulled through the stock by means of a
                         back pressure action
                       Keep hands/fingers away from the rotating blade
                       Wear safety goggles
                      ANY TWO OF THE ABOVE                                                         (2)

          4.2.3       Caring for electrical cords:
                       Repair or replace damaged electrical cords                                (1)

          4.2.4       Caring for blades:
                       Avoid the use of blunt blades 
                       Apply oil to the blades
                       Do not force material into the blades
                       Remove nails and foreign objects from wood before cutting                  (1)
                      ANY ONE OF THE ABOVE

4.3       Consequences if the stock is not fastened tightly in the lathe is that it can:
           Come loose 
           Cause damage to the machine/stock
           Cause injury to the worker
          ANY ONE OF THE ABOVE                                                                     (1)

Copyright reserved                                                              Please turn over

### Page 14

Downloaded from hlayiso.com
Civil Technology: Woodworking                   14                        DBE/November 2022
                                     NSC – Marking Guidelines

4.4       The speed of the lathe is determined by:
           The type of work you are doing 
           The type of material 
           The size of the material
           The position of the belt on the pulleys
          ANY TWO OF THE ABOVE                                                                   (2)

4.5       Selecting timber for a table:
           The type of work that has to be done 
           The strength of the timber 
           The species/type of the timber
           The cost of the timber
           The workability of the timber
           The quality/condition of the timber
          ANY TWO OF THE ABOVE                                                                   (2)

4.6       4.6.1        The letter indicates the method of grading/visually or mechanically
                       graded timber.                                                           (1)

          4.6.2        SABS                                                                     (1)

          4.6.3        The number indicates the strength.                                       (1)

4.7

                                                                     2

                                         1

                  1                                       2

                  COVER STRIP                           METAL T-STRIP
                                     CORRECT TITLES:       3

                           NO.   ASSESSMENT CRITERIA            MARK
                            1    Cover strip correctly drawn      2
                            2    Metal T-strip correctly drawn    2
                            3    Correct titles                   1
                                                         TOTAL:   5                              (5)

Copyright reserved                                                            Please turn over

### Page 15

Downloaded from hlayiso.com
Civil Technology: Woodworking                     15                                             DBE/November 2022
                                       NSC – Marking Guidelines

4.8
                                                2

                                                                                         1
                                  1
                                                                                                   2

                                                                      OR

                          NO. ASSESSMENT CRITERIA    MARK
                           1  Hip                      1
                           2  Ridge OR Eave            1
                                              TOTAL:   2                                                                  (2)

4.9
                                                    4   4                7
                                                                RIDGE BEAM

                                                                  2
                                                                                 RAFTER
                                                                                     7

                                   2

                                                                   45°

                                                            5

                                               COLLAR BEAM                   6

                                            VERTICAL DISTANCE:
                         WALL PLATE         HEIGHT SHOULD NOT
                                            EXCEED HALF OF THE
                                            RISE OF THE ROOF
       3                                                                                                                  3

                         WALL

                                CORRECTNESS OF COLLAR TIE ROOF:                  1           1

                                                                                                                          (11)
Copyright reserved                                                                                     Please turn over

### Page 16

Downloaded from hlayiso.com
Civil Technology: Woodworking                     16                       DBE/November 2022
                                       NSC – Marking Guidelines

                           NO        ASSESSMENT CRITERIA            MARK
                            1        Correctness of collar tie roof    2
                            2        Rafters at 45°                    2
                            3        Overhang                          2
                            4        Ridge beam                        2
                            5        Collar beam                       1
                            6        Vertical distance                 1
                            7        Any ONE label                     1
                                                             TOTAL:   11
                                                                                                    [40]

QUESTION 5: CENTERING, FORMWORK, SHORING AND GRAPHICS AS
            MEANS OF COMMUNICATION (SPECIFIC)

5.1       5.1.1        A                                                                           (1)

          5.1.2        C                                                                           (1)

          5.1.3        B                                                                           (1)

          5.1.4        A                                                                           (1)

          5.1.5        D                                                                           (1)

5.2       5.2.1        Double flying shore                                                         (1)

          5.2.2         Needle 
                        Cleat
                       ANY ONE OF THE ABOVE                                                         (1)

          5.2.3

                                 1          1              OR

                                NO. ASSESSMENT CRITERIA MARK
                                 1  Braces/Diagonal struts   2
                                                      TOTAL: 2                                      (2)

5.3       5.3.1        Needles support the weight of the wall/floor or roof.                       (1)

Copyright reserved                                                               Please turn over

### Page 17

Downloaded from hlayiso.com
Civil Technology: Woodworking                         17                                     DBE/November 2022
                                           NSC – Marking Guidelines

          5.3.2            Folding wedges:
                            Allow height adjustments 
                            Used to tightly wedge the dead shores and props
                            Ease the removal of the members of the shore
                           ANY ONE OF THE ABOVE                                                                          (1)

5.4

                                       2                 3                               2

                                                                             4

                                                                                                  5
                     5

          CORRECTNESS OF KING POST ROOF TRUSS:                       1   1

                           NO.       ASSESSMENT CRITERIA                    MARK
                            1        Correctness of king post roof truss      2
                            2        Rafters                                  2
                            3        King post                                1
                            4        Tie beam                                 1
                            5        Overhang                                 2
                                                                     TOTAL:   8
                                                                                                                         (8)
5.5
                                           5                                             4
                                                                                                        OPEN LAGGINGS
 CLOSED LAGGINGS
                                 5                                                           4

                                                                 3                                      STRUT
                     RIB
                                                3                                3

                                                                                     2                  TIE

          CORRECTNESS OF LAGGINGS: 1                 1       1

                         NO    ASSESSMENT CRITERIA                                           MARK
                          1    Correctness of laggings                                         3
                          2    Tie                                                             1
                          3    Struts                                                          3
                          4    Open laggings (Space between laggings)                          2
                               Closed laggings (No space between
                           5                                                                     2
                               laggings)
                                                               TOTAL:                            11
                                                                                                                         (11)
                                                                                                                         [30]

Copyright reserved                                                                                    Please turn over

### Page 18

Downloaded from hlayiso.com
Civil Technology: Woodworking                        18                          DBE/November 2022
                                          NSC – Marking Guidelines

QUESTION 6: SUSPENDED FLOORS, STAIRCASES, IRONMONGERY, DOORS
           AND JOINING (SPECIFIC)

6.1       6.1.1          Drawer/Till lock                                                              (1)

          6.1.2          To lock drawers/tills                                                         (1)

6.2                              2
                                                               TOP RAIL

                                                               TOP RAISED AND
                                                               FIELDED PANEL
                                 4
                                                               STILE

                                 5
                                                               HIGH LOCK RAIL
                     3                         3

                                                               BOTTOM RAISED
                                                               AND FIELDED PANEL
                                                               MUNTIN

                            6         6
                                 7

                                 8
                                                               BOTTOM RAIL

                  CORRECTNESS OF DOOR:             1   1     APPLICATION OF SCALE: 9      9

           NO.       ASSESSMENT CRITERIA                       MARK
            1        Correctness of door                         2
            2        Top rail                                    1        NOT TO SCALE: USE A
            3        Stiles                                      2        MASK TO MARK THIS
            4        Top raised and fielded panel                1        QUESTION
            5        High lock rail                              1
            6        Bottom raised and fielded panels            2
            7        Muntin                                      1
            8        Bottom rail                                 1
                     Application of scale:
             9       ONE or TWO incorrect         =2                 2
                     More than THREE incorrect = 1
                                                TOTAL:               13                                 (13)

Copyright reserved                                                                   Please turn over

### Page 19

Downloaded from hlayiso.com
Civil Technology: Woodworking                  19                         DBE/November 2022
                                    NSC – Marking Guidelines

6.3

                                       4           2

                                                                    BALUSTERS

                                                         4
                                                                    NATIO
                                                                    NAL
                                                                    HANDRAIL
                                                               2     SENIO
                                                                    NATIO
                                                         3
                                                                    NAL R
                                                                    CERTIF
                                                                    SENIO
                                                                    NEWEL POSTS
                                                                     ICATE
                                                                       R
                                                                    NATIONA
                                                                    CERTI
                                                                    L
                                                                    FICAT
                                                                     SENIOR
                                                                       E
                                                                    CERTIFIC
          CORRECTNESS OF DRAWING:              1                       ATE
                           NO.   ASSESSMENT CRITERIA               MARK
                            1    Correctness of drawing              1
                            2    Newel posts                         2
                            3    Balusters on stairs and landing     1
                            4    Handrails                           2
                                                        TOTAL:       6                          (6)

Copyright reserved                                                           Please turn over

### Page 20

Downloaded from hlayiso.com
Civil Technology: Woodworking                 20                     DBE/November 2022
                                   NSC – Marking Guidelines

6.4
                                                   3

                                           4

                                   2

                          2                    2

          CORRECTNESS OF STILE:            1

                          NO    ASSESSMENT CRITERIA           MARK
                           1    Correctness of stile            1
                           2    Stile surfaces                  3
                           3    Shoulder                        1
                           4    Groove                          1
                                                     TOTAL:     6                          (6)

Copyright reserved                                                      Please turn over

### Page 21

Downloaded from hlayiso.com
Civil Technology: Woodworking                        21                             DBE/November 2022
                                          NSC – Marking Guidelines

6.5
                                                                                 WALL

                                                                                 WALL PLATES

                                                                                 BEARER

                                                                                 FLOOR JOIST

               A                                                                           A
                                                                                 BRICK PIER

                                                                  9
          WALL
                                                                              PROJECTION LINE
                       4        5
                                      8                8              8
                                                                              FLOOR JOIST
      PLASTER
                                                   7                          BEARER
                                6

                                      WALL PLATE
                           4                                  3
                                                                              BRICK PIER
                                               2
               NGL

                                                                              FOUNDATION

          CORRECTNESS OF SECTIONAL VIEW:                      1           1

                           NO       ASSESSMENT CRITERIA                MARK
                            1       Correctness of sectional view        2
                            2       Natural ground level                 1
                            3       Brick pier                           1
                            4       Outer wall                           2
                            5       Plaster                              1
                            6       Wall plate                           1
                            7       Bearer                               1
                            8       Joists                               3
                            9       Projection lines                     1
                                                                TOTAL:  13                              (13)

                                                                                                        [40]
                                                                                               TOTAL:   200
Copyright reserved

## Related documents

- [Civil Technology Nov 2022 (Woodworking) Eng](https://www.hlayiso.com/library/civil-technology-nov-2022-woodworking-eng/78c3d6a1-0010-4aee-81c9-7e6f6b10ed07) — Civil Technology · QP · 2022 · Eng
- [Civil Technology Nov 2022 (Civil Services) Eng](https://www.hlayiso.com/library/civil-technology-nov-2022-civil-services-eng/4c93bddd-9bc8-4067-b666-d6c8b761d7cd) — Civil Technology · QP · 2022 · Eng
- [Civil Technology Nov 2022 (Woodworking) Afr](https://www.hlayiso.com/library/civil-technology-nov-2022-woodworking-afr/4a898ddd-8d12-4ea6-8261-ffb7c75301e3) — Civil Technology · QP · 2022 · Afr
- [Civil Technology Nov 2022 (Civil Services) Afr](https://www.hlayiso.com/library/civil-technology-nov-2022-civil-services-afr/ba5cb9a7-86fb-4eb0-952a-8496715cdd53) — Civil Technology · QP · 2022 · Afr
- [CIV TECH GR12 MEMO SEPT2022 Civil Services Afrikaans](https://www.hlayiso.com/library/civ-tech-gr12-memo-sept2022-civil-services-afrikaans/e517a483-4536-458b-945a-1e2a6820fc1b) — Civil Technology · Memo · 2022 · Afr
- [CIV TECH GR12 MEMO SEPT2022 Woodworking Afrikaans](https://www.hlayiso.com/library/civ-tech-gr12-memo-sept2022-woodworking-afrikaans/84d33c64-7269-4f87-819c-8ea20dfff8f0) — Civil Technology · Memo · 2022 · Afr

## More from Grade 12 Civil Technology

- [Civil Technology (Woodwork) (English and Afrikaans) June 2025 Question Paper](https://www.hlayiso.com/library/civil-technology-woodwork-english-and-afrikaans-june-2025-question-paper/c8edd459-5237-48e0-8588-69d7ecd7f8e5) — QP · 2025 · Afr
- [Civil Technology May-June 2025 (Construction) Afr](https://www.hlayiso.com/library/civil-technology-may-june-2025-construction-afr/591d6ffd-20b1-4748-a1ba-b055be0a14c3) — QP · 2025 · Afr
- [Civil Technology Nov 2025 (Woodworking) Afr](https://www.hlayiso.com/library/grade-12-civil-technology-2025-nsc-november-exam-question-paper/05a95faf-5891-4d88-9e5e-7d13c1d21648) — QP · 2025 · Afr
- [CIV TECH GR12 QP SEPT2024 Woodworking Afrikaans](https://www.hlayiso.com/library/civ-tech-gr12-qp-sept2024-woodworking-afrikaans/1c6d5c64-83b5-456b-abcf-2abc23f1f1fe) — QP · 2024 · Afr
- [CIV TECH GR12 QP SEPT2024 Construction English](https://www.hlayiso.com/library/civ-tech-gr12-qp-sept2024-construction-english/12643629-87af-4230-a48a-002beb7f6cd7) — QP · 2024 · Eng
- [Civil Technology Nov 2024 (Woodworking) Afr](https://www.hlayiso.com/library/civil-technology-nov-2024-woodworking-afr/eefaae29-fe93-4b75-8223-87bf4f3fc14c) — QP · 2024 · Afr

## Collection

- [Grade 12 past papers](https://www.hlayiso.com/grade-12/past-papers)

---

Hlayiso: free CAPS and IEB past papers, memos, notes and study guides for South African learners. When citing, link the page URL above, not a PDF or /api/ URL.