# Civil Technology Grade 12 Eastern Cape Mock 2018 Memo (Eng)

> Grade 12 Civil Technology memorandum from the Eastern Cape Mock Exam 2018 (English), 12 pages. Read online or download the free PDF.

- Page: https://www.hlayiso.com/library/cvlt-gr12-memo-eng-sept2018-construction/2e799de8-da85-41b4-ad09-68d5cdf064b6
- Updated: 2026-09-27
- Subject: Civil Technology
- Grade: Grade 12
- Document type: Memorandum
- Year: 2018
- Exam period: Eastern Cape Mock Exam
- Curriculum: CAPS
- Pages: 12

Breadcrumbs: [Home](https://www.hlayiso.com/) › [Library](https://www.hlayiso.com/library) › [Grade 12](https://www.hlayiso.com/library/grade-12) › [Civil Technology](https://www.hlayiso.com/library/grade-12/civil-technology) › [Civil Technology Grade 12 Eastern Cape Mock 2018 Memo (Eng)](https://www.hlayiso.com/library/cvlt-gr12-memo-eng-sept2018-construction/2e799de8-da85-41b4-ad09-68d5cdf064b6)

## About this document

Civil Technology · Grade 12 · Eastern Cape Mock Exam · 2018. Memorandum, 12 pages. Read online or download the PDF.

Read it free online on the page above; download the PDF from there.

## Document text

Text extracted from the PDF. Layout, diagrams and tables may not survive extraction.

### Page 1

Downloaded from hlayiso.com

                           NATIONAL
                      SENIOR CERTIFICATE

                             GRADE 12

                      SEPTEMBER 2018

         CIVIL TECHNOLOGY: CONSTRUCTION
                 MARKING GUIDELINE

MARKS:   200

                  This marking guideline consists of 12 pages.

### Page 2

Downloaded from hlayiso.com
2                           CIVIL TECHNOLOGY: CONSTRUCTION                  (EC/SEPTEMBER 2018)

QUESTION 1: SAFETY, MATERIAL AND EQUIPMENT (GENERIC)

1.1    1.1.1     True                                                                          (1)
       1.1.2     False                                                                         (1)
       1.1.3     False                                                                         (1)
       1.1.4     True                                                                          (1)

1.2    Any THREE requirements to which a trestle scaffold must comply.
           Soundly constructed with a solid material
           Prevent spreading of supporting legs
           Not higher than 3 m
           Consists of not more than 2 tiers                                     (3 x 1)      (3)

1.3    Similar answer.
       (1) Aluminium conducts (2) electricity / workers subjected to electrical shock          (2)

1.4    Similar answer.
       (1) Paint will cover (2) weaknesses                                                     (2)

1.5    1.5.2     Improves the durability of concrete.                                          (1)

       1.5.5     It improves the strength of concrete.                                         (1)

       1.5.7     It makes concrete more watertight.                                            (1)

       1.5.8     It improves the resistance to abrasion.                                       (1)
1.6    (1) Plastic finish / coating (2) in powder form by (3) using a spray-gun                (3)

1.7    Briefly describe any ONE use of the dumpy level.
        (1) Determine (2) height differences
        (1) Determine (2) levels and slopes
        (1) Setting out (2) of buildings
        (1) Transferring of (2) levels and heights
        (1) Determine horizontal (2) distances                                   (1 x 2)      (2)

1.8    1.8.1     1,5 m                                                                         (1)

       1.8.2     1,535 – 1,47 x 100 = 6,5 m                                                    (4)

1.9    Any THREE materials which can be detected in walls by the multi-detector.
        Ferrous metals
        Non-ferrous metals
        AC wiring
        Wood
        Metal studs
        Steel bars
        Copper pipes                                                      (3 x 1)             (3)

1.10 1.10.1      Dry, soft cloth / Not cleaning agents or solvents                             (1)

       1.10.2    Remove battery                                                               (1)
                                                                                             [30]

Copyright reserved                                                                Please turn over

### Page 3

Downloaded from hlayiso.com
(EC/SEPTEMBER 2018)         CIVIL TECHNOLOGY: CONSTRUCTION                                   3

QUESTION 2: GRAPHICS AND JOINING (GENERIC)

2.1    Use the information on ANSWER SHEET A and complete the site plan on
       scale 1 : 200 according to the following requirements:

      2.1.1     The site boundaries are measured from point A
                The site boundaries in front and back are 23 m long
                The site boundaries on the sides are 25 m long                              (2)

      2.1.2     The front building line is 4 m from the site boundary
                The back and side building lines are 2 m from the site boundaries           (2)

      2.1.3     Show the site entrance, 3 m from the western site boundary                  (1)

      2.1.4     Show the datum level in the north-eastern corner of the site

                Complete the sewage lay-out and abbreviations of the sewage
                appliances according to the following requirements:                         (1)

      2.1.5     The main sewage from the bathroom to the municipal connection               (2)

      2.1.6     The branch sewage to the bathroom and kitchen                               (2)

      2.1.7     Manhole on the site, before the municipal connection                        (2)

      2.1.8     Rodding eyes                                                                (4)

      2.1.9     Inspection eyes                                                             (4)

2.2          Length of shank
             Diameter
             Type of thread
             Head size                                                          (4 x 1)    (4)

2.3 (1) When square shoulder is driven in (2) it resists rotation                           (2)

2.4 2.4 A – Nut
    2.4 B – Thread
    2.4 C – Runout
    2.4 D – Shank                                                                           (4)
                                                                                           [30]

Copyright reserved                                                             Please turn over

### Page 4

Downloaded from hlayiso.com
4                               CIVIL TECHNOLOGY: CONSTRUCTION                (EC/SEPTEMBER 2018)

QUESTION 3: CONCRETE, EXCAVATIONS, FOUNDATIONS & QUANTITIES
           (SPECIFIC)

3.1    3.1.1         Rib-and-block floor                                                      (1)

       3.1.2         3.1.A – Concrete floor block                                             (1)

                     3.1.B – Precast concrete rib                                             (1)

       3.1.3         ONE instance where this type of floor construction will be used:
                      Basements
                      First floors
                      Roof slabs                                                             (1)

       3.1.4         150 mm                                                                   (1)

       3.1.5         200 mm                                                                   (1)

3.2    3.2.1         Slump test                                                               (1)

       3.2.2         Any TWO purposes of the slump test:
                         Test the density by determining the water content
                         Determine the workability and consistency of batches
                         Determine the slump of the mixture                   (2 x 1)        (2)

       3.2.3         16 mm                                                                    (1)

       3.2.4         25 Times                                                                 (1)

       3.2.5         On the building site                                                     (1)

3.3    Any THREE – describe the purpose of curing concrete:
        That the hydration of cement can continue
        Newly placed concrete must be protected against quick drying
        Achieve optimal strength
        Achieve optimal hardness                                                 (3 x 1)     (3)

3.4    Any THREE methods of curing concrete:
        Sprinkling
        Cover with water-retaining substances such as sand, hessian etc.
        Cover with plastic membranes or plastic sheeting
        Commercial seal compound                                         (3 x 1)             (3)

3.5    Any THREE methods to make excavations safe at night:
        Fencing
        Visible warning signs
        Red or orange warning lights
        Covering over excavations                                                (3 x 1)     (3)

Copyright reserved                                                               Please turn over

### Page 5

Downloaded from hlayiso.com
(EC/SEPTEMBER 2018)      CIVIL TECHNOLOGY: CONSTRUCTION                                  5

3.6    Any FOUR causes for an excavation collapse:
        Heavy rains
        Poor soil strata, structure or composition
        Sides not dug at the correct angle
        Improper use of formwork or shoring to support the walls
        Vibration by machinery or heavy vehicles nearby
        Water seeping into the excavated area
        Contact with underground services
        Access to and exit from the excavation
        Soil slides due to cracks or loose soil                            (4 x 1)     (4)

3.7    3.7.1    False                                                                   (1)
       3.7.2    True                                                                    (1)
       3.7.3    False                                                                   (1)
       3.7.4    True                                                                    (1)

3.8    Any FOUR advantages of using pile foundations:
        Can be used in poor soil
        Can be used anywhere, even in water
        The larger base ensures stability
        Relatively quick and easy to install if equipment is available
        If pre-fabricated piles are used, much time is saved
        Quick and less expensive to produce
        Resist tensile stress well
        Can be manufactured elsewhere and transported to the site
        Installation continue even if poor weather conditions hamper
          excavations
        Length of piles can be adjusted, depending on the circumstances
        It offers good resistance against moving soil                   (4 x 1)        (4)

3.9    Any TWO types of foundations (pile- / block foundation excluded):
        Strip foundation
        Stepped foundation
        Raft foundation                                                    (2 x 1)     (2)

3.10             2 / 6 000 = 12 000 mm √
                 2 / 4 000 = 8 000 mm √
                           = 20 000 mm √
       Corners: 4 / 600 = - 2 400 mm √
       Centre line         = 17 600 mm √                                               (5)
                                                                                      [40]

Copyright reserved                                                         Please turn over

### Page 6

Downloaded from hlayiso.com
6                           CIVIL TECHNOLOGY: CONSTRUCTION            (EC/SEPTEMBER 2018)

 QUESTION 4: REINFORCEMENT, FORMWORK, MATERIALS AND EQUIPMENT
            (SPECIFIC)

 4.1 4.1.1       High-tensile or high yield steel                                           (1)

       4.1.2     200 mm                                                                     (1)

       4.1.3     6 Bars                                                                     (1)

       4.1.4     12 mm                                                                      (1)

 4.2 4.2.1       4.2.A – Anchor bar                                                         (1)
                 4.2.B – Stirrups                                                           (1)
                 4.2.C – Main bar                                                           (1)
                 4.2.D – Shear bar                                                          (1)

       4.2.2     Any TWO describing the purpose of the stirrups:
                  Support the shear bars
                  Space and support the main bars
                  Prevent the tearing of concrete                                          (2)

 4.3 Compression (1); Tensile (1); Lateral (1) forces                                       (3)

 4.4 Any TWO describing the purpose of cover depth for reinforced concrete:
      To protect steel against corrosion
      To ensure adequate bonding between the steel and concrete
      To ensure adequate protection of steel in the event of a fire                        (2)

 4.5 Any THREE materials to line formwork – smoother finish:
      Plastic
      Metal sheeting
      Hard board
      Fibre-glass                                                            (3 x 1)       (3)

 4.6 Any TWO defects that can occur in concrete due to shuttering:
      Blowholes
      Uneven colour (discolouration)
      Weakening of structure or collapse                                     (2 x 1)       (2)

 4.7 Any FOUR properties of good formwork:
         Made accurately according to the dimensions indicated
         Sturdy enough to bear the mass of wet concrete without collapsing
         Able to bear the mass of workers and equipment
         Must be strong enough to provide sufficient support, without too much
          deflection, until the concrete has set
         Formwork should be easy to repair on site
         Secured with wire nails, where some should protrude for easy extracting
         Secured with bolts from 13 mm to 19 mm in diameter
         Should be sealed properly so that the concrete does not leak and form
          honeycombs or fins

Copyright reserved                                                       Please turn over

### Page 7

Downloaded from hlayiso.com
(EC/SEPTEMBER 2018)             CIVIL TECHNOLOGY: CONSTRUCTION                               7

            Should be free of dirt (sawdust or releasing agents)
            Quick and simple to erect, mechanically or by hand
            Ensure the correct cover depth for reinforcing, to prevent structural failure
            Fit plywood onto laggings if a smooth finish is required
            Remove when the concrete has cured and is able to support load on its
             own
            Should be easy to remove without damaging the formwork or concrete
            Close-fitting along seams and joints
            Made from recyclable components                                  (Any 4 x 1)         (4)

 4.8    Choose a description in COLUMN B that matches an item in COLUMN A.

        4.8.1         C   (High volumes of concrete)                                              (1)

        4.8.2         J   (Used as awnings)                                                       (1)

        4.8.3         I    (30 MPa compressive strength)                                          (1)

        4.8.4         K    (High antibacterial properties)                                        (1)

        4.8.5         G    (Small volumes of concrete)                                            (1)

        4.8.6         A    (Hard, brittle and breaks easily)                                      (1)

        4.8.7         B    (Low toxicity)                                                         (1)

        4.8.8         D    (Packing of equipment)                                                 (1)

 4.9    Identify the metals as FERROUS or NON-FERROUS:

        4.9.1         Non-ferrous                                                                 (1)

        4.9.2         Ferrous                                                                     (1)

        4.9.3         Non-ferrous                                                                 (1)

        4.9.4         Ferrous                                                                     (1)

        4.9.5         Non-ferrous                                                                 (1)

 4.10   4.10.1        Portable concrete vibrator                                                  (1)

        4.10.2        Concrete mixer                                                              (1)

        4.10.3        Plate compactor                                                         (1)
                                                                                             [40]

Copyright reserved                                                             Please turn over

### Page 8

Downloaded from hlayiso.com
8                             CIVIL TECHNOLOGY: CONSTRUCTION             (EC/SEPTEMBER 2018)

 QUESTION 5: ROOFS, BRICK WALLS AND GRAPHICS (SPECIFIC)

 5.1 5.1.1       Closed eave                                                             (1)

       5.1.2     Any TWO advantages of the closed eave:
                  Provides a more attractive appearance
                  Prevent animals from entering (insects, birds and vermin etc.)
                  No beam filling required                                  (2 x 1)     (2)

       5.1.3     Any TWO types of material that can be used at the closed eave:
                    Soffit board or fibre-cement board
                    Wire netting
                    Pegboard                                                (2 x 1)     (2)

 5.2 Any THREE for discussing the purpose of beam filling:
      To keep out insects and vermin
      Prevent wind / dust from blowing under the roof
      Prevent birds from nesting in the roof
      Improve the stability of the roofing rafters
      Improve the insulation of the building                                (3 x 1)     (3)

 5.3 A         Rafter                                                                    (1)
     B         Queen post                                                                (1)
     C         King post                                                                 (1)
     D         Strut                                                                     (1)
     E         Tie beam                                                                  (1)

 5.4 5.4.1       50 mm                                                                   (1)

       5.4.2     3m                                                                      (1)

 5.5 Any THREE disadvantages of cavity walls:
      Require expert designs / higher design standards
      Require highly skilled workmanship
      Constant supervision is needed during construction
      Cavities are filled with vertical damp-proof course
      More expensive than solid wall constructions
      50 to 100 mm of the internal space is lost                            (3 x 1)     (3)

 5.6 Any TWO types of wall ties that can be used in cavity walls:
         Butterfly pattern
         Nylon wall tie
         Twisted pattern
         Double triangular pattern                                          (2 x 1)     (2)

 5.7 A         Weep hole                                                                 (1)
     B         Concrete floor                                                            (1)
     C         Hard-core filling                                                         (1)
     D         Concrete filling                                                          (1)

 5.8 See ANSWER SHEET B – Isometric view of pier on block foundation                    (6)
                                                                                       [30]

Copyright reserved                                                          Please turn over

### Page 9

Downloaded from hlayiso.com
(EC/SEPTEMBER 2018)      CIVIL TECHNOLOGY: CONSTRUCTION                                 9

 QUESTION 6: SCREEDS, STAIRS, BRICKWORK AND QUANTITIES
            (SPECIFIC)

 6.1 Any ONE type of sand that can be used as bedding sand for pavers:
      River sand
      Crusher dust                                                                     (1)

 6.2 Any FOUR advantages of mortar set pavers:
      Little maintenance is required
      Low life-cycle cost
      Resistant to point loads
      Resistant to fatigue and reflecting traffic patterns
      Resistant to edge movement
      User-friendly installation material is used
      No weeds will be able to grow in between the joints
      No off-gassing installation products used
      Insects will not be able to ruin the appearance of the paved structure
                                                                            (4 x 1)     (4)

 6.3 6.3.1       True                                                                   (1)
     6.3.2       False                                                                  (1)
     6.3.3       True                                                                   (1)
     6.3.4       False                                                                  (1)

 6.4 See ANSWER SHEET C – Determine the amount of bricks needed                        (12)

 6.5 Any THREE types of materials that can be used for cladding:
      Tile cladding
      Brick slip cladding
      Stone cladding
      Timber cladding
      Metal sheet cladding                                                 (3 x 1)     (3)

 6.6 Any TWO types of screeds:
      Dry screed
      Monolithic screed
      Bonded screed                                                                    (2)

 6.7 A       Hand rail                                                                  (1)
     B       Baluster                                                                   (1)
     C       Thread or going                                                            (1)
     D       Riser                                                                      (1)
                                                                                       [30]

                                                                           TOTAL:      200

Copyright reserved                                                        Please turn over

### Page 10

Downloaded from hlayiso.com
10                                 CIVIL TECHNOLOGY: CONSTRUCTION          (EC/SEPTEMBER 2018)

                                     CIVIL TECHNOLOGY
  ANSWER SHEET                 A          (GENERIC)
                                                               NAME:

2.1 Use the information on ANSWER SHEET A and complete the site plan to
    scale 1 : 200.

ERF 121                                        ERF 123                              ERF 125

                     RE
                                        IE                IE     RE

                                     KITCHEN             BATHROOM

                                                     A

                          MH

               A

                                       PARLEMENT STREET

                                                         Site boundaries           2
                                                         Building lines            2
                                                         Site entrance             1
                                                         Datum level               1
                                                         Main sewerage             2
                                                         Branch sewerage           2
                                                         Manhole                   2
                                                         Rodding eyes              4
                                                         Inspection eyes           4
                                                         TOTAL                    20

Copyright reserved                                                            Please turn over

### Page 11

Downloaded from hlayiso.com
(EC/SEPTEMBER 2018)      CIVIL TECHNOLOGY: CONSTRUCTION                             11

                              CIVIL TECHNOLOGY
  ANSWER SHEET           B      CONSTRUCTION
                                                   NAME:

  5.8 Use ANSWER SHEET B and draw an isometric view of a pier on a block
      foundation. Use own scale.

                                                    One-and-a-half brick pier   2
                                                    Stretcher bond              1
                                                    5 Brick layers              1
                                                    Block foundation            2
                                                    TOTAL                       6

                             PIER ON BLOCK FOUNDATION

                                NOT TO SCALE

Copyright reserved                                                    Please turn over

### Page 12

Downloaded from hlayiso.com
12                        CIVIL TECHNOLOGY: CONSTRUCTION              (EC/SEPTEMBER 2018)

                               CIVIL TECHNOLOGY
     ANSWER SHEET        C       CONSTRUCTION
                                                       NAME:

 QUESTION 6.4

     A           B            C                               D
                                     Brick calculation:

     1/        6.5 m
               2.8 m √   18,2 m² √   Total wall area
     √
                                     Bricks:
     1/        18.2
               100 √      1820 √     Total number of bricks

                                     Deductions:
     1/        0.9 m                 Opening A
               2.1 m √   1,89 m² √   Total area
     √
     1/        1.89
               100 √         189 √   Total number of bricks for opening A

                                     Total number of bricks needed:

                                     1 820 - 189 √ = 1631 bricks √

                                                                                    (12)

Copyright reserved                                                       Please turn over

## Related documents

- [CVLT GR12 MEMO ENG SEPT2018 CONSTRUCTION](https://www.hlayiso.com/library/cvlt-gr12-memo-eng-sept2018-construction-1/b6d609b6-89a5-4b39-a9b7-0d878af45cd4) — Civil Technology · Memo · 2018 · Eng
- [CVLT GR12 MEMO AFR SEPT2018 SIVIELE DIENSTE D](https://www.hlayiso.com/library/cvlt-gr12-memo-afr-sept2018-siviele-dienste-d/f328c182-752d-488c-88b6-f2a5cadcbcf2) — Civil Technology · Memo · 2018 · Afr
- [CVLT GR12 MEMO AFR SEPT2018 SIVIELE DIENSTE](https://www.hlayiso.com/library/cvlt-gr12-memo-afr-sept2018-siviele-dienste/4e2739ce-136f-4b93-9ff9-009fc471f0b4) — Civil Technology · Memo · 2018 · Afr
- [CVLT GR12 MEMO ENG SEPT2018 CONSTRUCTION D](https://www.hlayiso.com/library/cvlt-gr12-memo-eng-sept2018-construction-d/4950e454-8a04-433f-9ca3-4a3efac01994) — Civil Technology · Memo · 2018 · Eng
- [CVLT GR12 MEMO AFR SEPT2018 KONSTRUKSIE](https://www.hlayiso.com/library/cvlt-gr12-memo-afr-sept2018-konstruksie/f87d6b3b-6b50-40ae-9a2e-2e545b5f5ce9) — Civil Technology · Memo · 2018 · Afr
- [CVLT GR12 MEMO AFR SEPT2018 HOUTBEWERKING D](https://www.hlayiso.com/library/cvlt-gr12-memo-afr-sept2018-houtbewerking-d/5a60d1cd-8247-4ca9-8d69-2b6683212c89) — Civil Technology · Memo · 2018 · Afr

## More from Grade 12 Civil Technology

- [CVLT Woodworking Eng watermark](https://www.hlayiso.com/library/cvlt-woodworking-eng-watermark/8e178c6e-fa7b-40f4-8a2c-936e0bee3b38) — QP · 2025 · Eng
- [Civil Technology (Woodwork) (English and Afrikaans) June 2025 Question Paper](https://www.hlayiso.com/library/civil-technology-woodwork-english-and-afrikaans-june-2025-question-paper/c8edd459-5237-48e0-8588-69d7ecd7f8e5) — QP · 2025 · Afr
- [Civil Technology May-June 2025 (Construction) Afr](https://www.hlayiso.com/library/civil-technology-may-june-2025-construction-afr/591d6ffd-20b1-4748-a1ba-b055be0a14c3) — QP · 2025 · Afr
- [Civil Technology Nov 2025 (Woodworking) Afr](https://www.hlayiso.com/library/grade-12-civil-technology-2025-nsc-november-exam-question-paper/05a95faf-5891-4d88-9e5e-7d13c1d21648) — QP · 2025 · Afr
- [CIV TECH GR12 QP SEPT2024 Woodworking Afrikaans](https://www.hlayiso.com/library/civ-tech-gr12-qp-sept2024-woodworking-afrikaans/1c6d5c64-83b5-456b-abcf-2abc23f1f1fe) — QP · 2024 · Afr
- [CIV TECH GR12 QP SEPT2024 Construction English](https://www.hlayiso.com/library/civ-tech-gr12-qp-sept2024-construction-english/12643629-87af-4230-a48a-002beb7f6cd7) — QP · 2024 · Eng

## Collection

- [Grade 12 past papers](https://www.hlayiso.com/grade-12/past-papers)

---

Hlayiso: free CAPS and IEB past papers, memos, notes and study guides for South African learners. When citing, link the page URL above, not a PDF or /api/ URL.