# Civil Technology Grade 12 Eastern Cape Mock 2015 Memo (Eng)

> Grade 12 Civil Technology memorandum from the Eastern Cape Mock Exam 2015 (English), 16 pages. Read online or download the free PDF.

- Page: https://www.hlayiso.com/library/cvltech-gr12-memo-sept2015-eng/734f23d1-2b96-4108-8dba-99cd5a8e7a89
- Updated: 2026-09-27
- Subject: Civil Technology
- Grade: Grade 12
- Document type: Memorandum
- Year: 2015
- Exam period: Eastern Cape Mock Exam
- Curriculum: CAPS
- Pages: 16

Breadcrumbs: [Home](https://www.hlayiso.com/) › [Library](https://www.hlayiso.com/library) › [Grade 12](https://www.hlayiso.com/library/grade-12) › [Civil Technology](https://www.hlayiso.com/library/grade-12/civil-technology) › [Civil Technology Grade 12 Eastern Cape Mock 2015 Memo (Eng)](https://www.hlayiso.com/library/cvltech-gr12-memo-sept2015-eng/734f23d1-2b96-4108-8dba-99cd5a8e7a89)

## About this document

Civil Technology · Grade 12 · Eastern Cape Mock Exam · 2015. Memorandum, 16 pages. Read online or download the PDF.

Read it free online on the page above; download the PDF from there.

## Document text

Text extracted from the PDF. Layout, diagrams and tables may not survive extraction.

### Page 1

Downloaded from hlayiso.com

                    NATIONAL
               SENIOR CERTIFICATE

                      GRADE 12

                SEPTEMBER 2015

               CIVIL TECHNOLOGY
                 MEMORANDUM

MARKS:   200

                 This memorandum consists of 16 pages.

### Page 2

Downloaded from hlayiso.com
2                                       CIVIL TECHNOLOGY                        (EC/SEPTEMBER 2015)

QUESTION 1: CONSTRUCTION PROCESSES

1.1     1.1.1        1.1.A – Site boundary
                     1.1.B – Building boundary
                     1.1.C – Base line                                            (3 x 1)      (3)

        1.1.2        Profile board                                                             (1)

        1.1.3        Foundation width and wall thickness                          (2 x 1)      (2)

        1.1.4        Any TWO methods to measure corners at a structure square.
                      3 : 4 : 5 method
                      Building square
                      Electronic/Infra-red square                         (2 x 1)            (2)

1.2     (1) Underground foundations offer more (2) stability / protection against
        compression / protection against weather circumstances.                                (2)

1.3     Any FOUR factors which will influence the choice of foundation
         Load-bearing capacity of the ground.
         Depth of suitable load-bearing ground.
         Depth of water-table.
         Distance from trees and other structures.
         Weight of building.                                                     (4 x 1)      (4)

1.4     Make a neat sketch to illustrate the construction of a raft foundation.

                                                                                               (2)

1.5     1.5.1        Line block – Stringing building lines / Laying of bricks at an even
                     height / level                                                            (1)

        1.5.2        Tingle – Keeping building lines straight                                  (1)

        1.5.3        Long jointer – Jointing of horizontal mortar joints                       (1)

        1.5.4        Belt sander – Levelling large surfaces / Removing marks on
                     wood / Sanding of curves                                                  (1)

        1.5.5        Thicknesser – Planing planks to a required thickness.                     (1)

1.6     Any similar answer:
        (1) Blocked ventilation openings (2) prevents the electric motor from
        cooling down / can cause the electric motor overheat.                                  (2)

Copyright reserved                                                                  Please turn over

### Page 3

Downloaded from hlayiso.com
(E/CSEPTEMBER 2015)               CIVIL TECHNOLOGY                             3

1.7     Any TWO uses of the dumpy level:
         Horizontal readings / height differences
         Determination of slopes
         Distance measuring                                (2 x 1)      (2)

1.8     (1) Set up level (2) through 360º                                (2)

1.9     Any THREE advantages of a cavity wall:
         Prevents water from penetrating the inner walls
         Good thermal isolation
         No rendering needed for outer walls
         Inner walls can be built with cheaper bricks
         Better sound insolation                           (3 x 1)      (3)
                                                                        [30]

Copyright reserved                                              Please turn over

### Page 4

Downloaded from hlayiso.com
4                                   CIVIL TECHNOLOGY                      (EC/SEPTEMBER 2015)

QUESTION 2: ADVANCED CONSTRUCTION PROCESSES

2.1     (1) Bottom side of concrete beam is subjected to tensile stress.
        (2) Concrete is weak under tensile stress and (3) steel is strong under
        tensile stress.                                                                 (3)

2.2      Bent up bars over shear line
         Stirrups over shear line                                          (2 x 1)     (2)

2.3     Any similar answer:
        (1) Depth of concrete (2) over steel reinforcement.                             (2)

2.4     2.4.1    4                                                                      (1)

        2.4.2    6                                                                      (1)

2.5      Any FIVE advantages of laminated shuttering boards:
          Economical
          Easy to handle
          Larger sheets give better finish
          Larger sheets require fewer joints
          Rigid
          No unnecessary expansion and shrinking                           (5 x 1)     (5)

2.6     Make a neat sketch on a scale 1 : 10 of an open-eave construction with
        beam filling and indicate the following parts:

        2.6.1    Single brick wall construction                                         (1)

        2.6.2    Wall plate                                                             (1)

        2.63     Rafter                                                                 (1)

        2.6.4    Tie beam                                                               (1)

        2.6.5    Purlin                                                                 (1)

        2.6.6    Roof sheet                                                             (1)

        2.6.7    Fascia board                                                           (1)

        2.6.8    Beam filling                                                           (1)

        2.6.9    Correct scale                                                          (2)

Copyright reserved                                                            Please turn over

### Page 5

Downloaded from hlayiso.com
(E/CSEPTEMBER 2015)               CIVIL TECHNOLOGY                                           5

2.7    Type / Weight of roof covering                                                      (1)
2.8    Any THREE situations where shoring is generally used:
        (1) To support walls (2) which are unstable.
        (1) To support walls where (2) structural changes are being carried out
        (1) To support walls (2) where the bottom part of the wall must be
          demolished.
        (1) To support walls where (2) furrows being dug close to foundations
        (1) To support adjacent walls where (2) structures are being
          demolished.
        (1) To give support to (2) a floor or roof for work to the load-bearing wall.
          (3 x 2)                                                                          (6)
2.9    Any THREE types of shoring which are generally used:
        Raking shores
        Flying shores
        Dead shores                                                         (3 x 1)       (3)
2.10   2.10.1        Voussoirs

       2.10.2        Intrados

       2.10.3        Key brick

       2.10.4        Extrados

       2.10.5        Abutment

       2.10.6        Span                                                                 (6)
                                                                                         [40]

Copyright reserved                                                              Please turn over

### Page 6

Downloaded from hlayiso.com
6                                   CIVIL TECHNOLOGY                       (EC/SEPTEMBER 2015)

QUESTION 3: CIVIL SERVICES

3.1     Raising water pressure.                                                           (1)

3.2     3.2.1    Ø20 mm

        3.2.2    Ø12 mm                                                                   (1)

3.3     Similar answer:
        (1) Black colour prevents (2) heat from being emanated (absorb heat).             (2)

3.4     (1) Sharpens the sun beams. (2) Prevents the dust from covering the
        parts.                                                                            (2)

3.5     Any THREE advantages of polythene pipes for water supply:
         Resistance to chemicals
         Flexible / Easily laid around bends
         Cheap
         Light in weight
         Easy to install                                                   (3 x 1)       (3)

3.6     3.6.1    Screwed threads                                                          (1)

        3.6.2    Glued / Clamps / Ball and spigot joint                                   (1)

        3.6.3    Fittings soldered together / Brass compression fittings                  (1)

3.7     3.7.1    False                                                                    (1)

        3.7.2    False                                                                    (1)

        3.7.3    True                                                                     (1)

        3.7.4    True                                                                     (1)

        3.7.5    True                                                                     (1)

3.8     (1) Amount of outflow / Number of persons.
        (2) Absorption ability of the soil                                  (2 x 1)       (2)

Copyright reserved                                                             Please turn over

### Page 7

Downloaded from hlayiso.com
(E/CSEPTEMBER 2015)               CIVIL TECHNOLOGY                                             7

3.9        Plug the lower end of the drain.
           Pour in water at the highest point until the pipe is full.
           Leave it for two hours.
           Check water level.
           Top the water level up.
           Check water level after half an hour – If the level has dropped less
            than 6 mm, there are no leaks.                                 (6 x 1)       (6)

3.10    Any FOUR advantages of PVC-drain pipes:
         Light weight
         Long lengths available
         Less joining work
         Tight joints
         Easy to handle / Install
         Good flow efficiency
         Resist most chemicals                                        (Any 4 x 1)       (4)
                                                                                        [30]

Copyright reserved                                                              Please turn over

### Page 8

Downloaded from hlayiso.com
8                                 CIVIL TECHNOLOGY                      (EC/SEPTEMBER 2015)

 QUESTION 4: MATERIALS AND QUANTITIES

 4.1    When necessary to remove shuttering prematurely.
        Cold weather                                                                    (2)

 4.2 (1) Chemical reaction (2) Physical reaction / Cement hardens                        (2)

 4.3 (1) Cement can react with moisture (2) in the air / hardened / becomes
     unusable                                                                            (2)

 4.4 4.4.1 Plasticisers – Lend workability to mix / Reduce amount of water
           needed / Less water – greater strength.                                       (1)

       4.4.2 Air-entraining agents – Improve workability / Tiny bubbles improve
             frost resistance.                                                           (1)

       4.4.3 Retarders – During hot weather / When transporting over long
             distances.                                                                  (1)

 4.5       Throw stone in mixing drum.
           Add some water.
           Add cement.
           Add sand.
           Add rest of water.                                                           (5)

 4.6 Removing air bubbles / Distribute concrete evenly                                   (1)

 4.7 Test workability of concrete / Determine water content of mix.                      (1)

 4.8 4.8.1 Veneer                                                                        (1)

       4.8.2 Plywood                                                                     (1)

       4.8.3 Block board                                                                 (1)

 4.9 Any THREE advantages of hardboard:
      Large sheets
      Uniform texture
      Different thicknesses
      Can be painted and varnished.
      Can be glued.
      Waste wood can be used optimally.
      Be worked with ordinary woodwork tools.                        (Any 3 x 1)        (3)

Copyright reserved                                                            Please turn over

### Page 9

Downloaded from hlayiso.com
(E/CSEPTEMBER 2015)                   CIVIL TECHNOLOGY                                   9

 4.10    FIGURE 4.10 on ANSWER SHEET A shows the foundation plan for a
         structure. Use the quantity list on ANSWER SHEET A and answer the
         following questions with regard to the foundation:

         4.10.1       Determine the centre line of the foundation.                    (4)

         4.10.2       Determine the volume of concrete needed to cast two
                      foundations.                                                   (4)
                                                                                    [30]

 QUESTION 5: APPLIED MECHANICS

 5.1 Determine the centroid from point P of the isosceles triangle in
     FIGURE 5.1. Show all formulas and calculations.

           X=     =    =2+2+4

         Y=     =     =2+3+5                                                          (4)

 5.2 FIGURE 5.2 on ANSWER SHEET B shows a beam with point loads.
     Determine the following on ANSWER SHEET B:

        5.2.1     The bending moment values.                                          (7)

        5.2.2     Complete the bending moment diagram according to the bending
                  moment values.                                                      (4)

 5.3 FIGURE 5.3 on ANSWER SHEET C shows a space diagram of a roof
     truss. Determine graphically on ANSWER SHEET C the sizes and nature
     of the parts of the truss by completing the force diagram and the table.       (15)
                                                                                    [30]

Copyright reserved                                                          Please turn over

### Page 10

Downloaded from hlayiso.com
10                                   CIVIL TECHNOLOGY                    (EC/SEPTEMBER 2015)

QUESTION 6: GRAPHICS AND COMMUNICATION

6.1     FIGURE 6.1 on ANSWER SHEET D shows the floor plan of a building
        which is drawn on a scale 1 : 100 according to the following requirements:

          The gable roof construction with a pitch of 30º.
          Eave incline of 400 mm at all four elevations.
          Wall height of 2,6 m from floor to ceiling.

        Use the information on ANSWER SHEET D and draw on ANSWER
        SHEET D the south elevation of the building on a scale 1 : 100. Draw the
        south elevation from the given NATURAL GROUND LEVEL-line.
        The following detail must be shown:

        6.1.1        Roof lines                                                         (2)

        6.1.2        Barge board                                                        (3)

        6.1.3        Eave incline                                                       (1)

        6.1.4        Wall height                                                        (2)

        6.1.5        Garage door                                                        (2)

        6.1.6        Garage door handle                                                 (1)

        6.1.7        Garage ramp                                                        (2)

        6.1.8        Window                                                             (2)

        6.1.9        Window sill                                                        (1)

        6.1.10       Door                                                               (2)

        6.1.11       Door handle                                                        (1)

        6.1.12       Step                                                               (1)

        6.1.13       Floor level                                                        (1)

        6.1.14       labels                                                             (2)

        6.1.15       Gutters/down pipes                                                 (3)

        6.1.16       Neatness                                                           (2)

Copyright reserved                                                           Please turn over

### Page 11

Downloaded from hlayiso.com
(E/CSEPTEMBER 2015)               CIVIL TECHNOLOGY                                       11

6.2      Any FOUR purposes of a site plan:
          Show building lines
          Show servitudes
          Show municipal sewerage connection
          Entrance to the site
          General placement of buildings
          Placing of buildings with regard to reference points and boundary lines.
          Detail of general services / sewerage points / water points
          Location of house in relation to north point / winds
          Number of site and adjacent sites                                             (4)

6.3     6.3.1
                 Water meter                      WM
                                                                                         (2)

        6.3.2    Inspection eye       IE
                                                                                         (2)

        6.3.3    Grease trap
                                    GT
                                                                                         (2)

        6.3.4
                 Hard core                                         HC
                                                                                        (2)
                                                                                       [40]

                                                                          TOTAL:        200

Copyright reserved                                                            Please turn over

### Page 12

Downloaded from hlayiso.com
12                                    CIVIL TECHNOLOGY                        (EC/SEPTEMBER 2015)

 ANSWER SHEET                   CIVIL TECHNOLOGY         NAME:

ANTWOORDBLAD
                           A SIVIELE TEGNOLOGIE NAAM:
QUESTION/VRAAG 4.10

                                                                   Fondament breedte = 600 mm
                                                                   Fondament dikte = 200 mm

                                                           5 000   Foundation width = 600 mm
                                                                   Foundation thickness = 200 mm

                             10 000

     A       B         C                                  D

                             Senterlyn / Centre line:

                             10 000 + 10 000 + 5 000 + 5 000 – (4 x 600) = 27 600 mm

                             Volume beton / Volume concrete:
     2    27,6
          0,6                            (3,312 m³ x 2)
          0,2        6,624    6, 624 m³ Beton benodig vir twee fondamente.
                                        Concrete needed for two foundations.

Copyright reserved                                                                Please turn over

### Page 13

Downloaded from hlayiso.com
  (E/CSEPTEMBER 2015)                   CIVIL TECHNOLOGY                                          13

      ANSWER SHEET                   CIVIL TECHNOLOGY              NAME:

   ANTWOORDBLAD
                             B SIVIELE TEGNOLOGIE NAAM:
  QUESTION/VRAAG 5.2

  5.2.1      Die buigmomentwaardes / The bending moment values

               a    = …0 N
               b    = …(80 x 2) + (-60 x 2) = 40 N
               c    = …(80 x 6)+(-60 x 6) +(-40 x 4) = -40 N
               d    = …(80 x 8) + (-60 x 8) + (-40 x 6) + (80 x 2) + (-40 x 2) = 0 N           (7)

  5.2.2       Die buigmomentdiagram / The bending moment diagram                               (5)

  SCALE/SKAAL: 1 N = 1 mm

      60 N          40 N                      40 N        20 N

             2m               4m                     2m

      80 N                                    80 N

             40 N

                  +
0N                                                            0N
  a                 b                     c               d

                                              -40 N

  Copyright reserved                                                                   Please turn over

### Page 14

Downloaded from hlayiso.com
14                            CIVIL TECHNOLOGY           (EC/SEPTEMBER 2015)

  ANSWER SHEET             CIVIL TECHNOLOGY      NAME:

 ANTWOORDBLAD
                       C SIVIELE TEGNOLOGIE NAAM:

QUESTION/VRAAG 5.3                                                     (15)

SPACE DIAGRAM:
RUIMTE-DIAGRAM:

Copyright reserved                                           Please turn over

### Page 15

Downloaded from hlayiso.com
(E/CSEPTEMBER 2015)              CIVIL TECHNOLOGY              15

AGTEDIAGRAM
FORCE DIAGRAM

Skaal/Scale: 1 mm = 1 N

  DEEL/PART      STUT/STRUT   STANG/TIE

     BG               58 N
      CH              34 N
      DI              58 N
      FI                        29 N
      FG                        50 N
     GH               25 N
      HI                        13 N

Copyright reserved                                  Please turn over

### Page 16

Downloaded from hlayiso.com
16                                         CIVIL TECHNOLOGY                    (EC/SEPTEMBER 2015)

 ANSWER SHEET                         CIVIL TECHNOLOGY        NAME:

ANTWOORDBLAD
                              D SIVIELE TEGNOLOGIE NAAM:
VRAAG/QUESTION 6.1                                                                  (28)

                                        8 000
                   280     3 000      280       4 160         280

             280

     8 000    7 440

             280

                                                                      Roof lines            2
                                           FLOORPLAN                  Barge board           3
                                                                      Eave incline          1
                                            SCALE 1 : 100             Wall height           2
                                                                      Garage door           2
                                                                      Garage handle         1
                                                                      Garage ramp           2
                                                                      Window                2
                                                                      Window sill           1
                                                                      Door                  2
                                                                      Door handle           1
                                                                      Step                  1
                                                                      Floor level           1
                                                                      labels                2
                                                                      Gutters/down pipes    3
                                                                      Neatness              2
                                                                      TOTAL                 28

                      SOUTH ELEVATION
                      SCALE 1 : 100              Neatness
Copyright reserved                                                                 Please turn over

## Related documents

- [CVLTECH GR12 MEMO SEPT2015 AFR](https://www.hlayiso.com/library/cvltech-gr12-memo-sept2015-afr/499243c3-9639-46d0-90f2-d372f7df4e7e) — Civil Technology · Memo · 2015 · Afr
- [CVLTECH GR12 QP SEPT2015 AFR](https://www.hlayiso.com/library/cvltech-gr12-qp-sept2015-afr/869b47f0-5b29-46c7-9698-b96a272efdd8) — Civil Technology · QP · 2015 · Afr
- [Civil Technology Nov 2015 Memo Eng](https://www.hlayiso.com/library/civil-technology-nov-2015-memo-eng/0b040a57-1607-42d5-971a-bf01f012786c) — Civil Technology · Memo · 2015 · Eng
- [Civil Technology Feb March 2015 Memo Eng](https://www.hlayiso.com/library/civil-technology-feb-march-2015-memo-eng/aedf8743-b698-4a4c-b0c6-791f5a20e050) — Civil Technology · Memo · 2015 · Eng
- [CIV TECH GR12 MEMO SEPT2023 Construction English](https://www.hlayiso.com/library/civ-tech-gr12-memo-sept2023-construction-english/9ab6f3f0-4774-49bf-8311-57f09822adf6) — Civil Technology · Memo · 2023 · Eng
- [CIV TECH GR12 MEMO SEPT2022 Civil Services Afrikaans](https://www.hlayiso.com/library/civ-tech-gr12-memo-sept2022-civil-services-afrikaans/e517a483-4536-458b-945a-1e2a6820fc1b) — Civil Technology · Memo · 2022 · Afr

## More from Grade 12 Civil Technology

- [CVLT Woodworking Eng watermark](https://www.hlayiso.com/library/cvlt-woodworking-eng-watermark/8e178c6e-fa7b-40f4-8a2c-936e0bee3b38) — QP · 2025 · Eng
- [Civil Technology (Woodwork) (English and Afrikaans) June 2025 Question Paper](https://www.hlayiso.com/library/civil-technology-woodwork-english-and-afrikaans-june-2025-question-paper/c8edd459-5237-48e0-8588-69d7ecd7f8e5) — QP · 2025 · Afr
- [Civil Technology May-June 2025 (Construction) Afr](https://www.hlayiso.com/library/civil-technology-may-june-2025-construction-afr/591d6ffd-20b1-4748-a1ba-b055be0a14c3) — QP · 2025 · Afr
- [Civil Technology Nov 2025 (Woodworking) Afr](https://www.hlayiso.com/library/grade-12-civil-technology-2025-nsc-november-exam-question-paper/05a95faf-5891-4d88-9e5e-7d13c1d21648) — QP · 2025 · Afr
- [CIV TECH GR12 QP SEPT2024 Woodworking Afrikaans](https://www.hlayiso.com/library/civ-tech-gr12-qp-sept2024-woodworking-afrikaans/1c6d5c64-83b5-456b-abcf-2abc23f1f1fe) — QP · 2024 · Afr
- [CIV TECH GR12 QP SEPT2024 Construction English](https://www.hlayiso.com/library/civ-tech-gr12-qp-sept2024-construction-english/12643629-87af-4230-a48a-002beb7f6cd7) — QP · 2024 · Eng

## Collection

- [Grade 12 past papers](https://www.hlayiso.com/grade-12/past-papers)

---

Hlayiso: free CAPS and IEB past papers, memos, notes and study guides for South African learners. When citing, link the page URL above, not a PDF or /api/ URL.