# Engineering Graphics and Design Grade 11 P1 2020 Memo (Eng)

> Grade 11 Engineering Graphics and Design Paper 1 memorandum from the Eastern Cape November 2020 (English), 10 pages. Read online or download the free PDF.

- Page: https://www.hlayiso.com/library/egd-p1-gr11-nov2020-qp-memo-eng-d/af275228-8eea-4314-8b2f-c1cb80bcfb8b
- Updated: 2026-09-27
- Subject: Engineering Graphics and Design
- Grade: Grade 11
- Document type: Memorandum
- Year: 2020
- Exam period: Eastern Cape November
- Paper: 1
- Curriculum: CAPS
- Pages: 10

Breadcrumbs: [Home](https://www.hlayiso.com/) › [Library](https://www.hlayiso.com/library) › [Grade 11](https://www.hlayiso.com/library/grade-11) › [Engineering Graphics and Design](https://www.hlayiso.com/library/grade-11/engineering-graphic-and-design) › [Engineering Graphics and Design Grade 11 P1 2020 Memo (Eng)](https://www.hlayiso.com/library/egd-p1-gr11-nov2020-qp-memo-eng-d/af275228-8eea-4314-8b2f-c1cb80bcfb8b)

## About this document

Engineering Graphic And Design · Grade 11 · Eastern Cape November · 2020. Memorandum, 10 pages. Read online or download the PDF.

Read it free online on the page above; download the PDF from there.

## Document text

Text extracted from the PDF. Layout, diagrams and tables may not survive extraction.

### Page 1

Downloaded from hlayiso.com

*IGRDSE1*

### Page 2

snc Downloaded from hlayiso.com es

QUESTION 1A: ANALYTICAL (CIVIL)
Given:
INCOMPLETE FLOOR PLAN The incomplete floor plan of a house. A title panel and a table of questions. The drawing has not been prepared to
an indicated scale.
Instructions:
Pa 5 500 y NOTE: Complete the table below by neatly answering the questions, which refer to the accompanying drawing and title
1 Contractors must verify all dimensions panel [28]
and levels on site before commencing
work. Architects to be notified
immediately of any discrepancies QUESTIONS ANSWERS
1 | What is the name of the architectural firm responsible for
ARCHITECTS SIGNATURE 1
ly drawing the house plans?
CHENTS SIGNATURE 2 | What is the project number for this drawing? 1
(ZZZZZZ
3 | 2020-03-27 Jcoupuete THe winoows 3 | Who was the person responsible for checking the 1
BEDROOM correctness of the drawing?
2 {2020-03-27 fins s
17,48 m? SERTTHE Doors 4 | Whois the person responsible for drawing the floor plan? q
5 | When was the drawing printed?
REVISION DATE DESCRIPTION 41
* BOTHA ARCHITECTS 6 | Who is the owner of the house? 1
11 Da Gamma street ——
?
q cxmmmoobL seeaewena 7 | What feature is indicated by the symbol at A? ;
3
S| IPASSAGE TILES 6330 Tai
| TILES 7,03 m ——c TEL: 072 293 0392 8 | What feature does the line, indicated by arrow B show? a
= 2.48 m2 . FAX: 042 293 0392
” [4 EMAIL: kbotha@gmail.com —
A SaNIcD BY OMEGF PRAT 9 | What does the abbreviation NTS in the title panel stand A
BLUEDEVILLE 2020-04-01 for?
> 10 | Has revision 3 been done correctly? Explain
(zzzzzz] DRAWING THLE 1
LOUNGE / DINING ROOM
‘WOOD | FLOOR PLAN
17,59 m* lI dei SRORGT 11 | What is wrong with the hatching in the floor plan? .
LU VW g 7 PROPOSED NEW HOUSE FOR
VW KITCHEN MRS. X. RUPPING, STAND 1442, 12 | What does the abbreviation BIC indicate?
4 B 1 | TILES THORNHILL, EASTERN CAPE. 2
iI ssi . ,
x i PROJECT NONBER DRAWING NUMBER 13 | Which VIEW is indicated by arrow C? 2
gl |S il DP 2020 - 04 10f4
| | DATE DRAWN | GRECKED SCALE 14 | What is the width of the doors in mm if a scale of 1 : 100
2020-03-20 LINDO | TYRON | NTS was used? 2
Y] Ail 2 REFERENGE CODE
ollle DOE-2020 15 | In the space provided below, determine the perimeter of the entire house. y
16 | in the space provided below, determine the total floor area that must be filed, in square meters. | 4
TOTAL | 27
oO ANSWER 15 ANSWER 16
NAME
NAME: [2

Copyright reserved Please tum over

### Page 3

Engineering graphics and design / P1

Downloaded from hlayiso.com —

QUESTION 2: INTERPENETRATION AND DEVELOPMENT

Given:

The top view and incomplete front view of a right regular
triangular prism that penetrates a right regular hexagonal
prism

The auxiliary view of the triangular prism

The position of point X, the centre ofthe hexagon and starting
point for the top view.

A starting point AB for the development required

Instructions:
Draw, to a scale 1: 1 and in first angle orthographic projection, the
following views of the two solids:

21
2.2
2.3
24

The given top view using point X as a starting point.

The complete front view showing the curve of interpenetration.
The left view

The surface development of the triangular prism

Use line AB as reference point.

Show ALL constructions.

[39]

60

20

60

ASSESSMENT CRITERIA

4 | TOP view+ 6
CONSTRUCTION

FRONT VIEW +

INTERPENETRATION | 9

3) Lert view 8

4) DEVELOPMENT 16

TOTAL | 39

NAME

NAME. [3

Copyright reserved

Please tum over

### Page 4

Engineering graphics and design / P1

EC / November 2020

Downloaded from hlayiso.com

QUESTION 3: PERSPECTIVE

Given:
Two views of a HOUSE and the information needed
to draw a two-point perspective drawing.

PP — Picture plane

HL - Horizon line

GL ~ Ground line

SP - Station point

Instructions:
Complete the perspective drawing

* Align the drawing sheet with the ground line (GL).
* Determine and label the vanishing points.

* Show ALL necessary construction.

* NO hidden detail is required.

144]
CEMENT PORCH AROUND:
THE HOUSE
PP
HL
ASSESSMENT CRITERIA

4 | CONSTRUCTION + VPs 5

2 | ROOF 15

3 | WALLS 7

4 | DOOR + WINDOWS 10
r
| 5 | PORCH 7
|
|
. TOTAL| 44

t : 1 GL
ae Me NAME
CEMENT PORCH AROUND SP
THE HOUSE
NAME [4

Copyright reserved

Please tum over

### Page 5

Engineering graphics and design / P1

Downloaded from hlayiso.com

EC / November 2020

QUESTION 4: CIVIL DRAWING

Given:

© The incomplete SOUTH ELEVATION of a proposed new
dwelling, showing the walls, step, windows, the door openings
and notes.

© The incomplete floor plan showing the walls, position of the
doors, windows and sanitary fixtures.

© The incomplete foundation and wall detail.

* Room designations and floor finishes.

* A door and window schedule.

* A table of sanitary fixtures.

* The floor plan of the new dwelling, drawn to scale 1 : 50 and the
starting point P for the sectional view to scale 1 : 20 (on page 6).

Instructions:
Answer this question on page 6

4.1. Using the given incomplete floor plan draw in first-angle
orthographic projection and to scale 1 : 50, the following views
of the new dwelling

4.1.1 THE COMPLETE FLOOR PLAN
Add the following features to the drawing:
* ALL doors and windows.
* ALL sanitary fixtures as indicated by the abbreviations.
* ALL hatching detail.

4.1.2 THE SOUTH ELEVATION
Show the following features on the drawing:
« The outside walls, step, doors and window detail as well as the
window sill under the widows.
« Draw a break line 2 700 mm above the finished floor level.
© The finished floor level.

4.2 In the space provided on page 6, using the incomplete
foundation and break line, draw, to scale 1 : 20, a DETAILED
SECTION on cutting plane A-A of the area in the ellipse shown
on the incomplete floor plan

Show the following features:

¢ The complete foundation, external wall and window detail
* The lintels above the window.

* The window sill under the window.

* The bath in position.

* Indicate with dimensioning the length of the bath.

* ALL hatching detail

* ALL substructure hatching may be drawn neat in freehand.

Label the following:

« The south elevation and scale.

« The room designations and floor finishes.

« Using the correct abbreviations, label the following features in
the correct view: natural ground level, finished floor level and
damp proof course.

NOTE:
ALL drawings must comply with the guidelines and graphical
symbols contained in the SANS 10143. [39]

3.000

INCOMPLETE SOUTH ELEVATION

AM wa wi Gy
NWS Wer 3
8 2
sH 3
D
we
1 4
—]
° w3
sD 5 in
STEP
INCOMPLETE FLOOR PLAN
4
2X 125 x80 mm
LINTELS ABOVE ALL
Z DOOR AND WINDOW
OPENINGS:
3
gs
Z|
| oI
3g
a
g
Z|
GROUND LEVEL
eI
FS)

600.

INCOMPLETE WALL AND
FOUNDATION DETAIL

DOOR AND WINDOW SCHEDULE

y TO FIT y , TOFIT )
t { t {
DOOR OPENING
WINDOW OPENING
SLIDING DOOR OPENING
|_— FINISHED FLOOR LEVEL
STEP
GROUND LEVEL g g
200) “ N
SLIDING DOOR DOOR FRAME AND
(sD) DOOR (0)
ROOM DESIGNATIONS
FLOOR FINISHES: 1500 2000
1. BEDROOM CARPET 450 450 450
2. BATHROOM TILE A 1 7
3, KITCHEN TILE
4, LOUNGE woop
5. PORCH CEMENT
c B A c B A c lA BI
3
FEATURES =
D DOOR
SD SLIDING DOOR 3
wi WINDOW g| c c c c c
w2 WINDOW
WS WINDOW WINDOW (wa) WINDOW (wa)
FIXTURES
We TOILET
WB WASH BASIN 1.000
SH SHOWER 1 ino notes
B BATH a
S SINK B )PENING SIDE
ol INGED SIDE
Z| A IXED PANE
o THICKNESS OF ALL FRAMES: 50mm
c
WINDOW SILL: 180 x 20 mm FIBRE
WINDOW (WA) CEMENT SILL UNDER ALL WINDOWS.
SANITARY FIXTURES

2.050

500
FA 200
3

| zor

850,

FLOOR LevEL|

750

750.

SHOWER
(SH)

(we)

400

WASH BASIN

1200
TOILET BATH SINK
(we) (8) ‘s)

Copyright reserved

Please tum over

### Page 6

Engineering graphics and design / P1

Downloaded from hlayiso.com

EC / November 2020

PENALTIES

1 | INCORRECT OVERALL
SCALE

2 | INCORRECT POSITIONING
OF VIEWS.

3 | NON-ALIGNMENT OF VIEWS

TOTAL PENALTIES (-)

ASSESSMENT CRITERIA

FLOOR PLAN

DOORS +

WINDOWS 7

FIXTURES 9

1
2
3 | vasets 5
4

HATCHING 5

SUB TOTAL 36

SOUTH ELEVATION

4 | Wats + steps

+ FFL + BREAK 7
LINE
DOOR +
2 WINDOWS 14
3 | casets 2

SUB TOTAL 23

DETAILED SECTION

4] Founoations= |g 3
wats+siaa | 82
3] HarcHine 6i
A} sath 24
5] vimension 4
6 | tasets 13

SUB TOTAL 30

f TOTAL | 89
PENALTIES (-)
—_ GRAND TOTAL
FLOOR PLAN DETAILED SECTION ON A:A i NAME
SCALE 1: 50 SCALE 1: 20
NAME [6

Copyright reserved

### Page 7

Downloaded from hlayiso.com

ISEBE LEMFUNDO LEMPUMA KOLONI
EASTERN CAPE EDUCATION DEPARTMENT
OOS-KAAP ONDERWYSDEPARTEMENT

NATIONAL SENIOR CERTIFICATE
NASIONALE SENIOR SERTIFIKAAT

GRADE 11
GRAAD 11

ENGINEERING GRAPHICS AND DESIGN P1
INGENIEURSGRAFIKA EN -ONTWERP V1

NOVEMBER 2020
MEMORANDUM

MARKS / PUNTE: 200
TIME / TYD: 3 hours / uur

This memorandum consists of 7 pages.
Hierdie memorandum bestaan uit 7 bladsye.

Copyright reserved / Kopiereg voorbehou

Engineering graphics and design/P1

NSC EC / November 2020

PAPER 1
QUESTION 1: ANALYTICAL _ MARKING GUIDELINE.

VRAESTEL 1
VRAAG 1: ANALITIES _NASIENRIGLYN

‘oon alle berekeninge / Show all calculati

ANSWERS ANTWOORDE
1 | BOTHA ARCHITECTS 1 1 | BOTHA ARGITEKTE 1
2 | DP 2020 - 04 1 2 | DP 2020 - 04 1
3 | TYRON 1 3 | TYRON 1
4 |LINDO 1 4 |LINDO 1
5 | 2020-04-01 1 5 | 2020-04-01 1
6 |MRS. X. RUPPING 1 6 | MEV. X. RUPPING 1
7 | BIDET 1 7 | BIDET 1
8 | ARCH / OPENING IN THE WALL 2 8 | BOOG (OPENING) IN DIE MUUR 2
9 |NOT TO SCALE 1 9 | NIE VOLGENS SKAAL 1
40 NO. THE WINDOW MUST HAVE 2 10 NEE. DIE VENSTERS MOET 2
TWO LINES INSTEAD OF ONE TWEE LYNE HE IPV EEN
" MECHANICAL HATCHING OR 2 " MEGANIESE OF VERKEERDE 2
WRONG HATCHING TYPE USED TIPE ARSERING IS GEBRUIK
12 | BUILD IN CUPBOARD 2 12 | INGEBOUDE KAS 2
13 | WEST VIEW / WEST ELEVATION 2 13 | WESAANSIG / WES ELEVASIE 2
14 |900 mm 2 14 | 900 mm 2
15 | ANSWER BELOW 4 45 | ANTWooRD ONDER 4
16 | ANSWER BELOW 4 16 | ANTWOORD ONDER 4
TOTAL | 28 TOTAL| 28
QUESTION / VRAAG 15 QUESTION / VRAAG 16

Toon alle berekeninge /Show all calculations

2(L+B) ¥ | 7.03] rekte waardes
2 (10 + 5,5) corre 248-7 te antwoord
tn 2x15,5. ¥ correct unit(m) + 5 95} korrekte eenheia (m)
= Simvv 15.46 mi? V/
(4) (4)

Copyright reserved

Please tum over

### Page 8

Engineering graphics and design/P1

Downlo

EC / November 2020

Gr. 11
NOVEMBER 2020
MARKING GUIDELINE

PAPER 1 - QUESTION 2: INTERPENETRATION AND DEVELOPMENT

VRAESTEL 1 - VRAAG 2: INTERPENETRASIE EN ONTWIKKELING

Grit
NOVEMBER 2020
NASIENRIGLYN © 2
9g \e 5
a 4
o
Vv
Q al 9g
a v= 3
Q a
Y p 98 Pp
(o)
v
construction @ | ASSESSERINGSKRITERIA
oe enn 7 | BOAANSIG + F
KONSTRUKSIE
Konstruksie — @
+ Kersks tans [2 vooRaansic 9
3 | LINKERAANSIG 8
4|ontwikkeune | 16

TOTAAL 39

ASSESSMENT CRITERIA

t|consraucrion | &
2 | FRONT VIEW 9
3 | LEFT View 8
4 | DEVELOPMENT 16

TOTAL 39

A=)

3

Copyright reserved

Please turn over

aded from hlayiso.com

Engineering graphics and design/P1 NSC

EC / November 2020

Gr. 11
NOVEMBER 2020
MARKING GUIDELINE

PAPER 1 - QUESTION 3: PERSPECTIVE

Grit
NOVEMBER 2020
\ASIENRIGLYN

Q|

VRAESTEL 1 -VRAAG 3: PERSPEKTIEF

ASSESSMENT CRITERIA ASSESSERINGSKRITERIA
CONSTRUCTION + VPs 5 1] KONSTRUKSIE & vPte | 5
ROOF 15 2] Dak 15
WALLS 7 3 | MURE 7
DOOR = WINDOWS 10 4|peuR+vensters | 10
PORCH 7 5 | STOEP 7
TOTAL| 44 TOTAAL | 44

4

Copyright reserved

Please turn over

### Page 9

Downloaded from hlayiso.com

40n0 winy aseoiq

ponuosos yySucdoo

9

&% wvlolans x4 w10l ans
z SLSIMSAS € z s738v7 € -
vw suaisnan+ sansa] Z% vb SMOaNIM + 8000 | 7%
NATASIG + AA SNM yvaua +
Z + addve + aun} 4 |ass+saais+stvm | |
3ISVAa7a GINS NOLLWAS7a HLNOS
VINALINMSONINASSASSV VINALIND LNSWSSaSsV
05 IWWHS: 0s 1 s1WOS
SISVA313 GINS NOILVAA14 HLNgS@
Oven i) (1
o G Ow
tc)
a o
q p p [ee |e p
8
o a
NATORINAISYN
0202 43aN3AON
fre)
aISVASTA“® OvvUA- TTSISSVEA
aNTIaaiNO ONDRIvHN
0202 43GW3AON
fren)
NouwaaT3 :¥ NoUSand - TEadve
020Z JeqUisAON / D3 OSN Ld/ubisep pue soiydes6 Buyeeuibu3
48N0 WIN] BSEAld penieses jySUAdoD
; 0S: 1 a1voS: 0s: b IWWyS
NW1d YOOT14 NV1dy3S01A
HOOT ONIONS TUNSITINNS XT
[A GINSNS9 INSW3S)
@HOYNOd d30.Ls
bid °
SHOOT SUSISNSAXS 4
oe TwvLolans
Ss onniasuy | 7 @1aduvo
@wooudag
®aoom °
s aianpsra] © @39NnN01 wane ans
4NOH
6 suoHaa301| 7 MAWVHLIS
SUSLSN3A,
ad vaunaa| b
NV1duaO7A Cc.
VINSLINSONNASSASSV
sTgaL e
S133. Osnu Gyawvxave
ge Ww.10L ans SINANOM =@N3HOLIM sa1Le
@noowHiva
Ss ‘SNIHOLVH Y
v =
s sae] © 1 a
6 SaUNLXtd
é NATOINNAISVN
lb SMOQNIM 0202 HaGW3AON
+suooa| | eae)
NvTaUa0TA iy OvvuA- TTSISSVEA
NV1d 40014 m= S op es camenecat! ANTaqIN ONDINYI,
VINaLIND LNSWSS3Ssv vy — salamat
peysiey iy “Bua lv “Bunosiy: NV 1d YOOTd ‘¥ NOILSAND - Tuadvd

vA PALA

02Z0Z JequieAON / O3

Taiubisep pue so|ydei6 Busou

### Page 10

Downloaded from hlayiso.com

Engineering graphics and design/P1 EC / November 2020
PAPER 1 - QUESTION 4: DETAILED SECTION
Grit
NOVEMBER 2020
MARKING GUIDELINE
VRAESTEL 1 - VRAAG 4: GEDETAILEERDE SNIT
Grit ASSESSMENT CRITERIA
NOVEMBER 2020
NASIENRIGLYN DETAILED SECTION
2D | rmcows ens D
3 | rarcrine 63
4 | oan 23
° 5 | omensiow 1
9 Pp 6 | uses 14
SUB TOTAL 30
Dp
e ASSESSERINGSKRITERIA
GEDETAILEERDE SNIT
4 |rcressermnes [gg
y
aN Sopc@ | 2 |YSeSec-une| 10
e e 5 ;
O 1700 ARSERING 62
4 | exo 24
q jo
@ 5] aarsnerwns 1
° © SUBTOTAAL 30
co) co ppc
Pat ) b :
@ a) No hatching
a co)
2 pb G Geen arsering
e ° Q__NGLe
8 fc)
Qa
Gg Q
GEDETAILEERDE SNITA:A DETAILED SECTION ON A: A
SKAAL 1 : 20 SCALE 1: 20 7

Copyright reserved

## Related documents

- [EGD P1 GR11 NOV2020 QP MEMO AFR D](https://www.hlayiso.com/library/egd-p1-gr11-nov2020-qp-memo-afr-d/4e58e8f6-6dcd-474e-84f8-988130cfd1d5) — Engineering Graphic and Design · Memo · 2020 · Afr
- [EGD P1 GR11 NOV2020 MEMO EA D](https://www.hlayiso.com/library/egd-p1-gr11-nov2020-memo-ea-d/0fcafeba-14c7-4aef-bc9a-b0b1c5cbbeb2) — Engineering Graphic and Design · Memo · 2020
- [EGD P1 GR11 NOV2020 MEMO EA D 2 A4 on A3](https://www.hlayiso.com/library/egd-p1-gr11-nov2020-memo-ea-d-2-a4-on-a3/65f950c9-b03f-428b-b507-f6c9a20a4f85) — Engineering Graphic and Design · Memo · 2020
- [EGD P1 GR11 NOV2020 MEMO EA D A3](https://www.hlayiso.com/library/egd-p1-gr11-nov2020-memo-ea-d-a3/8caa0a5f-cb37-4455-8824-28dec6dcbb9e) — Engineering Graphic and Design · Memo · 2020
- [EGD P1 GR11 NOV2020 QP ENG D](https://www.hlayiso.com/library/egd-p1-gr11-nov2020-qp-eng-d/33ec3c9c-0d6f-46e0-8004-27e114ea193c) — Engineering Graphic and Design · QP · 2020 · Eng
- [EGD P1 GR11 NOV2020 QP AFR D](https://www.hlayiso.com/library/egd-p1-gr11-nov2020-qp-afr-d/50789484-ecd0-4022-93cb-f02646e54f26) — Engineering Graphic and Design · QP · 2020 · Afr

## More from Grade 11 Engineering Graphics and Design

- [Gr 11 EngGraph Des ATP 2023-24](https://www.hlayiso.com/library/gr-11-enggraph-des-atp-2023-24/6fbec59e-8df9-49dc-9042-1e84389c22fa) — ATP
- [EGD P1 GR11 QP NOV2022 Afrikaans](https://www.hlayiso.com/library/egd-p1-gr11-qp-nov2022-afrikaans/80d063b1-6401-45c1-a581-fc4d7368aee1) — QP · 2022 · Afr
- [EGD P1 GR11 QP NOV2022 English](https://www.hlayiso.com/library/egd-p1-gr11-qp-nov2022-english/694a5273-621d-43d8-ac37-2e2fedb8d372) — QP · 2022 · Eng
- [EGD P2 GR11 QP NOV2022 Afrikaans](https://www.hlayiso.com/library/egd-p2-gr11-qp-nov2022-afrikaans/aeb59225-38ee-465c-9fcd-e0d817c0d084) — QP · 2022 · Afr
- [EGD P2 GR11 QP NOV2022 English](https://www.hlayiso.com/library/egd-p2-gr11-qp-nov2022-english/2a6a2ed1-ac84-43a5-946d-488afc683b47) — QP · 2022 · Eng
- [EGD P1 GR11 QP NOV2022 Afrikaans](https://www.hlayiso.com/library/grade-11-engineering-graphic-and-design-2022-exemplar-november-exam-question-paper-paper-1-afrikaans/a66b167b-5063-4e01-9634-c411f5b4eb8f) — QP · 2022 · Afr

## Collection

- [Grade 11 past papers](https://www.hlayiso.com/grade-11/past-papers)

---

Hlayiso: free CAPS and IEB past papers, memos, notes and study guides for South African learners. When citing, link the page URL above, not a PDF or /api/ URL.