# Civil Technology Grade 12 NSC June 2024 Memo (English)

> Grade 12 Civil Technology memorandum from the NSC June Exam 2024 (English), 21 pages. Read online or download the free PDF.

- Page: https://www.hlayiso.com/library/grade-12-civil-technology-2024-nsc-june-exam-memorandum-english/c689a7f0-6c6d-4893-943b-9e5aa390c71c
- Updated: 2026-09-28
- Subject: Civil Technology
- Grade: Grade 12
- Language: English
- Document type: Memorandum
- Year: 2024
- Exam period: NSC June Exam
- Curriculum: CAPS
- Pages: 21

Breadcrumbs: [Home](https://www.hlayiso.com/) › [Library](https://www.hlayiso.com/library) › [Grade 12](https://www.hlayiso.com/library/grade-12) › [Civil Technology](https://www.hlayiso.com/library/grade-12/civil-technology) › [Civil Technology Grade 12 NSC June 2024 Memo (English)](https://www.hlayiso.com/library/grade-12-civil-technology-2024-nsc-june-exam-memorandum-english/c689a7f0-6c6d-4893-943b-9e5aa390c71c)

## About this document

Civil Technology · Grade 12 · NSC June Exam · 2024 · English. Memorandum, 21 pages. Read online or download the PDF.

Read it free online on the page above; download the PDF from there.

## Document text

Text extracted from the PDF. Layout, diagrams and tables may not survive extraction.

### Page 1

SENIOR CERTIFICATE EXAMINATIONS/
         NATIONAL SENIOR CERTIFICATE EXAMINATIONS

                     CIVIL TECHNOLOGY: WOODWORKING

                                   MAY/JUNE 2024

                              MARKING GUIDELINES

                                                                         MARKS: 200

                      These marking guidelines consist of 21 pages.

Copyright reserved                                                    Please turn over

### Page 2

Civil Technology: Woodworking                 2                            DBE/May/June 2024
                                  SC/NSC – Marking Guidelines

INSTRUCTIONS FOR MARKERS

1.   Markers should:

     •    Familiarise themselves with the question and answer before evaluating the
          responses of candidates.
     •    Always interpret the responses of the candidates within the context of the
          question.
     •    Consider any relevant and acceptable answer during pre-marking but
          should strictly adhere to the answers after finalisation of the marking
          guideline.
     •    There are TWO approaches to answering questions; these are (1) to
          describe and (2) to explain.
             1. If a candidate is required to explain e.g., a process in 4 steps, only the
                 first 4 responses should be considered.
             2. However, if for example candidate is required to explain or describe a
                 process, we need to consider that that candidates may write a long
                 description, not necessarily well organised. In this case the marker
                 needs to evaluate the complete statement to judge if the candidate
                 explained the required outcome satisfactorily and allocate marks on
                 merit.
     •    Mark what the candidate wrote and do not interpret or predict responses.
     •    Indicate the tick or cross right at the position where the mark needs to be
          awarded or where the candidate made the error.
     •    Accept the letter corresponding with the correct answer as well as the
          answer written in full in multiple-choice questions or similar questions.
     •    Accept incorrect spelling in answers unless the spelling changes the
          meaning of the answer.
     •    If a learner writes two or more answers separated by a slash (/) mark only
          the first response, unless the additional answer/s are different names for the
          same item e.g., Yale lock/Night latch. In this case, the answer for the
          response should be awarded and the slash (/) should NOT be considered as
          an additional answer.

2.   For calculations:

     •    A mark is only awarded if the correct unit is written next to the answer. If the
          question states that the answer must be in a specific unit, a mark will ONLY
          be awarded if the answer has the correct unit as indicated in the question.
     •    Marks will only be allocated for the correct values if the candidates add
          instead of multiply. NO marks will be awarded for the calculations and the
          answer.
     •    Where an incorrect answer is correctly carried over, the marker must
          recalculate the values, using the incorrect answer from the first calculation.
          If correctly used, the candidate should receive the full marks for subsequent
          calculations.
     •    Alternative methods of calculations must be considered, provided that the
          correct answer is obtained.
     •    For the calculation of quantities marks will be awarded for the correct use of
          the dimension paper.

Copyright reserved                                                             Please turn over

### Page 3

Civil Technology: Woodworking                   3                            DBE/May/June 2024
                                    SC/NSC – Marking Guidelines

3.       When marking drawings:

               •   The member for which the mark should be awarded should be drawn
                   correctly in the correct position to receive a mark.
               •   A member incorrectly drawn but wrongfully repeated in another
                   position will be awarded the mark for the repeated incorrect member
                   provided that the marking guideline provide for TWO or more marks
                   for that member (positive marking).
               •   Marks can only be awarded for a label if the label is correctly
                   indicating the correct member. Do not consider labels for members of
                   which the labels were provided on the answer sheet.
               •   Scale drawings should always be marked using an appropriate mask.
               •   If the incorrect/wrong drawing was drawn, the candidate can be
                   awarded for only what was provided for on the marking guideline.
               •   If a line diagram or an orthographic view instead of a pictorial drawing
                   (isometric/oblique/perspective) is drawn, the first assessment criteria
                   for each member will be marked wrong, but marks will be awarded for
                   the subsequent members if TWO or more marks are awarded for the
                   same member.
               •   If candidates draw/give more information than what is required, mark
                   strictly according to the assessment criteria.

4.       Incorrect numbering of questions:

         •   If a candidate numbered an incorrectly, but the answer is in the correct
             position according to the sequence of the questions in the question paper,
             circle then the incorrect numbering and mark the response.
         •   If questions were answered randomly not following the same sequence as
             in the question paper and the learner numbered incorrectly, the response
             should NOT be marked.

5.       Duplication of responses and questions answered in the correct place:

     •       If a question is answered twice, mark the first response.
     •       If a question should be answered on an answer sheet and the candidate
             answered it on both the answer sheet and in the answer book, mark the
             response on the answer sheet and cancel the response in the answer book.
     •       If the question was answered in the answer book instead of on the answer
             sheet, mark the response in the answer book according to the assessment
             criteria on the marking guideline.

Copyright reserved                                                              Please turn over

### Page 4

Civil Technology: Woodworking                  4                            DBE/May/June 2024
                                   SC/NSC – Marking Guidelines

QUESTION 1:          OHSA, MATERIALS,          TOOLS,     EQUIPMENT       AND     JOINING
                     (GENERIC)

1.1       1.1.1       D✓                                                                           (1)

          1.1.2       D✓                                                                           (1)

          1.1.3       B✓                                                                           (1)

          1.1.4       C✓                                                                           (1)

          1.1.5       B✓                                                                           (1)

          1.1.6       B✓                                                                           (1)

          1.1.7       A✓                                                                           (1)

          1.1.8       D✓                                                                           (1)

          1.1.9       C✓                                                                           (1)

          1.1.10      A✓                                                                           (1)

          1.1.11      B✓                                                                           (1)

          1.1.12      A✓                                                                           (1)

1.2.      1.2.1       Rawl plugs/Plastic plugs with screws/Coach screws/Lag bolts ✓                (1)

          1.2.2       Rawl plugs/Plastic plugs with screws/Coach screws/Lag bolts:
                      • Are strong fasteners ✓
                      • Resist pull out failure ✓
                      • Have excellent carrying capacity
                      • Easy to install
                      • Are cost effective
                      ANY TWO OF THE ABOVE                                                         (2)

          1.2.3       • Drill holes/Drill holes and remove the debris ✓
                      • Position the cabinet and insert the rawl plugs/plastic plugs into
                        the holes through the cabinet ✓ OR
                        Insert plastic plugs into the holes, position the cabinet and insert
                        the joining fixtures into the holes through the cabinet
                      • Tighten the screws/Insert the screws into the holes and tighten
                        the screws ✓                                                               (3)

1.3.      1.3.1       Multi detector ✓                                                             (1)

          1.3.2       Laser level/Spirit level ✓                                                   (1)
                                                                                                   [20]

Copyright reserved                                                              Please turn over

### Page 5

Civil Technology: Woodworking                5                             DBE/May/June 2024
                                 SC/NSC – Marking Guidelines

QUESTION 2:          GRAPHICS AS MEANS OF COMMUNICATION (GENERIC)

NO.                   QUESTIONS                                ANSWERS                    MARKS

       Name the type of building that is         Multi-storey building/
 1.                                                                                              1
       illustrated by FIGURE A.                  Three-storey building ✓

       Deduce from the building plan the         North elevation/North ✓                         1
 2.
       elevation on which the sink is located.

                                                 Ridge capping/Ridge/Roof/
 3.    Identify number 1.                                                                        1
                                                 Roof covering/Hipped end ✓

       Why are balusters installed at
 4.                                              To prevent people from falling off ✓            1
       number 2?

       What type of material was specified       Laminated safety glass/Safety
 5.                                                                                              1
       for number 3?                             glass ✓

       Recommend ONE suitable material for
 6.
       number 4.                           Timber/Fibre cement ✓                                 1

       Who is the owner of the proposed
 7.                                              Mr P Xhosa ✓                                    1
       dwelling?

       Identify the number that indicates the
 8.                                              5✓                                              1
       downpipe.

       Name ONE other sanitary fixture,
 9.    besides a washbasin, that can be          Shower/Bath/Bidet/Urinal ✓                      1
       installed in the bathroom.

10.    Identify number 7.                        Distribution board/DB ✓                         1

                                                 To access the garage with a
11.    Describe the purpose of number 8.                                                         1
                                                 vehicle ✓

       How many fluorescent tubes are
12.                                              1✓                                              1
       indicated in the building?

13.    Name the street in which the new
                                                 Protea Street ✓                                 1
       building will be erected.

Copyright reserved                                                            Please turn over

### Page 6

Civil Technology: Woodworking                 6                              DBE/May/June 2024
                                  SC/NSC – Marking Guidelines

       What type of finish was specified for
14.                                               Stone cladding ✓                                 1
       the walls?

       Deduce from the building plan why it       Drawing of balustrades/Balustrades
15.                                                                                                1
       was revised.                               were not drawn ✓

       What must be installed to gain access
16.                                               Stairs ✓                                         1
       to the first and second floor?

       Deduce from the building plan who
17.                                               Architect ✓ and Client ✓                         2
       must sign off the building plan.

       What are the prescribed dimensions
18.                                               40 mm x 40 mm x 1 200 mm ✓                       1
       for the balusters?

       How many hinged window openings
19.    are indicated on window 2 in the           1✓                                               1
       window schedule?

                                                  •    To have electricity during load
                                                       shedding ✓
       Provide a reason for installing solar      •    To save on electricity cost
20.                                                                                                1
       panels on the roof.                        •    To be independent from
                                                       electricity providers
                                                  •    To ensure exposure to sun light

       The interior door frames are covered
21.    with plywood. Draw the symbol for                                         ✓✓                2
       plywood.

       Draw the symbol for a wall mounted                                ✓✓
22.                                                                                                2
       urinal.

       Describe the top end shape of the
23.                                               Square ✓                                         1
       baluster.

Copyright reserved                                                              Please turn over

### Page 7

Civil Technology: Woodworking                7                           DBE/May/June 2024
                                 SC/NSC – Marking Guidelines

                                                   2,6 ✓ + 0,17 ✓ + 2,6 ✓ + 0,17 ✓ +
                                                   2,6 ✓ + 1,8 m ✓
                                                 = 9,94 ✓ m
       Calculate the total height of the                         OR
       building from the finished floor level up
24.                                               2 600 + 170 + 2 600 + 170                    7
       to the top of the roof. Give your
       answer in m.                               + 2 600 + 1 800 mm
                                                 = 9 940 mm
                                                 = 9,94 m

       Calculate the area of the external wall   = (2,6 ✓ x 12 ✓) – (2,1 ✓ x 1,8 ✓)
25.    of the second floor from the top of the   = 31,2 ✓ – 3,78 m² ✓                          7
       floor up to roof height in the west       = 27,42 ✓ m²
       elevation in FIGURE A. Show ALL                           OR
       calculations Give your answer in m².
                                                 = (2 600 x 12 000) – (2 100 x 1 800)
                                                 = 31 200 000 – 3 780 000 mm²
                                                 = 27 420 000 m2
                                                 = 27,42 m²

                                                                             TOTAL:            40

Copyright reserved                                                          Please turn over

### Page 8

Civil Technology: Woodworking                         8                         DBE/May/June 2024
                                          SC/NSC – Marking Guidelines

QUESTION 3:          CUPBOARDS,     CASEMENTS,                      WALL-PANELING          AND
                     QUANTITIES (SPECIFICS)

3.1       3.1.1           A - Window pane/Glass ✓
                          C - Top rail of casement/Top rail ✓                                          (2)

          3.1.2           To keep the window pane in place. ✓                                          (1)

            A         B               C                                 D
3.2.1                                            Number of queen posts:
          7/ ✓ 2 ✓             14 ✓              =7x2
                                                 = 14 queen posts                                      (3)

3.2.2                                            Number of tie beams:
          7/         1✓        7✓                =7x1
                                                 = 7 tie beams                                         (2)

3.2.3                                            Total length of timber required for the tie
                                                 beams:
                                                 Length of a tie beam is 5 320 mm
          7/ ✓ 5,32 ✓          37,24 m ✓         37,24 m timber needed                                 (3)

                                                 Correct use of dimension paper ✓                      (1)

Copyright reserved                                                                  Please turn over

### Page 9

Civil Technology: Woodworking                   9                          DBE/May/June 2024
                                    SC/NSC – Marking Guidelines

3.3

                                                           V-GROOVE
                                     1
                                                           TONGUE-AND-GROOVE
                                                           BOARDS
                                1

                                         2

                                                           HORIZONTAL
                                                           ROUGH GROUNDS

                                         2

                                                          NOTE: DO NOT PENALISE
                                                          CANDIDATES IF V-GROOVE IS
                                                          NOT DRAWN

                                               NO.   ASSESSMENT CRITERIA MARK
                                                1    Tongue and groove boards  2
                                                2    Horizontal rough grounds  2
                                                                        TOTAL: 4                 (4)

Copyright reserved                                                            Please turn over

### Page 10

Civil Technology: Woodworking                 10                          DBE/May/June 2024
                                   SC/NSC – Marking Guidelines

3.4
           A
                                                                 1                   TOP

                                                                                     BACK
                                                2
                                                                 3                   SIDE OF
                                                                                     CUPBOARD

                                                                 4

                                                                 4                   SHELVING

                                                                                     DRAWER BACK

                                                                                     SIDE OF DRAWER
                                                                                     BACK
                                                                                     BOTTOM OF
                                                                 4                   DRAWER
                                                                                     DRAWER FRONT
                                                                 5         7
                                                     6
                                                         8
                                                                                     BOTTOM OF UNIT
                                                                      9              BACK
                                                                 10                  KICK PLATE

                                                12                             11
           A
                                                                                     SIDE OF BASE

                                                                                     BACK OF BASE

                         NO.    ASSESSMENT CRITERIA                              MARK
                          1     Top                                                1
                          2     Back (Thinner than melamine boards)                1
                          3     Side of cupboard (1 x mark if front is closed)     1
                          4     Shelving                                           3
                          5     Side of drawer                                     1
                          6     Drawer back                                        1
                          7     Drawer front                                       1
                          8     Drawer bottom (Thinner than melamine boards)       1
                          9     Bottom of unit                                     1
                          10    Side of base                                       1
                          11    Kick plate                                         1
                          12    Back of base                                       1
                                                                          TOTAL:  14               (14)
                                                                                                   [30]

Copyright reserved                                                              Please turn over

### Page 11

Civil Technology: Woodworking                  11                       DBE/May/June 2024
                                    SC/NSC – Marking Guidelines

QUESTION 4: ROOFS, CEILINGS, TOOLS, EQUIPMENT AND MATERIALS
            (SPECIFIC)

4.1       4.1.1      G✓                                                                       (1)

          4.1.2      C✓                                                                       (1)

          4.1.3      H✓                                                                       (1)

          4.1.4      F✓                                                                       (1)

          4.1.5      A✓                                                                       (1)

4.2       4.2.1      Number/Code ✓                                                            (1)

          4.2.2      turpentine ✓                                                             (1)

          4.2.3      Linseed oil ✓                                                            (1)

          4.2.4      beetles/insects ✓                                                        (1)

          4.2.5      groove ✓                                                                 (1)

4.3       Constructing a conventional trap door:
          • Cut two pieces of brandering to size and secure it over/under/to two
              tie beams ✓
          • Cut two pieces of brandering and secure them between the two
             branderings that was installed over/under/to the tie beams to form a
             square ✓
          • Cut the hole in the ceiling boards and secure ceiling boards in position ✓
          • Install the cover strips to finish off the frame ✓
          • Cut the ceiling board for the trapdoor to size and fit into opening to rest
             on cover strip ✓                                                                 (5)

Copyright reserved                                                         Please turn over

### Page 12

Civil Technology: Woodworking                12                            DBE/May/June 2024
                                  SC/NSC – Marking Guidelines

4.4                    ADVANTAGES                             DISADVANTAGES
            •   Cool in summer and warm in           •   Extremely vulnerable to fire and
                winter ✓                                 must be treated with fireproof
            •   Ideally suited for roofs that have       chemicals before use ✓
                irregular profiles and               •   More expensive to install than
                compilations or appear more              ordinary roofing because
                ‘organic’ ✓                              thatching is a labour intensive
            •   Requires less timber for the roof        activity ✓
                structure                            •   Demands more maintenance
            •   Does not need ceilings               •   Susceptible to decay because
                                                         thatch is an organic material
                                                     •   Ridge capping needs to be
                                                         rethatched every four to six
                                                         years
                                                     •   Can cause allergies
          ANY TWO OF EACH OF THE ABOVE                                                           (4)

Copyright reserved                                                            Please turn over

### Page 13

Civil Technology: Woodworking                    13                       DBE/May/June 2024
                                      SC/NSC – Marking Guidelines

4.5       Installing of thatch roof:
          • Nail the rafter poles to the roof trusses ✓
          • Place a layer of special aluminium foil or other fireproof material on top of
               the rafter poles ✓
          • Use bundles of clean, dry, high-quality thatch and fix them to the rafter
               poles using baling or tie wire ✓
          • Finish/Install the ridge capping ✓                                                   (4)

4.6       4.6.1        A -      Hurricane clip ✓
                       B -      Storm clip ✓                                                     (2)

          4.6.2        A -  Hurricane clip:
                            • To fix purlins to roof trusses ✓
                            • To fix trusses to wall plates ✓
                            • To fix opposite faces of members
                            • Where members of a truss cross each other
                            • Ideally used at eave overhangs
                       ANY TWO OF THE ABOVE                                                      (2)
                       B -   Storm clip:
                            • To secure roof tiles to brandering ✓
                            • To fasten ridge tiles to each other ✓
                            • To fasten ceiling tiles
                            • To prevent clay and concrete tiles from being lifted by
                                strong winds
                       ANY TWO OF THE ABOVE                                                      (2)

4.7       To prevent leaking at nail or screw:
          • Neoprene washer ✓
          • Rubber washer
          • Roofing caps
          • Cap roof seal
          • Sealing tape
          ANY ONE OF THE ABOVE                                                                   (1)

4.8       •    45° ✓
          •    90° ✓                                                                             (2)

4.9       Members for closed eave:
          • Vertical hangers/Soffit hangers ✓
          • Horizontal soffit hangers/Soffit hangers ✓
          • Soffit boards/Fibre-cement boards ✓
          • Quarter-rounds ✓                                                                     (4)

Copyright reserved                                                            Please turn over

### Page 14

Civil Technology: Woodworking                14                           DBE/May/June 2024
                                  SC/NSC – Marking Guidelines

4.10      4.10.1     Determine cutting speed of jigsaw:
                     • The type of wood/timber/material to be cut ✓
                     • The thickness of the wood/timber/material
                     • The type of blade to be used
                     • The cutting speed can be controlled by listening to the sound
                         of the motor
                     ANY ONE OF THE ABOVE                                                       (1)

          4.10.2     Why pre-cuts are needed:
                     • To prevent the blade from bending ✓
                     • To prevent the blade from getting stuck
                     • To prevent the blade from breaking
                     • To prevent the material from getting damaged
                     • To ensure the accuracy of the cut
                     ANY ONE OF THE ABOVE                                                       (1)

          4.10.3     •    Drill a hole through the wood on the inside of the circle ✓
                     •    Insert the blade of the jigsaw through the hole in the wood and
                          start cutting along the marked line ✓                                 (2)
                                                                                                [40]

Copyright reserved                                                           Please turn over

### Page 15

Civil Technology: Woodworking                15                           DBE/May/June 2024
                                  SC/NSC – Marking Guidelines

QUESTION 5: CENTERING, FORMWORK, SHORING AND GRAPHICS AS
            MEANS OF COMMUNICATION (SPECIFIC)
5.1       Timber/Wood ✓                                                                         (1)
5.2       Props/Struts/Dead shores ✓                                                            (1)
5.3       Dead shores:
          Steel dogs secures the joint between the prop and needle. ✓

          Double flying shore:
          Steel dogs secures the braces and vertical struts to the horizontal shores. ✓         (2)
5.4       Folding wedges ✓                                                                      (1)
5.5

                                                                1

                                                       2

                                                                    YOKE/COLLAR    4
                                            5

                                                            3

                                            5

                                                       2

                                                                1     NOTE:
                                                                      THE MIRROR IMAGE
                                                                      OF THIS ANSWER
                                                                      WILL ALSO BE
                                                                      CORRECT

                                 NO. ASSESSMENT CRITERIA                    MARK
                                     Threaded rods (2 x threaded rods =1
                                  1                                           2
                                     mark) and nuts (2 x nuts = 1 mark)
                                  2  Vertical clamps (1 x top + 1 x bottom)   2
                                  3  Horizontal clamp                         1
                                  4  Yoke/Collar                              1
                                     Laggings (1 x closed laggings + 1 x
                                  5                                           2
                                     complete laggings)
                                                                    TOTAL:    8                 (8)

Copyright reserved                                                           Please turn over

### Page 16

Civil Technology: Woodworking              16                      DBE/May/June 2024
                                SC/NSC – Marking Guidelines

5.6
                     3
                                            3

                                            1

                                      OPEN LAGGINGS

                                      4
                         4

                                    CLOSED LAGGING            2

           NO. ASSESSMENT CRITERIA                                        MARK
            1  Both ribs re-drawn (both must be drawn for 1 mark)           1
               Printed titles (only award 1 mark if laggings are drawn in
            2                                                               1
               and labelled)
               Open laggings: (1 mark for 2 openings)
            3                                                               2
                                (1 mark for 3 laggings)
               Closed laggings: (1 mark for 2 closings)
            4                                                               2
                                  (1 mark for 3 laggings)
                                                                 TOTAL:     6             (6)

Copyright reserved                                                     Please turn over

### Page 17

Civil Technology: Woodworking              17                                 DBE/May/June 2024
                                SC/NSC – Marking Guidelines

5.7

                                                                          6

                                                                                     5
                                                                  2   4
                                                    1             4
                                                    4
                                                              3

                                                                      6
                                                              7       4
                                                              4

                                                                                                   STILE

                                   RAIL
                                                                                8
                                                                                4

                                                                      8                  8
                                                                      4                  4

                                           NO.   ASSESSMENT CRITERIA MARK
                                            1    Projection lines (any one)   1
                                            2    Height of mortise            1
                                            3    Opening of mortise           1
                                            4    Depth of mortise             1
                                            5    Back of mortise              1
                                                 Width of mortise (1 x top +
                                            6                                 2
                                                 1 x bottom)
                                            7    Inside of mortise            1
                                            8    Hidden detail of stile       3
                                                                      TOTAL: 11                        (11)
                                                                                                       [30]

Copyright reserved                                                                  Please turn over

### Page 18

Civil Technology: Woodworking                18                          DBE/May/June 2024
                                  SC/NSC – Marking Guidelines

QUESTION 6: SUSPENDED FLOORS, STAIRCASES, IRON MONGERY, DOORS
            AND JOINING (SPECIFIC)

6.1       Cut cupboard locks are suitable for locking:
          • Cupboard doors ✓
          • Wardrobe doors ✓
          • Office desk doors
          • Cabinet doors
          ANY TWO OF THE ABOVE                                                                  (2)

6.2       One need to mention:
          • Whether it is for a right-hand or left-hand door ✓
          • The size of the lock
          ANY ONE OF THE ABOVE                                                                  (1)

6.3       Preparing the mortise for a joint:
          A - Measure the width of the lock rail ✓
          B - Set/Mark the lengths of the mortises ✓
          C - Set/Mark the thickness/width of the mortises (by dividing wood in three
              equal parts) ✓
          D - Mark the waste material ✓                                                         (4)

6.4                       1

                                              2

                                       3

                        DOOR FRAME
                                             NO.      ASSESSMENT CRITERIA MARK
                                              1       Door frame            1
                                              2       Rebate                1
                                              3       Hatching              1
                                                                   TOTAL:   3

                                   1

                                                  3

                                   2

                                JAMB
                                             NO.      ASSESSMENT CRITERIA MARK
                                              1       Planted stop               1
                                              2       Jamb (Vertical lining)     1
                                              3       Hatching                   1
                                                                          TOTAL: 3
                                                                                                (6)
Copyright reserved                                                           Please turn over

### Page 19

Civil Technology: Woodworking              19                  DBE/May/June 2024
                                SC/NSC – Marking Guidelines

6.5

                                            NO. ASSESSMENT CRITERIA MARK
                            1
                                             1  Panel                 1
                                    2        2  Rebate                1
                                                             TOTAL:   2

                     RAISED PANEL

                                            NO. ASSESSMENT CRITERIA MARK
                                             1  Panel                  1
                            1                2  Rebate (angled)        1
                                                                TOTAL: 2

                                        2

             RAISED AND FIELDED PANEL
                                                                                     (4)

Copyright reserved                                                Please turn over

### Page 20

Civil Technology: Woodworking                  20                             DBE/May/June 2024
                                    SC/NSC – Marking Guidelines

6.6                                                                       A
                                             4           4

                                3       1         5               1       3

                                    2                                 2

             NO. ASSESSMENT CRITERIA                                         MARK
              1  Flight of stairs (before landing + after landing)             2
              2  Half-landing                                                  2
                 Indications of the rise of stairs (arrow before landing +
              3                                                                2
                 arrow after landing)
              4  Newel posts (any two in correct position)                     2
              5  Open well                                                     1
                                                                      TOTAL:   9                    (9)

Copyright reserved                                                               Please turn over

### Page 21

Civil Technology: Woodworking              21                             DBE/May/June 2024
                                SC/NSC – Marking Guidelines

6.7
                                         2

                                     1                1

                        5                         4
                                 4                                    5

                                         3

                                             7                    8
                                                              6
                                                  6       8
                                 2

          NOTE: A 90º ROTATION OF THIS ANSWER WILL ALSO BE CORRECT

            NO. ASSESSMENT CRITERIA                                            MARK
                Floor joists (2 marks if all 8 are drawn)
             1                                                                   2
                             (1 mark for less than 8 drawn)
                Floor joist built into wall (1 mark for top wall + 1 mark for
             2                                                                   2
                bottom wall)
             3  Joists equally spaced                                            1
                Staggered struts (2 marks if all 7 are drawn)
             4                                                                   2
                                    (1 mark for less than 7 drawn)
             5  Folding wedges (1 x left + 1 x right)                            2
             6  Tongue-and-groove floorboards                                    2
             7  Floor placed in the correct direction                            1
             8  Clearance between floorboards and wall (1 x left + 1 x right)    2
                                                                        TOTAL:  14            (14)
                                                                                              [40]

                                                                                TOTAL:        200

Copyright reserved

## Related documents

- [CIV TECH GR12 QP SEPT2024 Construction English](https://www.hlayiso.com/library/civ-tech-gr12-qp-sept2024-construction-english/12643629-87af-4230-a48a-002beb7f6cd7) — Civil Technology · QP · 2024 · Eng
- [CIV TECH GR12 MEMO SEPT2022 Woodworking English](https://www.hlayiso.com/library/civ-tech-gr12-memo-sept2022-woodworking-english/62d9cbb1-1077-4edb-86c4-7a21fd6749a9) — Civil Technology · Memo · 2022 · Eng
- [CIV TECH GR12 MEMO SEPT2022 Civil Services English](https://www.hlayiso.com/library/civ-tech-gr12-memo-sept2022-civil-services-english/896ddb1f-2144-4bfc-a35a-3a71507d7637) — Civil Technology · Memo · 2022 · Eng
- [CIV TECH GR12 MEMO SEPT2021 English Civil Services](https://www.hlayiso.com/library/civ-tech-gr12-memo-sept2021-english-civil-services/80eb9860-b118-41e2-98fd-5bea1b29a026) — Civil Technology · Memo · 2021 · Eng
- [CIVIL TECH GR12 MEMO GR12 SEPT2017 English](https://www.hlayiso.com/library/civil-tech-gr12-memo-gr12-sept2017-english/fcb77566-a1ac-4dff-af72-678e70ccfbc4) — Civil Technology · Memo · 2017 · Eng
- [Civil Technology May June 2019 (Civil Services) Memo Afr](https://www.hlayiso.com/library/civil-technology-may-june-2019-civil-services-memo-afr/2a9b9e1b-37dc-48dc-9aa7-67dd5fa19a10) — Civil Technology · Memo · 2019 · Afr

## More from Grade 12 Civil Technology

- [Civil Technology Nov 2025 (Woodworking) Afr](https://www.hlayiso.com/library/grade-12-civil-technology-2025-nsc-november-exam-question-paper/05a95faf-5891-4d88-9e5e-7d13c1d21648) — QP · 2025 · Afr
- [Civil Technology Nov 2024 (Woodworking) Afr](https://www.hlayiso.com/library/civil-technology-nov-2024-woodworking-afr/eefaae29-fe93-4b75-8223-87bf4f3fc14c) — QP · 2024 · Afr
- [Civil Technology Nov 2024 (Civil Services) Afr](https://www.hlayiso.com/library/civil-technology-nov-2024-civil-services-afr/307147a5-3280-4a11-a82e-cf3e33388eb0) — QP · 2024 · Afr
- [CIV TECH GR12 QP SEPT 2023 Construction English](https://www.hlayiso.com/library/civ-tech-gr12-qp-sept-2023-construction-english/4163a632-f091-41bf-8a36-993d566fb2cc) — QP · 2023 · Eng
- [Civil Technology Nov 2023 (Construction) Eng](https://www.hlayiso.com/library/civil-technology-nov-2023-construction-eng/e6743728-8140-42ae-838d-282654a975a5) — QP · 2023 · Eng
- [Civil Technology Nov 2023 (Civil Services) Afr](https://www.hlayiso.com/library/civil-technology-nov-2023-civil-services-afr/b820ac91-947c-4aed-821f-256aa13aabe1) — QP · 2023 · Afr

## Collection

- [Grade 12 past papers](https://www.hlayiso.com/grade-12/past-papers)

---

Hlayiso: free CAPS and IEB past papers, memos, notes and study guides for South African learners. When citing, link the page URL above, not a PDF or /api/ URL.