# Civil Technology Grade 12 NSC June 2024 Memo (English)

> Grade 12 Civil Technology memorandum from the NSC June Exam 2024 (English), 20 pages. Read online or download the free PDF.

- Page: https://www.hlayiso.com/library/grade-12-civil-technology-2024-nsc-june-exam-memorandum-english/f1e46840-07a9-4691-9233-71e8e0e0bbde
- Updated: 2026-09-28
- Subject: Civil Technology
- Grade: Grade 12
- Language: English
- Document type: Memorandum
- Year: 2024
- Exam period: NSC June Exam
- Curriculum: CAPS
- Pages: 20

Breadcrumbs: [Home](https://www.hlayiso.com/) › [Library](https://www.hlayiso.com/library) › [Grade 12](https://www.hlayiso.com/library/grade-12) › [Civil Technology](https://www.hlayiso.com/library/grade-12/civil-technology) › [Civil Technology Grade 12 NSC June 2024 Memo (English)](https://www.hlayiso.com/library/grade-12-civil-technology-2024-nsc-june-exam-memorandum-english/f1e46840-07a9-4691-9233-71e8e0e0bbde)

## About this document

Civil Technology · Grade 12 · NSC June Exam · 2024 · English. Memorandum, 20 pages. Read online or download the PDF.

Read it free online on the page above; download the PDF from there.

## Document text

Text extracted from the PDF. Layout, diagrams and tables may not survive extraction.

### Page 1

SENIOR CERTIFICATE EXAMINATIONS/
         NATIONAL SENIOR CERTIFICATE EXAMINATIONS

                      CIVIL TECHNOLOGY: CONSTRUCTION

                                         2023

                               MARKING GUIDELINES

                                                                     MARKS: 200

                     These marking guidelines consist of 20 pages.

Copyright reserved                                                   Please turn over

### Page 2

Civil Technology: Construction                 2                                       DBE/2023
                                   SC/NSC – Marking Guidelines

INSTRUCTIONS FOR THE MARKERS

1.       Markers should:

             Familiarise themselves with the question and answer before evaluating
              responses from candidates.
             Always interpret the responses of the candidates within the context of the
              question.
             Consider any relevant and acceptable answer during pre-marking but
              should strictly adhere to the answers after finalisation of the marking
              guideline.
             There are TWO approaches to answering questions; these are (1) to
              explain and (2) to describe.
              1. If a candidate is required to explain a process in a specific number of
                 steps, only the first required number of responses should be considered.
              2. However, if for example a candidate is required to explain or describe a
                 process, we need to consider that candidates may write a long
                 description, not necessarily well organised. In this case the marker needs
                 to evaluate the complete statement to judge if the candidate explained
                 the required outcome satisfactorily and allocate marks on merit.

             Mark what the candidate wrote and do not interpret or predict responses.
             Indicate the tick or cross right at the position where the mark needs to be
              awarded or where the candidate made the error.
             Accept the letter corresponding with the correct answer as well as the
              answer written in full in multiple-choice or similar questions.
             Accept incorrect spelling in answers unless the spelling changes the
              meaning of the answer.
             If a learner writes two or more answers separated by a slash (/) mark only
              the first response, unless the additional answer/s are different names for the
              same item e.g., Yale lock/Night latch. In this case, the answer for the
              response should be awarded and the slash (/) should NOT be considered
              as an additional answer.

2.       For calculations:

             A mark is only awarded if the correct unit is written next to the answer. If the
              question states that the answer must be in a specific unit, a mark will ONLY
              be awarded if the answer has the correct unit as indicated in the question.
             Marks will only be allocated for the correct values if the candidates add are
              instead of multiply. NO marks will be awarded for the calculations and the
              answer.

Copyright reserved                                                                Please turn over

### Page 3

Civil Technology: Construction                3                                       DBE/2023
                                  SC/NSC – Marking Guidelines

             Where an incorrect answer is correctly carried over, the marker must
              recalculate the values, using the incorrect answer from the first calculation.
              If correctly used, the candidate should receive the full marks for subsequent
              calculations.
             Alternative methods of calculations must be considered, provided that the
              correct answer is obtained.
             For the calculation of quantities marks will be awarded for the correct use of
              the dimension paper.

3.       When marking drawings:

             The member for which the mark should be awarded must be drawn
              correctly in the correct position to receive a mark.
             A member incorrectly drawn but wrongfully repeated in another position will
              be awarded the mark for the repeated incorrect member provided that the
              marking guideline provide for TWO or more marks for that member (positive
              marking).
             Marks can only be awarded for a label if the label is correctly indicating the
              correct member that was drawn. Do not consider labels for members that
              were provided with labels on the answer sheet.
             Scale drawings should always be marked using an appropriate mask.
             If the incorrect/wrong drawing was drawn, the candidate can be awarded for
              only what was provided for on the marking guideline.
             If a two-dimensional drawing is required and a line
              diagram/pictorial/isometric drawing is drawn, members will be marked
              according to the assessment criteria and no marks will be awarded for the
              correctness of the drawing.
             If candidates draw/give more information than what is required, mark strictly
              according to the assessment criteria.
             The marks for the correctness of the drawing will only be awarded if the
              entire drawing with all members/parts is correctly drawn.

4.       Incorrect numbering of questions:

             If a candidate numbered an answer incorrectly, but the answer is in the
              correct position according to the sequence of the questions in the question
              paper, circle the incorrect numbering and mark the response.
             If questions were answered randomly not following the same sequence as
              in the question paper and the learner numbered incorrectly, the response
              should NOT be marked.

5.       Duplication of responses and questions answered in the incorrect place:

             If a question is answered twice, mark the first response.
             If a question should be answered on an answer sheet and the candidate
              answered it on both the answer sheet and in the answer book, mark the
              response on the answer sheet and cancel the response in the answer book.
             If the question was answered in the answer book instead of on the answer
              sheet, mark the response in the answer book according to the assessment
              criteria on the marking guideline.

Copyright reserved                                                             Please turn over

### Page 4

Civil Technology: Construction                  4                                    DBE/2023
                                    SC/NSC – Marking Guidelines

QUESTION 1:          OHSA, MATERIALS,          TOOLS,     EQUIPMENT     AND       JOINING
                     (GENERIC)

1.1       1.1.1        Safety features omitted from the scaffold are:
                         Baseplate 
                         Soleplate 
                         Kickboard/Toe-board 
                         Guardrails
                       ANY THREE OF THE ABOVE                                                    (3)

          1.1.2        Platform used as displayed:
                         Vertical standards will sink into the ground 
                         Can cause the scaffold/platform to tilt over 
                         Can cause injuries to workers
                         Tools may fall from the scaffold on the workers below
                         Workers can fall from the scaffold
                       ANY TWO OF THE ABOVE                                                      (2)

1.2       1.2.1        Rust                                                                     (1)

          1.2.2        Zinc                                                                     (1)

          1.2.3        Keeping it moist                                                         (1)

          1.2.4        Metal                                                                    (1)

          1.2.5        Plastic                                                                  (1)

1.3       Height of guardrails (900 – 1 000 mm):
            To keep workers safe on the platform 
            To prevent workers from falling over the guard rails
          ANY ONE OF THE ABOVE                                                                   (1)

1.4       Precautions when storing a ladder:
            Store a ladder in a dry place after use 
            Never store material and equipment on a ladder
            Hang the ladder vertically/horizontally on wall brackets
            The ladder should be stored within easy reach
          ANY ONE OF THE ABOVE                                                                   (1)

Copyright reserved                                                            Please turn over

### Page 5

Civil Technology: Construction                  5                                   DBE/2023
                                    SC/NSC – Marking Guidelines

1.5       The operator must check if:
            The builders hoist is not overloaded 
            The gates are shut when the device is being used
            Overhead protection is provided
            Material is stacked firmly and correctly
            Emergency brakes are installed/operational
            Safety measures are displayed inside the cage
          ANY ONE OF THE ABOVE                                                                  (1)

1.6       Any person/Fire fighters will be able to identify exactly what specific type of
          fire extinguisher to use in case of a fire.                                          (1)

1.7       A – Hexagonal nut 
          B – Square nut/Four sided nut 
          C – Wing nut/Butterfly nut 
          D – Domed top/Domed nut/Dome nut/Acorn nut/Cap nut                                   (4)

1.8       1.8.1        Tool that can be used:
                         Laser level 
                         Spirit level with straight edge
                         Transparent pipe level
                         Dumpy level
                       ANY ONE OF THE ABOVE                                                     (1)

          1.8.2        Tool that can be used:
                           Dumpy level 
                           Laser level
                       ANY ONE OF THE ABOVE                                                     (1)
                                                                                                [20]

Copyright reserved                                                           Please turn over

### Page 6

Civil Technology: Construction                6                                    DBE/2023
                                  SC/NSC – Marking Guidelines

QUESTION 2: GRAPHICS AS MEANS OF COMMUNICATION (GENERIC)
ANSWER SHEET 2.

NO.                   QUESTIONS                                 ANSWERS                    MARK
                                                 First floor: A/FIGURE A 
                                                  Garage in FIGURE B 
                                                  No arrows indicated in the staircase
                                                     in FIGURE A
        Name the FIGURE that represents
                                                  No ramp in FIGURE A
  1     the first floor. Give ONE reason for                                                   2
        your answer.                              Balcony in FIGURE A
                                                  Staircase
                                                 ANY ONE OF THE ABOVE ANSWER
                                                 AND REASON OR ANY OTHER
                                                 ACCEPTABLE ANSWER
  2     Deduce from the building plan the        10                                           1
        number of windows in the building.

  3     Identify number 1.                       Balcony                                      1

  4     Identify number 2.                       Shower                                       1

  5     Identify number 6.                       One way switch – double pole                 1

  6     Identify number 8.                       Ramp                                         1

  7     Identify number 9.                       Wall mounted light                           1

  8     Identify number 10.                      Wash tub                                     1

        Identify the number that indicates the
  9                                              7                                            1
        garage door.

        Deduce from the building plan the
 10                                              110 mm/110                                   1
        omitted dimension of number 11.

        Deduce from the building plan the
 11     material that must be used for           Concrete                                     1
        number 5.

Copyright reserved                                                          Please turn over

### Page 7

Civil Technology: Construction                7                                       DBE/2023
                                  SC/NSC – Marking Guidelines

        Give the abbreviations for the
        following:                              Number 3: WC 
 12                                                                                               2
             Number 3                          Number 4: WB/WHB 
             Number 4
                                                Two-way switch:
        Describe the purpose of a two-way        Used to switch the same light on or
 13                                                                                               2
        switch.                                   off 
                                                 From TWO different positions 
                                                Tiles/Novilon/Concrete/Vinyl/
        Recommend an appropriate floor          Painted floors/Laminated timber
 14                                                                                               1
        covering for the kitchen.               flooring/Timber floors 
                                                ANY ONE OF THE ABOVE

        Who was responsible for the
 15                                             P Kriel                                          1
        checking of the drawing?

                                                No switch/electrical
        Deduce ONE fault in the bathroom in     connection/wiring/light/door/door
 16                                                                                               1
        FIGURE A.                               opening/bath/bidet 
                                                ANY ONE OF THE ABOVE
                                                Rechargeable bulb/Candle/Paraffin
        Name an alternative light source that
                                                lamp/Gas lamp/Battery powered
 17     can be used during load shedding for                                                      1
                                                lights/Torch/Solar/Cell phone 
        a dwelling.
                                                ANY ONE OF THE ABOVE
        State what was done during revision
                                                Revision 1: Drawing of Staircase 
 18     1 and revision 2 of the house plan.                                                       2
                                                Revision 2: Drawing of light fittings 

        Name the finish for the ramp as
 19                                             Paving                                           1
        prescribed by the architect.

        Draw the symbol for a damp-proof
 20                                                                                             2
        membrane.

 21     Draw the symbol for finished wood.                                                        2
                                                                           

 22     Draw the symbol for hardcore filling.                                                     2
                                                                          

Copyright reserved                                                             Please turn over

### Page 8

Civil Technology: Construction                8                                          DBE/2023
                                  SC/NSC – Marking Guidelines

                                                  Total horizontal dimensions
                                                   Control test top   Control test bottom
                                                   220               220 
                                                   4 110             4 820 
                                                   3 510             3 020 
                                                   220 
                                                   = 8 060            = 8 060 

        Prove, by means of a control test,                            OR
        that the total horizontal dimensions      Top:
 23                                                                                                  8
        on the top and bottom of the plan in
                                                  220 + 4 110 + 3 510 + 220 mm
        FIGURE A are the same.
                                                  = 8 060 mm
                                                  Bottom:
                                                  220 + 4 820 + 3 020
                                                  = 8 060 mm
                                                  Note: If the alternative method is
                                                         used, one mark should be
                                                         allocated if both totals are
                                                         the same.

        Calculate the area of the floor plan in   = 8,06  m x 6,05  m
        FIGURE B. Show ALL the                    = 48,76 m²
 24     calculations. Give your answer in m².                                                        3
        Round your answers to TWO decimal         OR
        places.                                   = 8 060 mm x 6 050 mm
                                                  = 48,76 m²
                                                                                     TOTAL:          40

Copyright reserved                                                                Please turn over

### Page 9

Civil Technology: Construction                      9                                   DBE/2023
                                        SC/NSC – Marking Guidelines

QUESTION 3: ROOFS, STAIRCASES AND JOINING (SPECIFIC)

3.1
        RISE/
        RISER               2          1
                                                                             TREAD
            3
                                                   OR
                                                             RISE/RISER
                                 TREAD
                                   3

            NOTE: ISOMETRIC/OBLIQUE DRAWINGS ALSO ACCEPTABLE

                        NO.            ASSESSMENT CRITERIA                MARK
                          1            Tread                                1
                          2            Rise/Riser                           1
                          3            Labels                               2
                                                         TOTAL:             4                       (4)

3.2       Collar-tie roof truss 
          Couple roof truss                                                                        (2)

Copyright reserved                                                               Please turn over

### Page 10

Civil Technology: Construction                          10                                   DBE/2023
                                             SC/NSC – Marking Guidelines

3.3

                                                                           RAFTER 4

                                                                           CLOUT NAILS
                                     3
                       3
                                                                           TIE BEAM
                                         2
                       2
                                                                           WALL PLATE

                           2
                                                                           HOOP-IRON STRAP

                                                                           WALL
                                 2

                                                             CORRECTNESS OF JOINING     1

                               NO.       ASSESSMENT CRITERIA           MARK
                                1        Correctness of joining          1
                                2        Hoop-iron strap                 4
                                3        Clout nails                     2
                                4        Any ONE label                   1
                                                                TOTAL:   8                               (8)

Copyright reserved                                                                    Please turn over

### Page 11

Civil Technology: Construction                  11                                        DBE/2023
                                     SC/NSC – Marking Guidelines

 3.4

                                             2           2

                                                     3

                            2                                                   RAFTER
                                                     3                     2

                                                                                KING POST

             CORRECTNESS OF RIDGE OF ROOF TRUSS                     1
             APPLICATION OF SCALE 4
                                                                           DRAWING NOT TO SCALE:
                                                                           USE A MASK TO MARK THIS
           NO.       ASSESSMENT CRITERIA                     MARK
                                                                           DRAWING
            1        Correctness of ridge                      1
            2        Rafters                                   4
            3        King post                                 2
            4        Application of scale                      1
                                          TOTAL:               8

                                         3

                                                             RIDGE BEAM

                                     2           2            RAFTER

                                 2                       2

                                         3

              CORRECTNESS OF RIDGE OF ROOF TRUSS                       1
              APPLICATION OF SCALE 4

                                                                        DRAWING NOT TO SCALE:
                                                                        USE A MASK TO MARK THIS
           NO.       ASSESSMENT CRITERIA                     MARK       DRAWING
            1        Correctness of ridge                      1
            2        Rafters                                   4
            3        Ridge beam                                2
            4        Application of scale                      1
                                          TOTAL:               8                                      (16)
                                                                                                      [30]

Copyright reserved                                                                 Please turn over

### Page 12

Civil Technology: Construction                12                                   DBE/2023
                                   SC/NSC – Marking Guidelines

QUESTION 4:          EXCAVATIONS, FORMWORK,                TOOLS,   EQUIPMENT      AND
                     MATERIALS (SPECIFIC)

4.1       4.1.1        K                                                                      (1)

          4.1.2        C                                                                      (1)

          4.1.3        I                                                                      (1)

          4.1.4        G                                                                      (1)

          4.1.5        F                                                                      (1)

          4.1.6        A                                                                      (1)

          4.1.7        D                                                                      (1)

          4.1.8        B                                                                      (1)

          4.2.1        Properties of galvanised sheet metal:
                        Protects metal against corrosion 
                        Shiny bluish-white in colour
                        Metal dipped in molten zinc
                        Low in corrosion but is prone to corrode when galvanised layer
                          is damaged
                        Acids found in pot-clay soil may also reduce galvanised
                          protection
                       ANY ONE OF THE ABOVE                                                    (1)

          4.2.2        Properties of low carbon steel:
                         Fine smooth appearance 
                         Can be bent
                         Ideally suited for forging
                         Can be rolled out or flattened
                         Fairly tough and strong
                         Easy to weld
                         Prone to rust if not treated
                       ANY ONE OF THE ABOVE                                                    (1)

Copyright reserved                                                          Please turn over

### Page 13

Civil Technology: Construction                13                                 DBE/2023
                                   SC/NSC – Marking Guidelines

          4.2.3        Properties of high carbon steel:
                        Reduced welding ability 
                        Ductile
                        Impact toughness
                        Increased strength and hardness
                        Grey in colour
                        Malleable
                        Corrodes easy
                        Good conductor of heat and electricity
                        Durable
                       ANY ONE OF THE ABOVE                                                  (1)

4.3       Methods of fixing cladding to a wall:
            Adhesive fixing 
            Face fixing 
            Proprietary fixing                                                             (3)

4.4       4.4.1        Slump test                                                           (1)

          4.4.2        True slump                                                           (1)

          4.4.3        True slump profile:
                         Correct amount of water was used 
                         Correct mixing proportions was used                                (1)

4.5       Services that need to be located:
            Electrical cables 
            Water pipes 
            Gas lines 
            Communication lines
            Storm water systems
            Sewer lines
          ANY THREE OF THE ABOVE                                                             (3)

4.6       Heavy rains during excavations can cause:
            Excavation can collapse/Mudslides can occur 
            Excavation can fill up with water 
            Conditions inside the trench can become slippery
            Delays may occur
          ANY TWO OF THE ABOVE                                                               (2)

4.7       Workers may not work alone in an excavation because:
            It is a safety risk 
            No one will be able to help the worker in case of an emergency
            No one will be aware that the worker is in danger
          ANY ONE OF THE ABOVE                                                               (1)

4.8       4.8.1        Plate compacter                                                       (1)

Copyright reserved                                                        Please turn over

### Page 14

Civil Technology: Construction                14                                 DBE/2023
                                   SC/NSC – Marking Guidelines

          4.8.2        Operating machine safely:
                        Operate with care 
                        Wear appropriate personal protective equipment (PPE) 
                        Do not place hands or feet near moving parts
                        Use both hands to operate this machine
                        Do not make any adjustments while the machine is in motion
                        Ensure a firm and well-balanced stance
                       ANY TWO OF THE ABOVE                                                  (2)

Copyright reserved                                                        Please turn over

### Page 15

Civil Technology: Construction                            15                                     DBE/2023
                                                   SC/NSC – Marking Guidelines

    4.9
                                                                5                          CLEAT

 BEAM/JOIST
                         3         3

                                                                                           FIXING PLATES
                                                                    2
SHUTTER
                                                                            4
BOARD SIDES
    WEDGE                          4
                                           2

                                       8                                8
                                                                                           BRACES/STRUTS
                                                            6
                               7                                                7

                                                                                           BEARER/HEAD TREE

                                                                                           SOFFIT/SHUTTER BOARD

                                                                                           BRACES/STRUTS

                                                                                           PROPS/STRUTS

     CORRECTNESS OF FORMWORK                   1      1

                  NO.        ASSESSMENT CRITERIA                                    MARK
                   1         Correctness of formwork                                  2
                   2         Cleats                                                   2
                   3         Beam/Joist (under floor)                                 2
                   4         Braces/Struts                                            2
                   5         Shutter board side (right)                               1
                   6         Soffit board                                             1
                   7         Fixing plates                                            2
                   8         Wedges                                                   2
                                                                    TOTAL:           14
                                                                                                                 (14)
                                                                                                                 [40]

    Copyright reserved                                                                        Please turn over

### Page 16

Civil Technology: Construction                16                                     DBE/2023
                                   SC/NSC – Marking Guidelines

QUESTION 5:          PLASTER AND SCREED, BRICKWORK AND GRAPHICS AS
                     MEANS OF COMMUNICATION (SPECIFIC)

5.1       Ratio:
           1 :3 /1:6/1:5
           1 Bag cement:3 Wheelbarrows sand/
           1 Bag cement:2½ Wheelbarrows sand
          ANY ONE OF THE ABOVE                                                                   (2)

5.2       Preparation of floors to receive screed:
           Chip the surface 
           Remove all debris and dust 
           Test the absorption ability of the concrete                                         (3)

5.3       A monolithic screed is a screed that is laid over fresh concrete.                      (1)

5.4       Plastering the stop-end of a wall, in chronological order:
           Clamped straight edges to stop-end of the wall 
           Apply the plaster and allow to dry 
           Cut the access plaster to the level of the straight edges 
           Finish off the sharp edges after removing the straight-edges                        (4)

5.5       Advantages of a gauge arch:
           Looks neat and aesthetic 
           Do not need plastering                                                              (2)

5.6

                                                             4

                            FORMWORK BOARD
                                                                 2

                                               3
                             LAGGINGS

              CORRECTNESS OF TURNING PIECE         1

                                 NO.    ASSESSMENT CRITERIA                      MARK
                                 1      Correctness of turning piece               1
                                 2      Formwork board                             1
                                 3      Laggings                                   1
                                 4      Space between laggings (open laggings)     1
                                                                      TOTAL:       4             (4)

Copyright reserved                                                            Please turn over

### Page 17

Civil Technology: Construction              17                                      DBE/2023
                                 SC/NSC – Marking Guidelines

5.7

                                                            3

                                                                         3
                                                3

                                                                             3
                                                        3

                                                                 3

          CORRECTNESS OF SECOND COURSE: 1

                                                                 2

                                                        2
                                                                             2
                                            2

                                                                     2

                                                            2

          CORRECTNESS OF FIRST COURSE:      1

                                          NO.        ASSESSMENT CRITERIA         MARK
                                           1        Correctness of courses         2
                                           2        First course                   6
                                           3        Second course                  6
                                                                        TOTAL:    14            (14)
                                                                                                [30]

Copyright reserved                                                           Please turn over

### Page 18

Civil Technology: Construction                 18                                   DBE/2023
                                    SC/NSC – Marking Guidelines

QUESTION 6:          REINFORCEMENT IN CONCRETE, FOUNDATIONS, CONCRETE
                     FLOORS AND QUANTITIES (SPECIFIC)

6.1       6.1.1        B                                                                       (1)

          6.1.2        D                                                                       (1)

          6.1.3        A                                                                       (1)

          6.1.4        C                                                                       (1)

          6.1.5        B                                                                       (1)

6.2

                                             2

                                                     3

                                                         4

                                                 5

          CORRECTNESS OF ENLARGED BASE HAMMERED IN                1

            NO.      ASSESSMENT CRITERIA                              MARK
             1       Correctness of enlarged concrete base              1
             2       Drop hammer                                        1
             3       Steel casing                                       1
             4       Shape of enlarged base                             1
             5       Symbol for concrete in the base                    1
                                                      TOTAL:            5                       (5)

6.3       Components of a rib-and-block floor:
           Hollow core blocks 
           Precast ribs/Pre-stressed ribs 
           Steel mat/Steel mesh/Wire/Reinforcing mesh/Reinforcing steel 
           Spacers 
           In-situ cast concrete/Concrete
          ANY FOUR OF THE ABOVE                                                                 (4)

6.4       The rib-and-block floor can collapse under the weight of the wet concrete.           (1)

Copyright reserved                                                           Please turn over

### Page 19

Civil Technology: Construction                    19                               DBE/2023
                                       SC/NSC – Marking Guidelines

6.5       6.5.1        Number of bars in the group                                            (1)

          6.5.2        Diameter of the bar                                                    (1)

          6.5.3        Center-to-center spacing/Heart spacing                                 (1)

6.6

                                   3

                                                                        4

                           2
                                                                               STIRRUPS 6

                                                        4
                                          5

              MINIMUM CONCRETE COVER           6
                                                                4

                                                    2

                                                                    3
                                 MAIN BAR

          CORRECTNESS OF L-SHAPED COLUMN                    1   1

                      NO.      ASSESSMENT CRITERIA                      MARK
                       1       Correctness of L-shaped column             2
                       2       Completed column                           2
                       3       8 main bars
                               Correct number of bars                     1
                               Correct placement of bars                  1
                       4       Stirrups                                   3
                       5       Minimum concrete cover (indicated)         1
                       6       Any TWO labels                             2
                                                                 TOTAL:  12                    (12)

Copyright reserved                                                          Please turn over

### Page 20

Civil Technology: Construction               20                                       DBE/2023
                                  SC/NSC – Marking Guidelines

6.7          A         B         C                             D
                                          Correct use of dimension paper                         (1)

                                          Internal dimensions long walls:
                                          7 000 – 2/220 = 6 560 mm 
                                          Internal dimensions of the short walls:
                                          6 000 – 2/220  = 5 560 mm 
                                                                                                (4)
                                          Volume of blinding layer:
            1/      6,56 
                     5,56 
                     0,04  1,46 m³
                                                                                                 (5)
                                                                                                 [40]

                                                                                    TOTAL:       200

Copyright reserved

## Related documents

- [CIV TECH GR12 QP SEPT2024 Construction English](https://www.hlayiso.com/library/civ-tech-gr12-qp-sept2024-construction-english/12643629-87af-4230-a48a-002beb7f6cd7) — Civil Technology · QP · 2024 · Eng
- [CIV TECH GR12 MEMO SEPT2022 Woodworking English](https://www.hlayiso.com/library/civ-tech-gr12-memo-sept2022-woodworking-english/62d9cbb1-1077-4edb-86c4-7a21fd6749a9) — Civil Technology · Memo · 2022 · Eng
- [CIV TECH GR12 MEMO SEPT2022 Civil Services English](https://www.hlayiso.com/library/civ-tech-gr12-memo-sept2022-civil-services-english/896ddb1f-2144-4bfc-a35a-3a71507d7637) — Civil Technology · Memo · 2022 · Eng
- [CIV TECH GR12 MEMO SEPT2021 English Civil Services](https://www.hlayiso.com/library/civ-tech-gr12-memo-sept2021-english-civil-services/80eb9860-b118-41e2-98fd-5bea1b29a026) — Civil Technology · Memo · 2021 · Eng
- [CIVIL TECH GR12 MEMO GR12 SEPT2017 English](https://www.hlayiso.com/library/civil-tech-gr12-memo-gr12-sept2017-english/fcb77566-a1ac-4dff-af72-678e70ccfbc4) — Civil Technology · Memo · 2017 · Eng
- [Civil Technology May June 2019 (Civil Services) Memo Afr](https://www.hlayiso.com/library/civil-technology-may-june-2019-civil-services-memo-afr/2a9b9e1b-37dc-48dc-9aa7-67dd5fa19a10) — Civil Technology · Memo · 2019 · Afr

## More from Grade 12 Civil Technology

- [Civil Technology Nov 2025 (Woodworking) Afr](https://www.hlayiso.com/library/grade-12-civil-technology-2025-nsc-november-exam-question-paper/05a95faf-5891-4d88-9e5e-7d13c1d21648) — QP · 2025 · Afr
- [Civil Technology Nov 2024 (Woodworking) Afr](https://www.hlayiso.com/library/civil-technology-nov-2024-woodworking-afr/eefaae29-fe93-4b75-8223-87bf4f3fc14c) — QP · 2024 · Afr
- [Civil Technology Nov 2024 (Civil Services) Afr](https://www.hlayiso.com/library/civil-technology-nov-2024-civil-services-afr/307147a5-3280-4a11-a82e-cf3e33388eb0) — QP · 2024 · Afr
- [CIV TECH GR12 QP SEPT 2023 Construction English](https://www.hlayiso.com/library/civ-tech-gr12-qp-sept-2023-construction-english/4163a632-f091-41bf-8a36-993d566fb2cc) — QP · 2023 · Eng
- [Civil Technology Nov 2023 (Construction) Eng](https://www.hlayiso.com/library/civil-technology-nov-2023-construction-eng/e6743728-8140-42ae-838d-282654a975a5) — QP · 2023 · Eng
- [Civil Technology Nov 2023 (Civil Services) Afr](https://www.hlayiso.com/library/civil-technology-nov-2023-civil-services-afr/b820ac91-947c-4aed-821f-256aa13aabe1) — QP · 2023 · Afr

## Collection

- [Grade 12 past papers](https://www.hlayiso.com/grade-12/past-papers)

---

Hlayiso: free CAPS and IEB past papers, memos, notes and study guides for South African learners. When citing, link the page URL above, not a PDF or /api/ URL.