basic education Department: Basic Education REPUBLIC OF SOUTH AFRICA NATIONAL SENIOR CERTIFICATE if ENGINEERING GRAPHICS AND DESIGN P1 a) I le NOVEMBER 2025 J MARKS: 100 TIME: 3 hours This question paper consists of 6 pages. | | | | | | | Barcode label | | | | | | | Confidential INSTRUCTIONS AND INFORMATION This question paper consists of FOUR questions. Answer ALL the questions. ALL drawings are in first-angle orthographic projection, unless otherwise stated. ALL drawings must be prepared using pencil and instruments, unless otherwise stated. ALL answers must be drawn accurately and neatly. ALL the questions must be answered on the QUESTION PAPER, as instructed. ALL the pages, irrespective of whether the question was attempted or not, must be re-stapled in numerical sequence in the TOP LEFT-HAND CORNER ONLY. 8. Time management is essential in order to complete all the questions. 9. Print your examination number in the block provided on every page. 10. Any details or dimensions not given must be assumed in good proportion. BONS NOD FOR OFFICIAL USE ONLY QUESTION | MARKS OBTAINED | } | SIGN MODERATED 3} SIGN RE-MARKING 3] SIGN 1 2 3 4 TOTAL 2/;0/0 2/0/0 2/;0/0 FINAL CONVERTED MARK CHECKED BY 100 COMPLETE THE FOLLOWING: CENTRE NUMBER CENTRE NUMBER EXAMINATION NUMBER Testpa Pers .co.za Testquestions .cO.Za
Engineering Graphics and Design/P1 NSC Confidential DBE/November 2025 NOTE: UESTION 1: ANALYTICAL (CIVIL) Coe | LAND SURVEYOR'S CERTIFICATE OF THE SYNE OE CECENS Contractors must verly al dimensions and | @ (emily ge CORNER HEIGHTS AND BOUNDARY levels on site before commencing work. . Cc YELLOWWOOD . LENGTHS OF LOT 1080 TREE & Architects to be notified immediately of any | Given: discrepancies. The site plan of an existing building with a proposed new building, a title panel and a table of questions. The drawing is CORNER HEIGHTS Pxenis PALM TREE ¥ ARCHITECT'S SIGNATURE not presented to the indicated scale 'N METRES MILLIMETRES PARKING FOR (CHENTSS SIGNATURE Instructions: A 60 aa | 46070 PEOPLE WITH 6 ANSWER 20 Complete the table below by neatly answering the questions, which refer to the accompanying drawing, title panel and DISABILITIES civil content. [30] 8 61 ac | 38640 In the space below, draw, in neat . 3 * co) sero NEW 2,5 m HIGH freehand, the SANS 10143 SECURITY FENCE [77] graphical symbol for: D 585 DE 30000 (a) A RAMP with a gradient of 1: 15 QUESTIONS ANSWERS with the lowest point on the right —_ E 58 EA 64780 (b) The elevation/front view of a 1 | What scale is indicated for the site plan? 41 DOUBLE SINK 2 | When was the second revision made to the drawing? 1 6 m VEHICLE ENTRANCE (a) RAMP 3 | Whatis the height of the lowest comer of LOT 1080 in metres? 1 ‘AND EXIT ! 4 | In which town is LOT 1080 situated? 1 FIRST AVENUE TAA ONE 5 | How many parking bays are shown on LOT 1080? 1 _ Y oO 6 | How wide Is the vehicle entrance and exit in millimetres? 1 A \ pavemeny om wie B 7_| What does the arrow at the vehicle entrance and exit indicate? 1 — p—-J--—_.- = Sep (b) DOUBLE SINK 8 | What is the fall of the municipal sewerage line? 1 2500kVA_ | ISUBSTATION 9 | How many existing rodding eyes are indicated on LOT 1080? 1 10 | Give the full name of the feature at 1. 1 EXISTING fa ROUND- 11 | Name the feature at 2. 1 ABOUT LOT 1081 w 42 | What security feature is added to the masonry wall on boundary CD? 4 28 CY Zac 13 | What is the abbreviation for CONCRETE? 1 = REDUCE LENGTH OF oe aI 2 02/07/2025 | “PARKING BAYS 44 | What colour is used to represent new steel on sectional elevations? 4 a FA s PROPOSED 4 30/06/2025 ADD SECURITY 15 | On what type of drawing is brown used for drains and soil pipes? 1 re FENCE q BUILDING 16 | How many palm trees are north-west of the existing building? 2 REVISION | DATE DESCRIPTION - 47 | [building line P-Q is 21 m from corner S on the proposed new 6 eb ARCHTELTS building, how far is comer S from FIRST AVENUE in millimetres 17 LYNX ROAD imberc@siynetcom | 48 | In the space below (ANSWER 18), determine the length of the new security fence in metres. 3 MACASSAR ‘021 7652468 EXISTING 7945 19 | In the space below (ANSWER 19), determine the total area of the new building in square metres. 3 BUILDING PROJECT ARORITEGT: In the space in the title panel (ANSWER 20), draw, in neat freehand, the SANS 10143 graphical MENSLIN 20 | symbol for: (a) a RAMP with a gradient of 1 : 15 with the lowest point on the right, and (b) the 5 PRINTED BY: DATE OF PRINT: elevation/front view of a DOUBLE SINK. BIG TREE 04/07/2025 TOTAL | 30 PRINTERS DRAWING THLE ANSWER 18 11000 ANSWER 19 x x LAD ON LE OR EAS SITE PLAN Show ALL calculations. p00 Show ALL calculations. PRONEGT (Do NOT round off the answer.) | 3s — ory (Do NOT round off the answer.) PROPOSED NEW BUILDING FOR 8 3 HIGH ALTITUDE DRONE DESIGNERS, SS 8 PERISTING 2 HIGH 25 FIRST AVENUE, STRAND 300 ; 6-LINE ELECTRIC FENCE | PROvecT NUMBER: DRAWING NUMBER: Sg 416-25 D[o[*]o][4]4 J N DATE pawns | cnecxen: | scale 8 PAVEMENT 3 m WIDE 28/06/2025 | R NEWTON |MENSLIN | 1: 400 L REFERENGE CODE: DRAWING SEQUENCE 5000 BEACH DRIVE HAD-150169 30f6 Ly EXAMINATION NUMBER SITE PLAN 43000 SCALE 1: 400 ‘ 7 EXAMINATION NUMBER [2 Copyright reserved Please tun over
Engineering Graphics and Design/P1 NSC Confidential DBE/November 2025 QUESTION 2: INTERPENETRATION AND DEVELOPMENT... Given: © The top view and incomplete front view of a right regular hexagonal prism that passes through a right regular pentagonal prism. The axes of both solids lie in a common vertical plane. * Auxiliary views of the hexagonal prism Instructions: Draw, to scale 1 : 1, the following views of the TWO solids: 2.1 The given top view 2.2 The right view 2.3 The complete front view, clearly showing the curves of interpenetration © Planning is essential * Show ALL hidden detail * Show ALL construction [39] ASSESSMENT CRITERIA 41 |TOP VIEW 13 2. |FRONT VIEW 18 3 |RIGHT VIEW 8 PENALTIES () TOTAL| 39 EXAMINATION NUMBER EXAMINATION NUMBER [3 Copyright reserved Please turn over
Engineering Graphics and Design/P1 NSC Confidential DBE/November 2025 PP. QUESTION 3: PERSPECTIVE Given: Three views of a poolhouse with a splash pool and the information needed to draw a two-point perspective drawing PP - Picture plane HL - Horizon line GL - Ground line SP - Station point Instructions: Complete the perspective drawing * Align the drawing sheet with the ground line (GL). * Determine and label the vanishing points * Show ALL construction Show depth at the entrance opening * Show interior detail as seen through the entrance opening * NO hidden detail is required [41] ASSESSMENT CRITERIA CONSTRUCTION 6 WALLS + PATIO 14 HL = | ENTRANCE OPENING GL t t t Li--41-__4 SPLASH POOL OPENING + POOL 7 alaleln]= ROOF 6 7 ARC + CONSTRUCTION PENALTIES (-) TOTAL} 41 HL GL EXAMINATION NUMBER EXAMINATION NUMBER [4 Copyright reserved Please turn over
Engineering Graphics and Design/P1 NSC Confidential DBE/November 2025 ROOF CAP AND RIDGE CAP 150 x 100 mm GUTTER ON 200 x 20 mm FASCIA BOARD WITH @100 mm RWDP THAT STOPS 50 mm ABOVE THE GROUND LEVEL GABLED WALL 300 x 80 mm BARGE BOARD WINDOW OPENING 2900 SLIDING DOOR OPENING CONCRETE STEP FINISHED FLOOR LEVEL GROUND LEVEL —---—-ROQFLINE_____, @_ F INCOMPLETE SCHEMATIC DIAGRAM OF A ROOF TRUSS FOR ROOF ‘Mt FEATURES D1 SLIDING DOOR D2 DOOR Wi WINDOW w2 WINDOW w3 WINDOW FIXTURES S SINK WB WASHBASIN we TOILET SH SHOWER B BATH BIC BUILT-IN CUPBOARD ELECTRICAL FITTINGS 1. ONE-WAY SWITCH - SINGLE-POLE 2, ONE-WAY SWITCH - DOUBLE-POLE 3, FLUORESCENT LIGHT 3 x 40 W 4, CEILING LIGHT 5, WALL-MOUNTED LIGHT 6, SWITCHED SOCKET OUTLET 7. DISTRIBUTION BOARD. NOTE: THE ARROW SHOWS THE LIGHT CONNECTION TO THE SWITCH. gy A000, A050 |, FLOOR FINISHES 1 g 1. LIVING AREA 2. BATHROOM: 3 3. BEDROOM: TILE TILE CARPET ROOM DESIGNATIONS. DOOR AND WINDOW SCHEDULE x TOFIT 1500 y yf 4 TORT poppe? 800, A 800 _ 400 , 2100 = S ‘| 800_|, WINDOW (W1) 1200 # 4 ———————————— SLIDING DOOR (D1) WINDOW NOTES: * A= OPENING SIDE * B= FIXED PANEL XS SINGLE DOOR ‘AND FRAME (D2) 900 A ‘WINDOW (W3) * ALL FRAMES = 50 mm THICK © 200 x 20 mm FIBRE CEMENT SILL UNDER ALL WINDOWS ANDOW (W2) ROOF COMPONENTS ELECTRICAL SYMBOLS 4 ROOF CAP AND RIDGE CAP 300 x 80 mm BARGE BOARD oun) 3200 GROUND LEVEL ROOF NOTES: 20° ROOF PITCH 120 x 40 mm ROOF TRUSSES ON 120 x 40 mm WALL PLATES 350 mm ROOF OVERHANG TO END OF ROOF TRUSS 40 mm CORRUGATED ROOF SHEET ON 80 x 50 mm PURLINS @ 900 mm cic 200 x 20 mm FASCIA BOARDS WITH 150 x 100 mm GUTTERS ON ALL SIDES 300 x 80 mm BARGE BOARDS SHAPED TO FIT ON THE END OF ROOF 'N', 150 mm PAST FASCIA BOARDS. 10 mm CEILING BOARDS ON 40 x 40 mm BRANDERING STRIPS @ 300 mm cle INCOMPLETE GABLE WALL DETAIL pp 200 s— HJ] lA |—200 x 80 mm LINTELS ABOVE ‘ALL DOOR AND WINDOW OPENINGS, 2380 | LEVEL 400 400 | | | INCOMPLETE FOUNDATION, STEP AND EXTERNAL WALL DETAIL 200 x 20 mm FASCIA BOARD one) 150 x 100 mm GUTTER o 80 axaoW x 50 mm PURLIN FIXTURE SCHEDULE GROUND| 500 800 3 a 500 800 NS 8 g <> TOILET (WC) 500 WASHBASIN (WB) BATH(B) ay 850 1 Ss PLAN/TOP VIEW OF X BUILT-IN CUPBOARD (BIC) SHOWER (SH) 850 y 800_, 1700 £ 4 Qui IESTION 4: CIVIL DRAWING Given: eee ewe Inst The incomplete south-east elevation of a new house, showing the walls, the window and door openings, step, roof, gabled wall and labels The incomplete floor plan showing the walls, roof line, steps, positions of the doors, windows, fixtures and electrical layout An incomplete schematic diagram of a roof truss for roof 'M' and roof notes The incomplete gable wall detail The incomplete foundation, step and external wall detail Room designations and floor finishes A door and window schedule A table of roof components A table of electrical symbols A fixture schedule The incomplete floor plan and position of the ground level of the south-east elevation of the new house, drawn to scale 1: 50, and the incomplete foundation and break line for the detailed section, drawn to scale 1 : 20, on page 6 structions: Answer this question on page 6. 44 42 Using the given incomplete floor plan and ground level, draw, to scale 1 : 50, the following views of the new house: 4.1.1 THE COMPLETE FLOOR PLAN Add the following features to the drawing: * ALL doors and windows * ALL fixtures as indicated by the abbreviations * ALL electrical fittings as indicated by the numbers * ALL hatching detail 4.1.2 THE COMPLETE SOUTH-EAST ELEVATION Show the following features on the drawing: © The walls, window, sliding door and step detail © The roof detail including fascia boards, barge board, gutters and rainwater downpipe © The finished floor level Using the incomplete foundation and break line on page 6, draw, to scale 1 : 20, a DETAILED SECTION on cutting plane A-A of the area in the ellipse shown on the incomplete floor plan Show the following features on the drawing: © The complete foundation, step, external wall and door detail * The roof detail including the fascia board and gutter © The wall, barge board and gable wall detail to the right (north-east) of cutting plane A-A * ALL hatching detail. ONLY the substructure hatching may be drawn in neat freehand Label the following: The south-east elevation The floor finishes Ground level, finished floor level, damp-proof course and rainwater downpipes (use the correct abbreviations and show them on ALL relevant views) NOTE: ALL drawings must comply with the guidelines and graphical symbols as contained in SANS 10143, [90] [5 Copyright reserved Please turn over
Engineering Graphics and Design/P1 NSC Confidential DBE/November 2025 MARK moyen FOR OFFICIAL USE ONLY SECTION OF ROOF | |iNCORRECT A SCALE(S) USED B NON-ALIGNMENT OF VIEWS c VIEW(S) ROTATED ° ‘SECTION VIEWED E INCORRECTLY F INCORRECT LETTERING SG H J K TOTAL TOTAL ASSESSMENT CRITERIA FLOOR PLAN Possisie | oaraneo | sion | moveRaTeD fey 1 | anbows 11 2 | rorures 104 _ 3 feccmen | of a | 4 4 | assis a a — Xe Mo =: | J U SUBTOTAL 363 \ | \ | SOUTH-EAST ELEVATION \ T= Tat | N | BATHROOM RWOP z | \ \ | 2 | oye 6 ) | 3 [ew | ad | t | 4 | aes 1 wl | | SUBTOTAL 24 Si Lg A 4 t | DETAILED SECTION 2 ILIVING AREA | 4 |roorcera, | 124 | | | ——7 2 Se: Be LS + 7 . | 3 | Brea 2 | BEDROOM 4 | warcuIne 53 | | 5 | users 1 | | SUBTOTAL 294 | TOTAL 90 PENALTIES (-) TTT LI GRAND TOTAL FLOOR PLAN SCALE 1: 51 SECTION A-A SCALE 1:20 EXAMINATION NUMBER EXAMINATION NUMBER [6 Copyright reserved