INSTRUCTIONS AND INFORMATION
1. This question paper consists of FOUR questions.
2. Answer ALL the questions.
3. All drawings must be drawn to scale 1 : 1, unless otherwise stated.
4. ALL drawings are in first angle orthographic projection, unless stated
otherwise.
5. ALL drawings must be prepared using pencil and instruments, unless
otherwise stated.
6. All answers must be drawn accurately and neatly.
7. The questions must be answered on the question paper, as instructed.
8. All the answer sheets must be re-stapled in numerical sequence and handed
in irrespective of whether the question was attempted or not.
9. Time management is essential in order to complete all the questions.
10. Print your name in the block provided on every ANSWER SHEET.
11. Any details or dimensions not given, must be assumed in good proportion.
FOR OFFICIAL USE ONLY
MODERATED
NATIONAL MARK
SENIOR CERTIFICATE 1
2
3
4
GRADE 12 TOTAL
2 0 0 2 0 0
FINAL CONVERTED CHECKED BY
MARK
ENGINEERING GRAPHICS AND DESIGN P1
100
SEPTEMBER 2024
COMPLETE THE FOLLOWING:
PREPARATORY EXAMINATION
NAME
NAME
MARKS: 200
EXAMINATION CENTRE
TIME: 3 hours
This question paper consists of 6 pages.
EXAMINATION CENTRE
Copyright reserved
Please turn over
Hosted by www.ecexams.co.za.
Skip to contentAll 2024 papers 





View all





Engineering Graphics and Design Grade 12 P1 2024 QP (Eng)
Grade 12 Engineering Graphics and Design Paper 1 question paper from the Eastern Cape Prelim Exam 2024 (English), 6 pages. Read online or download the free PDF.
Engineering Graphic And Design · Grade 12 · Eastern Cape Prelim Exam · 2024. Question paper, 6 pages. Read online or download the PDF.
- Subject
- Engineering Graphics and Design
- Grade
- Grade 12
- Document type
- Question paper
- Year
- 2024
- Exam period
- Eastern Cape Prelim Exam
- Paper
- 1
- Curriculum
- CAPS
- Pages
- 6
- File size
- 1.7 MB
Free to read online, no sign-up needed
Loading document…
Loading document…
1 of 6
This exam
Eastern Cape Prelim Exam 2024
Questions in this paper
Document textSearch extracted text and jump to a page.
Engineering graphics and design / P1
Downloaded from hlayiso.com NSC EC / September 2024
NOTE: QUESTION 1: ANALYTICAL (CIVIL)
SYMBOL LEGEND LAND SURVEYOR'S CERTIFICATE Contractors must verify all dimensions
OF THE BORDER LINE LENGTHS and levels on the site before Given:
1 BRICK PAVING AND CORNER HEIGHTS OF commencing work. Architects to be The site plan of an existing fruit packhouse with alterations of a new dining hall on stand 6358, a title block and a table of
STAND 6358 notified immediately of any questions. The drawing has not been prepared to the indicated scale.
HOUSING
2 CONTAINER FOR 4 SURVEYED ON 2024-02-27 discrepancies.
PEOPLE
LENGTHS IN CORNER HEIGHTS IN Instructions:
2 100 mm HIGH MILLIMETRES METRES Complete the table below by neatly answering the questions which refer to the accompanying drawing and title block. [28]
3 SECURITY FENCING ARCHITECT'S SIGNATURE ...................................
AB = 87 000 A = 83
4
1 250 KVA DIESEL
GENERATOR
BC = 41 250 B = 81,5 CLIENT'S SIGNATURE ...................................
QUESTIONS ANSWERS
CD = 8 250 C = 81
5 INDIGENOUS TREE DE = 63 750 D = 81 1 In which town is the fruit packhouse situated? 1
EF = 93 000 E = 82 ANSWER 17
FA = 93 750 F = 80
On what date was the borderline lengths and corner heights of
6 STREETLIGHT
In the space below, draw in neat 2 1
stand 6358 surveyed?
freehand, the front view and top view
7 ZEBRA-CROSSING
of the SANS 10143 graphical symbol 3 What is the reference code of this drawing? 1
for a SLAB URINAL.
4 What is the indicated KVA of the diesel generator? 1
STAND 6356
5 How many open parkings are indicated on stand 6358? 1
B
In what colour should a new steel security gate be presented on
6 1
3800 BL the siteplan?
A
7 Name the feature at X. 1
W
8 Name the feature at Y. 1
STAND 6358 BL
What is the purpose of the boom gate, indicated at Z, on the site
3800 9 1
plan?
10 What does the abbreviation IC stands for? 1
800 BL
C
D 3
11 What is the height of the security fencing on stand 6358, in meter?
2000 BL
HOUSING FOR 1
Show the position of
FRUIT PACKERS 2 2024-04-16 the shaded parking
STAFF Y 12
How many packing staff can be accommodated in the housing
2
Indicate the KVA of containers?
EXISTING FRUIT 1 2024-03-28 the generatior
PACKHOUSE PROPOSED In relation to the north point, which elevation of the existing office
NEW DINING REVISION DATE DESCRIPTION 13 2
faces Porter road?
X HALL
3000 BL
KOTZE AND FOX ARCHITECTS Determine the total length that is paved, from the dining hall to the
133 PIET RETIEF ROAD 14 3
entrance of the packhouse, in meters.
20000
3750
DURBANVILLE, CAPE TOWN
PACKHOUSE RE
IE 083 789 555 Determine, in the space provided below (ANSWER 15) the total length of the security fence
ENTRANCE 15 3
IE kotze.fox@gmail.com around stand 6358 in meters. Show ALL calculations and formulas.
SHADED Determine, in the space provided below (ANSWER 16), the total area of the new dining hall on
PARKING
17250 4500 11250 PRINTED BY: DATE OF PRINT: 16 3
stand 6358, in square meters. Show ALL calculations and formulas.
IE IE RE PARKING FLOW SIGNS 2024-03-20
AREA DRAWING TITLE: In the space at the title panel (ANSWER 17), draw in neat freehand, the top view and front view of the
SITE PLAN 17 4
EXISTING SANS 10143 graphical symbol for a slab urinal.
OFFICE BOOM GATE 4800
IC SECURITY PROJECT: ANSWER 15 ANSWER 16
3500 BL CHECKPOINT NEW DINING HALL PROPOSAL ON Show ALL calculations. Show ALL calculations.
TOTAL 28
IC STAND 6358 FOR
MR P. KOK
F
MH EXISTING SEWERAGE Z E
Cnr. PORTER ROAD, GOUDA
13500
LINE LAID AT 1:40
STEEL
6000
PROJECT NUMBER: DRAWING NUMBER:
PORTER ROAD SECURITY
12750
01-2024 KJ-20/03-24
SWING GATE
DATE: DRAWN: CHECKED: SCALE: 3750
2024-03-03 JACQUES WILLEM 1 : 750 NAME
REFERENCE CODE: DRAWING NO.: 9750
SITE- 6358-24 1 of 5 NAME 2
Copyright reserved Please turn over
Hosted by www.ecexams.co.za.
Engineering graphics and design / P1
Downloaded from hlayiso.com
NSC EC / September 2024
QUESTION 2: SOLID GEOMETRY
Given:
· The complete front view and top view of a hexagonal
prism with a half circular hole and a triangular pyramid.
One of the pyramid sides, rests against the prism.
· A cutting line A-A.
· Starting Point O.
Instructions:
Draw to scale 1 : 1, the following views of the solids:
2.1 The given front view.
2.2 The sectional top view.
2.3 The sectional left view.
· ALL hidden detail is required.
· Show ALL necessary constructions.
[38]
30 A
75
65
X Y
12
A R20
32
45° ASSESSMENT CRITERIA
O
1 FRONT VIEW 7½
66
2 SECTIONAL TOP VIEW 11
O 3 SECTIONAL LEFT VIEW 14½
4 HATCHING 5
PENALTIES (-)
TOTAL 38
NAME
NAME 3
Copyright reserved Please turn over
Hosted by www.ecexams.co.za.
Engineering graphics and design / P1
Downloaded from hlayiso.com NSC EC / September 2024
ASSESSMENT CRITERIA
QUESTION 3: PERSPECTIVE
Given: 1 CONSTRUCTION + VP's 6
· Three views of a house with a porch and the information
needed to draw a two-point perspective drawing. 2 WALLS + PORCH + STEP 18½
WINDOW
PP − Picture plane 3 ROOF 4
HL − Horizon line
GL − Ground line 4 WINDOWS + DOOR 5½
SP − Station point
5 ARCH + CONSTRUCTION 4
Instructions:
Complete the perspective drawing. PENALTIES (-)
· Align the drawing sheet with the ground line (GL). TOTAL 38
· Determine and label the vanishing points.
· Show ALL necessary construction.
· NO hidden detail is required. [38]
DOOR
PORCH
PP PP
HL HL
OPENING
DOOR WINDOW
IN WALL
FFL FFL
GL
NAME
SP
NAME 4
Copyright reserved Please turn over
Hosted by www.ecexams.co.za.
Engineering graphics and design / P1
Downloaded from hlayiso.com NSC
200 x 20 ROOF BARGE BOARD
EC / September 2024
FASCIA BOARD QUESTION 4: CIVIL DRAWING
RIDGE COVER COVER THE GUTTER
Ø100 mm RWDP THAT STOPS
DOOR AND WINDOW SCHEDULE GUTTER
100 mm ABOVE THE GULLEY Given:
TO FIT 20° · The incomplete east elevation of a new house, showing the
ROOF COMPONENTS
walls, windows and door openings, the steps and ramp, the
300
RIDGE COVER 150 roof and labels.
1200
600 · The incomplete floor plan showing the walls, steps, ramp,
position of the doors, windows, fixtures and the electrical
3100
200 x 20 mm
layout.
600 950
ROOF BARGE BOARD 2100
2100
A B
· A schematic diagram of a single roof truss and roof notes.
A
· The incomplete foundation and external wall with dimensions.
200 x 20 mm 400
WINDOW FASCIA BOARD · A door and window schedule
(NE1) WINDOW · A steps and ramp schedule
(NC2) 150 x 100 GUTTER FINISHED FLOOR LEVEL GROUND LEVEL · A table of electrical symbols
100
INCOMPLETE EAST ELEVATION 100 · A table of roof components
DOOR (D1) FEATURES · Floor finishes
D1 DOORS · A table of sanitary fixtures
WINDOW NOTES NE1 + NC2F + NC2 WINDOWS
1200 B WB · The incomplete floor plan, of a new house, drawn to scale
A = OPENING SIDE
B = FIXED PANEL
400 FIXTURES NE1 5 1 : 50, and the incomplete foundation and break lines for the
THICKNESS OF ALL S SINK
WC
for the detailed section, drawn to scale 1 : 20, on page 6.
FRAMES: 50 mm A B BATH
D1
950 A
WC TOILET Instructions:
WINDOW SILL: 1
WB WASH BASIN
B Answer this question on page 6.
NC2F
180 x 20 mm
FIBRE CEMENT ELECTRICAL FITTINGS 5
1 4.1 Use the given incomplete floor plan, to draw, in first-angle
WINDOW SILL UNDER WINDOW 1. ONE-WAY SWITCH - SINGLE-POLE orthographic projection to scale 1 : 50, the following views of
(NC2F) D1
ALL WINDOWS 2. ONE-WAY SWITCH - DUBBLE-POLE the new house:
3. SWITCHED SOCKET OUTLET 4 4.1.1 THE COMPLETE FLOOR PLAN
4. FLUORESCENT LIGHT 2 x 40 W
5. CEILING LIGHT S Add the following features to the drawing:
NC2F
D1
6. WALL-MOUNTED LIGHT 5 · ALL doors and windows
FLOOR FINISHES
1 A · ALL sanitary fixtures as indicated by the abbreviations
1. OPEN PLAN: TILES 1
2 · ALL electrical fittings as indicated by the numbers
2. BEDROOM 1: CARPET NOTE: D1 NC2
THE ARROWS ON THE FLOOR PLAN SHOW 6 · ALL hatching detail
3. BATHROOM: TILES
4. OFFICE: WOOD THE LIGHT CONNECTION TO THE SWITCH. 5 NE1 750 4.1.2 THE COMPLETE EAST ELEVATION
A Show the following features on the drawing:
3
CONCRETE SLAB · The outside walls, door, steps, ramp and the detailed
windows.
FLOOR PLAN · The roof detail, including the fascia boards, ridge covers,
ELECTRICAL SYMBOLS STEPS AND RAMP 260 SCALE 1 : 50 ROOF NOTES: roof barge board, gutters.
SCHEDULE 20° ROOF PITCH · The finished floor level.
1 X 250 x 100 mm LINTEL
130 ABOVE ALL DOOR AND 4.2 Using the given foundation and break line on page 6,
WINDOW OPENINGS 114 x 38 mm ROOF TRUSSES ON draw, to scale 1 : 20 a DETAILED SECTION on cutting
114 x 38 mm WALL PLATES plane A-A of the area in the ellipse shown on the
900 incomplete floor plan.
W 650 300 mm ROOF OVERHANG TO THE END OF THE ROOF TRUSS
n x 40 W Show the following features on the drawing:
NGL ROOF COVER: 20 mm FIBRE CEMENT ROOF SHEETING · The complete foundation-, concrete slab-, external wall-,
150 ON 75 x 50 mm PURLINS @ 900 mm c/c and window detail.
· The steps, with the ramp, to the south of the cutting plane
SANITARY FIXTURES 2640 200 x 20 mm FASCIA BOARD WITH 150 X 100 mm GUTTERS ON ALL
2100
A-A
SIDES AND A Ø100 mm RAINWATER DOWN-PIPE · The roof detail, including the fascia board and gutter.
500 200 x 20 mm ROOF BARGE BOARD
400 · ALL hatching detail. ONLY the substructure hatching may
10 mm CEILING BOARD ON 38 x 38 mm BRANDERING @ 400 mm c/c be drawn in neat freehand.
130
850 200
750
400 900 Label the following:
400 100 SCHEMATIC DIAGRAM OF · The east elevation.
FLOOR LEVEL
ROOF TRUSS FOR ROOF · The floor finishes.
300 · Ground level, finished floor level and damp proof course (use
300
400 350 GROUND LEVEL c/c the correct abbreviations and show it on ALL the relevant
600 200
700
500 900
100 400 c/c views)
200 900
NOTE:
1700 1200 c/c
600 900 ALL drawings must comply with the guidelines and graphical
WASH BASIN TOILET BATH SINK 20°
symbols as contained in the SANS 10143. [96]
(WB) (WC) (B) (S) DIMENSION GUIDE:
400 c/c 400 c/c 400 c/c
INCOMPLETE FOUNDATION AND
EXTERNAL WALL DETAIL
5
Copyright reserved Please turn over
Hosted by www.ecexams.co.za.
Engineering graphics and design / P1
Downloaded from hlayiso.com NSC EC / September 2024
PENALTIES
ROOF DETAIL:
MARK ALLOCATION 1 INCORRECT SCALE
A ROOF ANGLE 1
2 2 NON-ALIGNMENT OF VIEWS
ROOF SHEET
B (SHOW 2 3 INCORRECT LETTERING
THICKNESS)
ROOF TRUSS
C
OVERHANG
221 TOTAL PENALTIES (-)
PURLIN +
D 121
SPACING
BRANDERING
ASSESSMENT CRITERIA
E 121
+ SPACING
CEILING 1
FLOOR PLAN
F 2
BOARD
DOORS +
G WALL PLATE 1
1 WINDOWS
14
H FACIA BOARD 121 2 ELECTRICAL 9
I GUTTER 121 3 FIXTURES 7
TOTAL 12 21 4 HATCHING 3
5 LABELS 2
NGL
SUBTOTAL 35
EAST ELEVATION
ROOF + FACIA +
GUTTER +
1 COVERS + BARGE 12 21
BATHROOM
BOARD
WALLS + PORCH
2 + STEPS + 8
RAMP + FFL
DOOR +
3 WINDOW
5 21
4 LABELS 1
SUBTOTAL 27
BEDROOM 1 DETAILED SECTION
1 ROOF DETAIL 12 21
FOUNDATIONS +
OPEN PLAN
2 WALLS + FLOOR 6
+ SLAB
WINDOW +
BEDROOM 2 3 STEPS + RAMP
8 21
4 HATCHING 5 21
A 5 LABELS 1 21
SUBTOTAL 34
TOTAL 96
OFFICE PENALTIES (-)
A
CONCRETE SLAB
GRAND TOTAL
NAME
FLOOR PLAN DETAILED SECTION A-A
SCALE 1 : 50 SCALE 1 : 20 NAME 6
Copyright reserved
Hosted by www.ecexams.co.za.
Study this subject
Recommended for this subject

Memorandum
Engineering Graphics and Design Grade 12 P2 2024 Memo (Eng)

Question paper
Engineering Graphics and Design Grade 12 P1 2023 QP (Eng)

Question paper
Engineering Graphics and Design Grade 12 P1 2022 QP (Eng)

Question paper
Engineering Graphics and Design Grade 12 P1 NSC June 2021 QP

Question paper
Engineering Graphics and Design Grade 12 P1 NSC June 2021 QP

Question paper
Engineering Graphics and Design Grade 12 P1 2021 QP (Afr)
More from Grade 12 Engineering Graphics and Design

Memorandum
Engineering Graphics and Design Grade 12 P1 2025 Memo

Memorandum
Engineering Graphics and Design Grade 12 P2 2025 Memo (Eng)

Memorandum
Engineering Graphics and Design Grade 12 P2 2025 Memo

Memorandum
Engineering Graphics and Design Grade 12 P1 2023 Memo (Afr)

Question paper
Engineering Graphics and Design Grade 12 P2 2023 QP

Question paper