Civil Technology Grade 12 NSC Supplementary 2018 Memo (Eng)

MemorandumCivil TechnologyGrade 12201815 pages

Grade 12 Civil Technology memorandum from the NSC Supplementary Exam 2018 (English), 15 pages. Read online or download the free PDF.

Free to read online, no sign-up needed

Loading document…

Loading document…

Document textSearch extracted text and jump to a page.
Downloaded from hlayiso.com GRAAD 12 NATIONAL SENIOR CERTIFICATE GRADE 12 CIVIL TECHNOLOGY FEBRUARY/MARCH 2018 MARKING GUIDELINES MARKS: 200 These marking guidelines consist of 15 pages. Copyright reserved Please turn over
Downloaded from hlayiso.com Civil Technology 2 DBE/Feb.–Mar. 2018 NSC – Marking Guidelines QUESTION 1: CONSTRUCTION, SAFETY AND MATERIAL 1.1 1.1.1 B (1) 1.1.2 E (1) 1.1.3 A (1) 1.1.4 D (1) 1.1.5 F (1) 1.1.6 C (1) 1.1.7 H (1) 1.1.8 I (1) 1.1.9 G (1) 1.1.10 J (1) 1.2 1.2.1 A – To protect your feet against falling objects.  (1) 1.2.2 B – To protect your feet when working with wet material.  (1) 1.3 The paint conceals defects  (1) 1.4  Excavations must be fenced off.   Red warning lights should be placed at intervals to warn the public.   All excavations must take place under supervision.  The contractor must test the stability of the terrain before commencement of excavations.  Shoring should be cross braced.  Bracing should be strong enough to support the shoring.  No tools or materials other than those in use are allowed inside the trench when excavations are in progress.  Access to the excavation should be safe e.g. ladders can be used.  A responsible person must inspect and investigate underground electricity and water supply.  The sides should be braced and protected if deeper than 1,5 meters. ANY TWO OF THE ABOVE OR ANY OTHER ACCEPTABLE ANSWER (2) 1.5  Baseplate   Mould/Cube   Tamping rod   Plaster trowel/straight edge/shovel ANY THREE OF THE ABOVE (3) Copyright reserved Please turn over
Downloaded from hlayiso.com Civil Technology 3 DBE/Feb.–Mar. 2018 NSC – Marking Guidelines 1.6  Water makes the fresh concrete workable.   Water acts as a lubricant.  Water is also needed for the hydration process. ANY ONE OF THE ABOVE (1) 1.7 1.7.1 To prevent moisture from getting into the building.  (1) 1.7.2 To prevent moisture from moving up in the walls.  (1) 1.8  Preservatives with a base of water-soluble salts.   Varnish ANY ONE OF THE ABOVE (1) 1.9 Roof tiles/Clay tiles/Concrete tiles  (1) 1.10 Ridge capping  (1) 1.11 Gang nails/plate connectors  (1) 1.12      ASSESSMENT CRITERIA MARK CANDIDATES MARK One brick wall 2 Half brick wall 1 (T-junction) Three-quarter bricks 2 TOTAL 5 (5) [30] Copyright reserved Please turn over
Downloaded from hlayiso.com Civil Technology 4 DBE/Feb.–Mar. 2018 NSC – Marking Guidelines QUESTION 2: ADVANCED CONSTRUCTION AND EQUIPMENT ANSWER THIS QUESTION ON A NEW PAGE. 2.1 2.1.1 C (1) 2.1.2 D (1) 2.1.3 A (1) 2.1.4 B (1) 2.1.5 A (1) 2.2 2.2.1 Portable electric generator  – It is used to generate electricity  (2) 2.2.2 Portable electric circular saw  – It is used for cross cutting and ripping of timber.  (2) 2.3 Chalk line  (1) 2.4  Flat steel square   Tape measure ANY ONE OF THE ABOVE (1) 2.5  Rough arch will be built with common bricks   Gauge arch will be built with face bricks  (2) 2.6 2.6.1 Driven in-situ pile  (1) 2.6.2  Low bearing capacity of soil   Subsoil – subjected to movement   Subsoil – subjected to high moisture content.  Recently placed filling materials that is not sufficiently compacted  Unstable soil structure  High water table ANY TWO OF THE ABOVE (2) 2.6.3 Steel reinforcement  (1) 2.7 2.7.1 Twisted square bar  (1) 2.7.2 Round bar (mild steel)  (1) 2.8 A – Landing  B – Rise  C – Tread  (3) Copyright reserved Please turn over
Downloaded from hlayiso.com Civil Technology 5 DBE/Feb.–Mar. 2018 NSC – Marking Guidelines 2.9  Blow holes   Uneven colour/discoloration   Honey comb effect/Leaking of grout ANY TWO OF THE ABOVE (2) 2.10 2.10.1 Cavity wall  (1) 2.10.2  A – Wall tie   Keeps the two skins of the wall securely together.   It strengthens the wall ANY TWO OF THE ABOVE (2) 2.10.3  B – Weak concrete mixture   Concrete mixture ANY ONE OF THE ABOVE (1) 2.10.4  To strengthen the wall below the DPC (damp proof course)   To close the cavity below the damp proof course ANY ONE OF THE ABOVE (1) 2.10.5 C – Damp-proof membrane  (1) 2.10.6 50 mm  (Unit must be part of the answer) (1) 2.11 2.11.1 A – Cladding (or any cladding material)  B–  Timber floor board   Base plate  Base board ANY ONE OF THE ABOVE FOR B (2) 2.11.2  Steel   Metal  Aluminium ANY ONE OF THE ABOVE (1) 2.11.3  There is no wet material   There is no heavy material to carry   Dry walls are light in weight.  Dry walls are easier to install  Dry walls are easy to remove if required ANY TWO OF THE ABOVE (2) 2.12 2.12.1 Rib and Block floor  (1) 2.12.2 A – Rib  B – Hollow block/Block  C – Reinforcing steel/Steel rod/Reinforcement  (3) [40] Copyright reserved Please turn over
Downloaded from hlayiso.com Civil Technology 6 DBE/Feb.–Mar. 2018 NSC – Marking Guidelines QUESTION 3: CIVIL SERVICES 3.1 3.1.1 P-trap  (1) 3.1.2 Washbasin/Urinal/Shower/Sink  (1) ANY ONE 3.2 3.2.1 A-Is the inlet pipe for cold water  B-Is the outlet pipe for warm water  (2) 3.2.2 To shut down water supply during maintenance.  ANY OTHER ACCEPTABLE ANSWER (1) 3.2.3  To prevent water from leaking through the ceiling   It is compulsory to install a drip tray ANY ONE OF THE ABOVE (1) 3.3 3.3.1 Storm water is hail, snow, rain that falls to the earth in large quantities.  ANY OTHER ACCEPTABLE ANSWER (1) 3.3.2 Storm water is guided into the channels where after the water is guided to storm water pipes and catchment areas.  ANY OTHER ACCEPTABLE ANSWER (1) 3.4 Water in shallow wells is:  Easily dug out   Cheap  Relatively reliable ANY ONE OF THE ABOVE (1) 3.5 Wind pump  (1) Copyright reserved Please turn over
Downloaded from hlayiso.com Civil Technology 7 DBE/Feb.–Mar. 2018 NSC – Marking Guidelines 3.6 C X   FRIDGE B A   ASSESSMENT MARK CANDIDATE'S CRITERIA MARK 2 way light switch 2 Socket outlet 2 Light 2 Electrical wire 2 TOTAL 8 (8) Copyright reserved Please turn over
Downloaded from hlayiso.com Civil Technology 8 DBE/Feb.–Mar. 2018 NSC – Marking Guidelines 3.7 ANSWER SHEET 3.7      IE IE IE  IE  MH  VP  G WHB S  WC SH   Conservancy tank ASSESSMENT MARK CANDIDATE'S CRITERIA MARK Rodding eye 1 Gully 1 Vent pipe 1 Main sewerage pipes 2 Inspection eyes 4 Manhole 1 Any TWO abbreviations for the 2 sanitary fixtures (12) TOTAL 12 [30] Copyright reserved Please turn over
Downloaded from hlayiso.com Civil Technology 9 DBE/Feb.–Mar. 2018 NSC – Marking Guidelines QUESTION 4: QUANTITIES, MATERIALS AND JOINING 4.1 4.1.1  Gang nail  (1) USE:  Gang nails are used to join the members of roof trusses.   Extend the length of a timber board/beam. ANY ONE OF THE ABOVE USES (1) 4.1.2  Bolt and nut  (1) USE:  Bolts and nuts are used to join the members of roof trusses.   Join material to brackets  To fix truss hangers to rafters ANY ONE OF THE ABOVE USES (1) 4.1.3  Dry wall screw  (1) USE:  Drywall screws are used to fix dry wall materials.   Joining ceilings and battens to other members  Joining timber to each other ANY ONE OF THE ABOVE USES (1) 4.2  Rawl bolt/Expansion anchor   Sleeve anchor  Dina bolt ANY ONE OF THE ABOVE (1) 4.3  Compression joint   Capillary joint ANY ONE OF THE ABOVE (1) 4.4  Screws have greater holding power than nails   They can be fixed where vibration has to be avoided   Screws can easily be removed  The appearance of screws is better in finishing than nails ANY TWO OF THE ABOVE (2) 4.5 4.5.1 38 or 38 mm  (1) 4.5.2 2 349 or 2 349 mm  (1) 4.5.3 5√ (1) 4.5.4 2 575 or 2 575 mm  (1) 4.5.5 5 150 or 5 150 mm  (1) 4.5.6 4 500 or 4 500 mm  (1) 4.5.7 10 300 or 10 300 mm  (1) Copyright reserved Please turn over
Downloaded from hlayiso.com Civil Technology 10 DBE/Feb.–Mar. 2018 NSC – Marking Guidelines 4.6 A B C D Inside measurement of: Long walls = 6 500 – 2/220  = 6 060 mm  Short walls = 3 800 – 2/220  = 3 360 mm  (4) 1/ 6,06 Inside floor area of the room is 3,36  20,36 m2  (2) Area of one ceiling board: 1/ 3,9 One board is 3 900 mm x 900 mm 2 0,9  3,51 m  (3) Length of skirting: = 2(6 060 + 3 360 ) – 900 mm  = 17,94 m  OR 12 120 + 6 720 - 900 =17,94 m OR 6 060 + 6 060 + 3 360 + 3 360 - 900 =17,94 m (4) (13) [30] Copyright reserved Please turn over
Downloaded from hlayiso.com Civil Technology 11 DBE/Feb.–Mar. 2018 NSC – Marking Guidelines QUESTION 5: APPLIED MECHANICS 5.1 5.1.1 (A1 x d) + (A2 x d) Total area     = (3 200 x 20) + (900 x 60) 4 100    = 64 000 mm + 54 000 mm3 3 4 100 = 118 000 mm3  4 100 mm2 = 28,78  mm  OR Part Area (A) Y AY 1 3 200 mm²  20 mm  3 200 x 20 = 64 000 mm3  2 900  mm² 60 mm  900 mm x 60 mm = 54 000 mm3  ∑ 4 100 mm²  118 000 mm3 Y  Ay A = 118 000 mm3  4 100 mm2 = 28,78  mm  (10) Copyright reserved Please turn over
Downloaded from hlayiso.com Civil Technology 12 DBE/Feb.–Mar. 2018 NSC – Marking Guidelines 5.2.1 60 N B 40 N C F G A 30° E 30° 60° 60° D 10 m RL = 45 N RR = 55 N a   b  g e d    f   c (8) 5.2.2 MEMBER NATURE MAGNITUDE FG Tie  23 N  (4) BF Strut  50 N  Tolerance of 1 N to either side NOT TO SCALE DUE TO ELECTRONIC TRANSFER USE A MASK TO MARK THIS QUESTION Copyright reserved Please turn over
Downloaded from hlayiso.com Civil Technology 13 DBE/Feb.–Mar. 2018 NSC – Marking Guidelines 5.3 5.3.1 40 Nm  (1) 5.3.2 7m (1) 5.3.3 3m (1) 5.3.4 10 N 40 N 20 N 20 N/m 2m 2m 3m 3m A B C D E F RL = 66 N RR = 44 N 204 Nm   178 Nm  132 Nm 132 Nm   0 Nm 0 Nm A B C D E F (5) SCALE 1 mm = 2 Nm NOT TO SCALE DUE TO ELECTRONIC TRANSFER USE A MASK TO MARK THIS QUESTION If the bending moment diagram is not to scale, deduct 1 mark. Marks are allocated for each line between A to F. If the lines between B and D are straight lines no marks will be awarded for these lines. [30] Copyright reserved Please turn over
Downloaded from hlayiso.com Civil Technology 14 DBE/Feb.–Mar. 2018 NSC – Marking Guidelines ANSWER SHEET 6.1 NO. QUESTIONS ANSWERS MARKS 1 Name the scale used for the West 1:100  elevation. 1 2 Identify number 1. Barge board  1 3 Identify number 2. Window/window pane/glass 1 casement  4 Identify number 3. Door/door opening  1 5 Identify number 4. FFL/Finished floor level  1 6 Identify number 5. Step  1 7 Identify number 6. NGL/Natural ground level  1 8 Identify number 7. Window sill  1 9 Name the material that can be Fibre cement  used for the soffit board at a closed 1 eave? 10 Recommend a suitable exterior Paint/plaster/face brick/ 1 finish for the wall. cladding  11 Deduce on which elevations will the North elevation  and South gutters be placed in this house? 2 elevation 12 Draw the roof lines for the roof of   the building shown in FIGURE 6.1 3 in the column alongside.  TOTAL 15 Copyright reserved Please turn over
Civil Technology Downloaded from hlayiso.com 15 DBE/Feb.–Mar. 2018 NSC – Marking Guidelines QUESTION 6: GRAPHICS AND COMMUNICATION ASSESSMENT MARKS LM CRITERIA ANSWER SHEET 6.2 Correctness of 3 drawing External wall 1 Symbol for wall 1  Plaster 2 Wall plate 1   Tie beam 1 King post Rafter Rafters 2 King post 1 Brandering 1  Ceiling board 1  Cornice 1 Fascia board 1 Print title and scale 2  Tie beam  Any FOUR labels 4    Application of scale: One or two incorrect  =3  Three or four incorrect =2   More than five Fascia board incorrect = 1 No measurement  correct = 0 3   TOTAL 25 SECTION B–B   SCALE 1:20 NOT TO SCALE: USE A MASK TO MARK THIS QUESTION Correctness of drawing  All parts of the drawing must be correctly drawn to receive a mark. [40]   If the section is drawn the wrong way around deduct 1 mark. 200 Copyright reserved