Downloaded from hlayiso.com
NATIONAL
SENIOR CERTIFICATE
GRADE 12
SEPTEMBER 2018
CIVIL TECHNOLOGY: CONSTRUCTION
MARKING GUIDELINE
MARKS: 200
This marking guideline consists of 12 pages.
Skip to contentAll 2018 papers _hlayiso.com_--b6d609b6-89a5-4b39-a9b7-0d878af45cd4/v1-9c90f1958077961e2845/card.webp)





View all
%20(English%20and%20Afrikaans)%20June%202025%20Question%20Paper--c8edd459-5237-48e0-8588-69d7ecd7f8e5/v1-be996aaed91bf782e098/card.webp)
%20Afr--591d6ffd-20b1-4748-a1ba-b055be0a14c3/v1-4d98a131fd37e013458a/card.webp)
%20Afr--05a95faf-5891-4d88-9e5e-7d13c1d21648/v1-f5ca67113376f7457b83/card.webp)


Civil Technology Grade 12 Eastern Cape Mock 2018 Memo (Eng)
Grade 12 Civil Technology memorandum from the Eastern Cape Mock Exam 2018 (English), 12 pages. Read online or download the free PDF.
Civil Technology · Grade 12 · Eastern Cape Mock Exam · 2018. Memorandum, 12 pages. Read online or download the PDF.
- Subject
- Civil Technology
- Grade
- Grade 12
- Document type
- Memorandum
- Year
- 2018
- Exam period
- Eastern Cape Mock Exam
- Curriculum
- CAPS
- Pages
- 12
- File size
- 292.8 KB
Free to read online, no sign-up needed
Loading document…
Loading document…
1 of 12
This exam
Eastern Cape Mock Exam 2018
- Other filesQuestion paper · EngQuestion paper · Eng (2)Question paper · Eng (3)Question paper · Eng (4)Question paper · Eng (5)Question paper · Eng (6)Question paper · AfrQuestion paper · Afr (2)Question paper · Afr (3)Question paper · Afr (4)Question paper · Afr (5)Question paper · Afr (6)Memo · EngMemo · Eng (2)Memo · Eng (3)Memo · Eng (4)Memo · Eng (5)Memo · Eng (6)Memo · Eng (7)Memo · Eng (8)Memo · Eng (9)Memo · AfrMemo · Afr (2)Memo · Afr (3)Memo · Afr (4)Memo · Afr (5)Memo · Afr (6)Memo · Afr (7)Memo · Afr (8)Memo · Afr (9)
Document textSearch extracted text and jump to a page.
Downloaded from hlayiso.com
2 CIVIL TECHNOLOGY: CONSTRUCTION (EC/SEPTEMBER 2018)
QUESTION 1: SAFETY, MATERIAL AND EQUIPMENT (GENERIC)
1.1 1.1.1 True (1)
1.1.2 False (1)
1.1.3 False (1)
1.1.4 True (1)
1.2 Any THREE requirements to which a trestle scaffold must comply.
Soundly constructed with a solid material
Prevent spreading of supporting legs
Not higher than 3 m
Consists of not more than 2 tiers (3 x 1) (3)
1.3 Similar answer.
(1) Aluminium conducts (2) electricity / workers subjected to electrical shock (2)
1.4 Similar answer.
(1) Paint will cover (2) weaknesses (2)
1.5 1.5.2 Improves the durability of concrete. (1)
1.5.5 It improves the strength of concrete. (1)
1.5.7 It makes concrete more watertight. (1)
1.5.8 It improves the resistance to abrasion. (1)
1.6 (1) Plastic finish / coating (2) in powder form by (3) using a spray-gun (3)
1.7 Briefly describe any ONE use of the dumpy level.
(1) Determine (2) height differences
(1) Determine (2) levels and slopes
(1) Setting out (2) of buildings
(1) Transferring of (2) levels and heights
(1) Determine horizontal (2) distances (1 x 2) (2)
1.8 1.8.1 1,5 m (1)
1.8.2 1,535 – 1,47 x 100 = 6,5 m (4)
1.9 Any THREE materials which can be detected in walls by the multi-detector.
Ferrous metals
Non-ferrous metals
AC wiring
Wood
Metal studs
Steel bars
Copper pipes (3 x 1) (3)
1.10 1.10.1 Dry, soft cloth / Not cleaning agents or solvents (1)
1.10.2 Remove battery (1)
[30]
Copyright reserved Please turn over
Downloaded from hlayiso.com
(EC/SEPTEMBER 2018) CIVIL TECHNOLOGY: CONSTRUCTION 3
QUESTION 2: GRAPHICS AND JOINING (GENERIC)
2.1 Use the information on ANSWER SHEET A and complete the site plan on
scale 1 : 200 according to the following requirements:
2.1.1 The site boundaries are measured from point A
The site boundaries in front and back are 23 m long
The site boundaries on the sides are 25 m long (2)
2.1.2 The front building line is 4 m from the site boundary
The back and side building lines are 2 m from the site boundaries (2)
2.1.3 Show the site entrance, 3 m from the western site boundary (1)
2.1.4 Show the datum level in the north-eastern corner of the site
Complete the sewage lay-out and abbreviations of the sewage
appliances according to the following requirements: (1)
2.1.5 The main sewage from the bathroom to the municipal connection (2)
2.1.6 The branch sewage to the bathroom and kitchen (2)
2.1.7 Manhole on the site, before the municipal connection (2)
2.1.8 Rodding eyes (4)
2.1.9 Inspection eyes (4)
2.2 Length of shank
Diameter
Type of thread
Head size (4 x 1) (4)
2.3 (1) When square shoulder is driven in (2) it resists rotation (2)
2.4 2.4 A – Nut
2.4 B – Thread
2.4 C – Runout
2.4 D – Shank (4)
[30]
Copyright reserved Please turn over
Downloaded from hlayiso.com
4 CIVIL TECHNOLOGY: CONSTRUCTION (EC/SEPTEMBER 2018)
QUESTION 3: CONCRETE, EXCAVATIONS, FOUNDATIONS & QUANTITIES
(SPECIFIC)
3.1 3.1.1 Rib-and-block floor (1)
3.1.2 3.1.A – Concrete floor block (1)
3.1.B – Precast concrete rib (1)
3.1.3 ONE instance where this type of floor construction will be used:
Basements
First floors
Roof slabs (1)
3.1.4 150 mm (1)
3.1.5 200 mm (1)
3.2 3.2.1 Slump test (1)
3.2.2 Any TWO purposes of the slump test:
Test the density by determining the water content
Determine the workability and consistency of batches
Determine the slump of the mixture (2 x 1) (2)
3.2.3 16 mm (1)
3.2.4 25 Times (1)
3.2.5 On the building site (1)
3.3 Any THREE – describe the purpose of curing concrete:
That the hydration of cement can continue
Newly placed concrete must be protected against quick drying
Achieve optimal strength
Achieve optimal hardness (3 x 1) (3)
3.4 Any THREE methods of curing concrete:
Sprinkling
Cover with water-retaining substances such as sand, hessian etc.
Cover with plastic membranes or plastic sheeting
Commercial seal compound (3 x 1) (3)
3.5 Any THREE methods to make excavations safe at night:
Fencing
Visible warning signs
Red or orange warning lights
Covering over excavations (3 x 1) (3)
Copyright reserved Please turn over
Downloaded from hlayiso.com
(EC/SEPTEMBER 2018) CIVIL TECHNOLOGY: CONSTRUCTION 5
3.6 Any FOUR causes for an excavation collapse:
Heavy rains
Poor soil strata, structure or composition
Sides not dug at the correct angle
Improper use of formwork or shoring to support the walls
Vibration by machinery or heavy vehicles nearby
Water seeping into the excavated area
Contact with underground services
Access to and exit from the excavation
Soil slides due to cracks or loose soil (4 x 1) (4)
3.7 3.7.1 False (1)
3.7.2 True (1)
3.7.3 False (1)
3.7.4 True (1)
3.8 Any FOUR advantages of using pile foundations:
Can be used in poor soil
Can be used anywhere, even in water
The larger base ensures stability
Relatively quick and easy to install if equipment is available
If pre-fabricated piles are used, much time is saved
Quick and less expensive to produce
Resist tensile stress well
Can be manufactured elsewhere and transported to the site
Installation continue even if poor weather conditions hamper
excavations
Length of piles can be adjusted, depending on the circumstances
It offers good resistance against moving soil (4 x 1) (4)
3.9 Any TWO types of foundations (pile- / block foundation excluded):
Strip foundation
Stepped foundation
Raft foundation (2 x 1) (2)
3.10 2 / 6 000 = 12 000 mm √
2 / 4 000 = 8 000 mm √
= 20 000 mm √
Corners: 4 / 600 = - 2 400 mm √
Centre line = 17 600 mm √ (5)
[40]
Copyright reserved Please turn over
Downloaded from hlayiso.com
6 CIVIL TECHNOLOGY: CONSTRUCTION (EC/SEPTEMBER 2018)
QUESTION 4: REINFORCEMENT, FORMWORK, MATERIALS AND EQUIPMENT
(SPECIFIC)
4.1 4.1.1 High-tensile or high yield steel (1)
4.1.2 200 mm (1)
4.1.3 6 Bars (1)
4.1.4 12 mm (1)
4.2 4.2.1 4.2.A – Anchor bar (1)
4.2.B – Stirrups (1)
4.2.C – Main bar (1)
4.2.D – Shear bar (1)
4.2.2 Any TWO describing the purpose of the stirrups:
Support the shear bars
Space and support the main bars
Prevent the tearing of concrete (2)
4.3 Compression (1); Tensile (1); Lateral (1) forces (3)
4.4 Any TWO describing the purpose of cover depth for reinforced concrete:
To protect steel against corrosion
To ensure adequate bonding between the steel and concrete
To ensure adequate protection of steel in the event of a fire (2)
4.5 Any THREE materials to line formwork – smoother finish:
Plastic
Metal sheeting
Hard board
Fibre-glass (3 x 1) (3)
4.6 Any TWO defects that can occur in concrete due to shuttering:
Blowholes
Uneven colour (discolouration)
Weakening of structure or collapse (2 x 1) (2)
4.7 Any FOUR properties of good formwork:
Made accurately according to the dimensions indicated
Sturdy enough to bear the mass of wet concrete without collapsing
Able to bear the mass of workers and equipment
Must be strong enough to provide sufficient support, without too much
deflection, until the concrete has set
Formwork should be easy to repair on site
Secured with wire nails, where some should protrude for easy extracting
Secured with bolts from 13 mm to 19 mm in diameter
Should be sealed properly so that the concrete does not leak and form
honeycombs or fins
Copyright reserved Please turn over
Downloaded from hlayiso.com
(EC/SEPTEMBER 2018) CIVIL TECHNOLOGY: CONSTRUCTION 7
Should be free of dirt (sawdust or releasing agents)
Quick and simple to erect, mechanically or by hand
Ensure the correct cover depth for reinforcing, to prevent structural failure
Fit plywood onto laggings if a smooth finish is required
Remove when the concrete has cured and is able to support load on its
own
Should be easy to remove without damaging the formwork or concrete
Close-fitting along seams and joints
Made from recyclable components (Any 4 x 1) (4)
4.8 Choose a description in COLUMN B that matches an item in COLUMN A.
4.8.1 C (High volumes of concrete) (1)
4.8.2 J (Used as awnings) (1)
4.8.3 I (30 MPa compressive strength) (1)
4.8.4 K (High antibacterial properties) (1)
4.8.5 G (Small volumes of concrete) (1)
4.8.6 A (Hard, brittle and breaks easily) (1)
4.8.7 B (Low toxicity) (1)
4.8.8 D (Packing of equipment) (1)
4.9 Identify the metals as FERROUS or NON-FERROUS:
4.9.1 Non-ferrous (1)
4.9.2 Ferrous (1)
4.9.3 Non-ferrous (1)
4.9.4 Ferrous (1)
4.9.5 Non-ferrous (1)
4.10 4.10.1 Portable concrete vibrator (1)
4.10.2 Concrete mixer (1)
4.10.3 Plate compactor (1)
[40]
Copyright reserved Please turn over
Downloaded from hlayiso.com
8 CIVIL TECHNOLOGY: CONSTRUCTION (EC/SEPTEMBER 2018)
QUESTION 5: ROOFS, BRICK WALLS AND GRAPHICS (SPECIFIC)
5.1 5.1.1 Closed eave (1)
5.1.2 Any TWO advantages of the closed eave:
Provides a more attractive appearance
Prevent animals from entering (insects, birds and vermin etc.)
No beam filling required (2 x 1) (2)
5.1.3 Any TWO types of material that can be used at the closed eave:
Soffit board or fibre-cement board
Wire netting
Pegboard (2 x 1) (2)
5.2 Any THREE for discussing the purpose of beam filling:
To keep out insects and vermin
Prevent wind / dust from blowing under the roof
Prevent birds from nesting in the roof
Improve the stability of the roofing rafters
Improve the insulation of the building (3 x 1) (3)
5.3 A Rafter (1)
B Queen post (1)
C King post (1)
D Strut (1)
E Tie beam (1)
5.4 5.4.1 50 mm (1)
5.4.2 3m (1)
5.5 Any THREE disadvantages of cavity walls:
Require expert designs / higher design standards
Require highly skilled workmanship
Constant supervision is needed during construction
Cavities are filled with vertical damp-proof course
More expensive than solid wall constructions
50 to 100 mm of the internal space is lost (3 x 1) (3)
5.6 Any TWO types of wall ties that can be used in cavity walls:
Butterfly pattern
Nylon wall tie
Twisted pattern
Double triangular pattern (2 x 1) (2)
5.7 A Weep hole (1)
B Concrete floor (1)
C Hard-core filling (1)
D Concrete filling (1)
5.8 See ANSWER SHEET B – Isometric view of pier on block foundation (6)
[30]
Copyright reserved Please turn over
Downloaded from hlayiso.com
(EC/SEPTEMBER 2018) CIVIL TECHNOLOGY: CONSTRUCTION 9
QUESTION 6: SCREEDS, STAIRS, BRICKWORK AND QUANTITIES
(SPECIFIC)
6.1 Any ONE type of sand that can be used as bedding sand for pavers:
River sand
Crusher dust (1)
6.2 Any FOUR advantages of mortar set pavers:
Little maintenance is required
Low life-cycle cost
Resistant to point loads
Resistant to fatigue and reflecting traffic patterns
Resistant to edge movement
User-friendly installation material is used
No weeds will be able to grow in between the joints
No off-gassing installation products used
Insects will not be able to ruin the appearance of the paved structure
(4 x 1) (4)
6.3 6.3.1 True (1)
6.3.2 False (1)
6.3.3 True (1)
6.3.4 False (1)
6.4 See ANSWER SHEET C – Determine the amount of bricks needed (12)
6.5 Any THREE types of materials that can be used for cladding:
Tile cladding
Brick slip cladding
Stone cladding
Timber cladding
Metal sheet cladding (3 x 1) (3)
6.6 Any TWO types of screeds:
Dry screed
Monolithic screed
Bonded screed (2)
6.7 A Hand rail (1)
B Baluster (1)
C Thread or going (1)
D Riser (1)
[30]
TOTAL: 200
Copyright reserved Please turn over
Downloaded from hlayiso.com
10 CIVIL TECHNOLOGY: CONSTRUCTION (EC/SEPTEMBER 2018)
CIVIL TECHNOLOGY
ANSWER SHEET A (GENERIC)
NAME:
2.1 Use the information on ANSWER SHEET A and complete the site plan to
scale 1 : 200.
ERF 121 ERF 123 ERF 125
RE
IE IE RE
KITCHEN BATHROOM
A
MH
A
PARLEMENT STREET
Site boundaries 2
Building lines 2
Site entrance 1
Datum level 1
Main sewerage 2
Branch sewerage 2
Manhole 2
Rodding eyes 4
Inspection eyes 4
TOTAL 20
Copyright reserved Please turn over
Downloaded from hlayiso.com
(EC/SEPTEMBER 2018) CIVIL TECHNOLOGY: CONSTRUCTION 11
CIVIL TECHNOLOGY
ANSWER SHEET B CONSTRUCTION
NAME:
5.8 Use ANSWER SHEET B and draw an isometric view of a pier on a block
foundation. Use own scale.
One-and-a-half brick pier 2
Stretcher bond 1
5 Brick layers 1
Block foundation 2
TOTAL 6
PIER ON BLOCK FOUNDATION
NOT TO SCALE
Copyright reserved Please turn over
Downloaded from hlayiso.com
12 CIVIL TECHNOLOGY: CONSTRUCTION (EC/SEPTEMBER 2018)
CIVIL TECHNOLOGY
ANSWER SHEET C CONSTRUCTION
NAME:
QUESTION 6.4
A B C D
Brick calculation:
1/ 6.5 m
2.8 m √ 18,2 m² √ Total wall area
√
Bricks:
1/ 18.2
100 √ 1820 √ Total number of bricks
Deductions:
1/ 0.9 m Opening A
2.1 m √ 1,89 m² √ Total area
√
1/ 1.89
100 √ 189 √ Total number of bricks for opening A
Total number of bricks needed:
1 820 - 189 √ = 1631 bricks √
(12)
Copyright reserved Please turn over
Study this subject
Recommended for this subject
_hlayiso.com_--b6d609b6-89a5-4b39-a9b7-0d878af45cd4/v1-9c90f1958077961e2845/card.webp)
Memorandum
Civil Technology Grade 12 Eastern Cape Mock 2018 Memo (Eng)

Memorandum
Civil Technology Grade 12 Eastern Cape Mock 2018 Memo (Afr)

Memorandum
Civil Technology Grade 12 Eastern Cape Mock 2018 Memo (Afr)

Memorandum
Civil Technology Grade 12 Eastern Cape Mock 2018 Memo (Eng)

Memorandum
Civil Technology Grade 12 Eastern Cape Mock 2018 Memo (Afr)

Memorandum
Civil Technology Grade 12 Eastern Cape Mock 2018 Memo (Afr)
More from Grade 12 Civil Technology

Question paper
Civil Technology Grade 12 Eastern Cape Mock 2025 QP (Eng)
%20(English%20and%20Afrikaans)%20June%202025%20Question%20Paper--c8edd459-5237-48e0-8588-69d7ecd7f8e5/v1-be996aaed91bf782e098/card.webp)
Question paper
Civil Technology Grade 12 Gauteng June 2025 QP (Afr)
%20Afr--591d6ffd-20b1-4748-a1ba-b055be0a14c3/v1-4d98a131fd37e013458a/card.webp)
Question paper
Civil Technology Grade 12 NSC June 2025 Question Paper (Afr)
%20Afr--05a95faf-5891-4d88-9e5e-7d13c1d21648/v1-f5ca67113376f7457b83/card.webp)
Question paper
Civil Technology Grade 12 NSC November 2025 QP (Afr)

Question paper
Civil Technology Grade 12 Eastern Cape Prelim 2024 QP (Afr)

Question paper