CIVIL TECHNOLOGY: CIVIL SERVICES
2023
MARKS: 200
TIME: 3 hours
This question paper consists of 14 pages and 7 answer sheets.
Copyright reserved Please turn over
Skip to contentAll 2023 papers 




%20Afr_hlayiso.com_--b820ac91-947c-4aed-821f-256aa13aabe1/v1-3be01795eace6f81b174/card.webp)
View all%20MG%20Eng--0e265899-dc44-4809-aabf-8f374f1af392/v1-73a07814cfc9334618a1/card.webp)



%20%20MG%20Afr_hlayiso.com_--42b5315c-825c-40e3-b394-85e0253fc0fb/v1-6058b260e68654519cc3/card.webp)
%20Afr_hlayiso.com_--f6f7ac38-fb55-4d61-bc66-5441e4cbcee0/v1-b3313a875de5f3475dc0/card.webp)
Civil Technology Grade 12 NSC June 2023 Question Paper (Eng)
Grade 12 Civil Technology question paper from the NSC June Exam 2023 (English), 23 pages. Read online or get the free PDF download, memo linked when available.
Civil Technology · Grade 12 · NSC June Exam · 2023 · English. Question paper, 23 pages. Read online or download the PDF.
- Subject
- Civil Technology
- Grade
- Grade 12
- Language
- English
- Document type
- Question paper
- Year
- 2023
- Exam period
- NSC June Exam
- Curriculum
- CAPS
- Pages
- 23
- File size
- 881.0 KB
Free to read online, no sign-up needed
Loading document…
Loading document…
1 of 23
This exam
Document textSearch extracted text and jump to a page.
Civil Technology: Civil Services 2 DBE/2023
SC/NSC
REQUIREMENTS:
1.
2.
3.
Drawing instruments
A non-programmable calculator
ANSWER BOOK
INSTRUCTIONS AND INFORMATION
1.
2
3.
4
a
o 7 N ®
11,
12.
13.
14.
15.
16.
17.
18.
This question paper consists of SIX questions.
Answer ALL the questions.
Read ALL the questions carefully.
Answer each question as a whole. Do NOT separate subsections of
questions.
Number the answers correctly according to the numbering system used in this
question paper.
Start the answer to EACH question on a NEW page.
Do NOT write in the margins of the ANSWER BOOK.
You may use sketches to illustrate your answers.
Write ALL calculations and answers in the ANSWER BOOK or on the
attached ANSWER SHEETS.
Use the mark allocation as a guide to the length of your answers.
Make drawings and sketches in pencil, fully dimensioned and neatly finished
off with descriptive titles and notes to conform to the SANS/SABS Code of
Practice for Building Drawings.
For the purpose of this question paper, the size of a brick should be taken as
220 mm x 110 mm x 75 mm.
Use your own discretion where dimensions and/or details have been omitted.
Answer QUESTIONS 2, 3.10, 4.9, 5.5, 6.3, 6.5 and 6.7 on the attached
ANSWER SHEETS using drawing instruments, where necessary.
Write your CENTRE NUMBER and EXAMINATION NUMBER on every
ANSWER SHEET and hand them in with your ANSWER BOOK, whether you
have used them or not.
Drawings in the question paper are NOT to scale due to electronic transfer.
Google Images was used.as the source of all photographs and pictures.
Write neatly and legibly.
Copyright reserved Please turn over
Civil Technology: Civil Services 3 DBE/2023
SC/NSC
QUESTION 1: OHSA, MATERIALS, TOOLS, EQUIPMENT AND JOINING
(GENERIC)
Start this question on a NEW page.
1.1 FIGURE 1.1 below shows a temporary platform that is currently not suitable
for use in the building environment.
FIGURE 1.1
1.4.4 Identify THREE parts that have been omitted from the structure that
will negatively impact on the safety of workers. (3)
1.1.2 Predict what could happen if the platform is used as shown in
FIGURE 1.1. (2)
1.2 Choose the correct word(s) from those given in brackets. Write only the
word(s) next to the question numbers (1.2.1 to 1.2.5) in the ANSWER BOOK,
e.g. 1.2.6 casement.
1.2.1 Oil-based paint can be applied to protect ferrous metal against
(shrinkage/rust/bending). (1)
1.2.2 Galvanising is the process to cover iron or steel with a layer of
(aluminium/lead/zinc). (1)
41.2.3 The strength of concrete can be increased by (adding lime/keeping
it moist/drying it quickly). : (1)
1.2.4 Electroplating is the process of coating (metal/lead/plastic) with a
thin layer of another material. (1)
1.2.5 Powder coating is the process of applying a
(plastic/aluminium/copper) finish in powder form. (1)
Copyright reserved Please turn over
Civil Technology: Civil Services 4 DBE/2023
1.3
1.4
1.5
1.6
1.7
1.8
SC/NSC
Explain why it is advisable to keep the height of the guard rails between
900 to 1 000 mm above the scaffold working platform. (1)
Describe ONE precaution that must be adhered to when storing a ladder. (1)
Workers and materials are in a builder's hoist. Describe ONE check that the
operator needs to perform before the builder's hoist moves. (1)
Explain why the fire-fighting measures must be stated in the material safety
data sheet of hazardous chemical substances. (1)
FIGURE 1.7 below shows joining fixtures.
FIGURE 1.7
Identify A to D. (4)
A new building is being erected. Name the tool that can be used to:
1.8.1 Check if the height of doors and windows is at the same level (1)
1.8.2 Measure levels and slopes (1)
[20]
QUESTION 2: GRAPHICS AS MEANS OF COMMUNICATION (GENERIC)
Start this question on a NEW page.
FIGURE A and FIGURE B on the next page show drawings that appear on a building
plan. Analyse the drawings and complete the table on ANSWER SHEET 2.
Copyright reserved Please turn over
Civil Technology: Civil Services
5
SC/NSC
DBE/2023
220
220
aL ie
3510
. 220
4110 oy
110
| BEDROOM 2
BEDROOM 1
M7
220
4820, _|
3.020
FIGURE A
NOTES:
Contractors must verify all
dimensions and levels on site
before commencing work.
Architects to be notified
immediately of any discrepancies.
Wall thickness: External = 220 mm
Internal = 110 mm
Architect's signature
Client's signature
Concrete stairs according to the
engineer's specifications.
The ramp is finished off with
paving.
3.200 |
220
—+-—
KITCHEN
LOUNGE (
oo}
Al" T
2x40W
GARAGE
220
FIGURE B
DATE:
REVISION
1 26/03/2023
DRAWING
OF
STAIRCASE
DRAWING
OF
LIGHT
FITTINGS
DATE:
REVISION
- 2 28/03/2023
DATE OF PRINT:
30/03/2023
PRINTED BY:
XENO PRINTERS
DRAWING TITLE:
FLOOR PLANS PLOT 48
PROJECT:
PROPOSED DWELLING ON PLOT 48,
BENONI
DRAWING NO.:
226P7
PROJECT NO.:
GR 488-820
CHECKED:
PKRIEL
DATE:
24/03/2023
DRAWN:
KB BAM
FLOOR PLANS SCALE 1: 100
REFERENCE CODE:
QP 8— 2023
[40]
Copyright reserved
Please turn over
Civil Technology: Civil Services 6 DBE/2023
SC/NSC
QUESTION 3: CONSTRUCTION ASSOCIATED WITH CIVIL SERVICES, OHSA
AND QUANTITIES (SPECIFIC)
Start this question on a NEW page.
3.1 Name the maximum thickness of soil layers when compaction is done by
hand. (1)
3.2 Explain how the lid of a concrete ring manhole deeper than 750 mm should
be set to ensure airtightness. (2)
3.3 Name the length of the engineered bricks that are used in manhole
construction. (1)
3.4 Draw a two-dimensional sketch to show how the sides of excavations in loose
and water-logged soil should be supported. (7)
3.5 Name the tool and accessory that can be used to test if the slope of a drain
pipe is correct over a short distance. (2)
3.6 Who must monitor the free end of the rope attached to the safety harness of
the worker? (1)
3.7 Explain TWO safety precautionary measures that must be taken before a
worker enters a‘confined space to work. (2)
3.8 State TWO regulations that must be adhered to when working in elevated
places. (2)
3.9 The internal measurement of the sides of a cubic water storage tank is
3 700 mm.
Calculate the following. Show ALL calculations:
3.9.1 The volume of the tank in m? (4)
3.9.2 The volume of the tank in litres (2)
3.10 FIGURE 3.10 below shows the top view of a one-brick wall built in English
bond.
A
FIGURE 3.10
3.10.1 Identify A. (1)
3.10.2 Use ANSWER SHEET 3.10. Project and draw, in good proportion,
the FRONT VIEW of TWO consecutive brick courses. (6)
[30]
Copyright reserved Please turn over
Civil Technology: Civil Services DBE/2023
7
SC/NSC
QUESTION 4: COLD AND HOT-WATER SUPPLY, TOOLS, EQUIPMENT AND
MATERIALS (SPECIFIC)
Start this question on a NEW page.
44 Choose a description from COLUMN B that matches an item in COLUMN A.
Write only the fetter (A-L) next to the question numbers (4.1.1 to 4.1.8) in the
ANSWER BOOK, e.g. 4.1.9M
COLUMN A COLUMN B
4.1.1 Airlock A does not generate heat but moves
the heat instead
4.1.2 Heat pump
B sole purpose is to prevent water from
4.1.3. Pressure-control valve flowing back in the wrong direction
4.1.4 Vacuum breaker C hot-water outlet of a solar geyser
4.1.5 Stopcock D enables local authorities to calculate
the amount of water
4.1.6 Thermostat
Eto balance the water pressure of the
4.1.7 Solar geyser hot- and cold-water supply
4.1.8 Drip tray F regulates the heating of water
inside the geyser
G_used to close or shut off the water
supply
H_ the panels must face north
| collecting and draining away water
from a geyser
J no hot water, only a spluttering
K prevents the siphoning of water out of
a geyser when cold water is shut off
L _ self-sacrificing rod that protects the
geyser
(8x 1)
Copyright reserved Please turn over
(8)
Civil Technology: Civil Services 8 DBE/2023
SC/NSC
4.2 FIGURE 4.2 below is a picture of a device used in cold-water systems.
B A
Cc
FIGURE 4.2
4.2.1 Name the device.
4.2.2 Identify A, B and C.
4.2.3 Explain what will happen to C when A is turned 90°.
4.2.4 What is the valve used for?
4.3 FIGURE 4.3 below shows a blocked sewer pipe.
vs
A
| ©) /"———-WATER CLOSET OUTLET
Cc
B
FIGURE 4.3
4.3.1 Name a non-electrical hand tool that can be used to unclog the
sewer pipe.
4.3.2 Identify fittings A, B and C.
44 Differentiate between a compressed air test apparatus and a centrifugal pump
in terms of their use.
4.5 There is a constant running of water into the water closet pan. Identify the
possible problem.
Copyright reserved
Please turn over
(1)
(3)
(1)
(1)
(1)
(3)
(2)
(1)
Civil Technology: Civil Services 9 DBE/2023
SC/NSC
46 FIGURE 4.6 below shows a valve used in cold-water installation as a water-
saving device.
FIGURE 4.6
46.1 Name the valve.
46.2 Explain how this valve works.
47 Draw the following symbols that are used in hot-water systems:
4.7.1 Shower (movable)
4.7.2 Non-return valve
4.8 FIGURE 4.8 below shows a part in a solar water heater installation.
A
B
NN
c
™
FIGURE 4.8
4.8.1 Identify A, B and C.
4.8.2 What could be a clear sign that part A is malfunctioning?
49 ANSWER SHEET 4.9 shows an incomplete drawing of a high-pressure
geyser installed vertically against a wall without the cold- and hot-water pipes
and components. Draw the correct installation of the cold- and hot-water
pipes and indicate the direction of the flow of water with the TWO vacuum
breakers.
Copyright reserved Please turn over
(1)
(2)
(2)
(2)
(3)
(2)
(7)
[40]
Civil Technology: Civil Services 10 DBE/2023
SC/NSC
QUESTION 5: GRAPHICS AS MEANS OF COMMUNICATION, ROOF WORK AND
STORM WATER (SPECIFIC)
Start this question on a NEW page.
5.1
5.2
5.3
5.4
5.5
Copyright reserved
Describe TWO factors that must be determined before installing the flashing
for a ventilation pipe on a pitched roof.
Discuss TWO regulations that must be adhered to when artificial storm-water
channels connect with open natural channels.
By means of neat freehand sketches, differentiate between the top/plan views
of a rectangular and a round gutter outlet.
Name the component that can be used to secure the downpipe of a gutter to
a wall.
ANSWER SHEET 5.5 shows the front view and top view of a square-based
truncated pyramid.
Use the views and information given and draw the development of the
pyramid. Start the development at A.
The pyramid has a 3-mm seam on both sides.
Show ALL construction and projection lines.
Please turn over
(2)
(2)
(4)
(1)
(21)
[30}
Civil Technology: Civil Services 11
SC/NSC
DBE/2023
QUESTION 6: SEWERAGE, SANITARY FITTINGS AND JOINING (SPECIFIC)
Start this question on a NEW page.
6.1 Various options are given as possible answers to the following questions.
Choose the answer and write only the letter (A-D) next to the question
numbers (6.1.1 to 6.1.5) in the ANSWER BOOK, e.g. 6.1.6 D.
6.1.1
6.1.5
Copyright reserved
... decompose the solid matter in a septic tank.
A
B
Cc
D
Hydrochloric acid
Viruses
Bacteria
Water
The septic tank consists of two chambers that are called the ...
A settling and discharge chambers.
B
Cc
D_ bacteria and sludge chambers.
inspection and soil chambers.
soil and water chambers.
Which ONE of the following is the acceptable slope for a 110 mm
diameter sewer pipe?
A
B
Cc
D
The ... allows gases to escape from a sewer system.
A
B
c
1:75
1: 100
1:20
None of the above-mentioned
manhole
vent pipe
gully
rodding eye
... is the colour used to indicate soil water pipes on a drainage plan.
Green
Brown
Blue
Orange
Please turn over
(1)
(1)
(1)
(1)
(1)
Civil Technology: Civil Services 12 DBE/2023
SC/NSC
6.2 FIGURE 6.2 below shows a water closet pan.
6.2.1
6.2.2
6.2.3
6.2.4
6.2.5
6.2.6
Copyright reserved
C J
FIGURE 6.2
Name the unit that supplies water to the water closet pan.
Name the pipe that comes from the water supply unit and joins the
water closet pan at A.
What component is used at A to prevent leaks?
Name the PVC fitting that is used at B to connect the water closet
pan to the sewer pipe.
State ONE material that is used to manufacture the water closet
pan.
Name ONE fixing agent that can be used to attach the water closet
pan to a floor.
Please turn over
(1)
(1)
(1)
(1)
(4)
(1)
Civil Technology: Civil Services 13 DBE/2023
SC/NSC
6.3 FIGURE 6.3 below shows the section through a 110 mm diameter PVC pipe
and a 110 mm PVC socket.
The PVC socket is on ANSWER SHEET 6.3.
Complete the drawing by joining the PVC pipe to the socket and showing the
solvent welding.
" A Le
FIGURE 6.3 °
6.4 FIGURE 6.4 below shows a horizontal sectional view of a vacuum tank.
A
_|_ ROAD
Q KERB
B
FIGURE 6.4
6.4.1 Identify the type of wall finish at A. (1)
6.4.2 Describe ONE reason for the type of wall finish at A. (1)
6.4.3 Identify B. (1)
6.4.4 Explain why component B is located close to the road kerb. (1)
Copyright reserved Please turn over
Civil Technology: Civil Services 14 DBE/2023
SC/NSC
6.5 FIGURE 6.5 on ANSWER SHEET 6.5 shows the outline of a French drain.
Use ANSWER SHEET 6.5 and draw a complete French drain.
Print ALL labels. (6)
6.6 FIGURE 6.6 below shows the INCORRECTLY drawn sewerage plan of a
dwelling.
Identify THREE errors in the sewerage plan and give a reason for each error.
© MUNICIPAL CONNECTION
fe a
| 4){|2
REO
! LS |
(6)
FIGURE 6.6
6.7 ANSWER SHEET 6.7 shows a building with an incomplete sewerage layout.
Use ANSWER SHEET 6.7 and design and draw the sewerage plan. (10)
[40]
TOTAL: 200
Copyright reserved
Civil Technology: Civil Services
DBE/2023
SC/NSC
[| CENTRE NUMBER: [ | 1 J
| EXAMINATION NUMBER: | | | | el
ANSWER SHEET 2
NO. QUESTIONS ANSWERS MARKS
Name the FIGURE that represents the
1 | first floor. Give ONE reason for your 2
answer.
2 | Deduce from the building plan the 41
number of windows in the building.
3 | Identify number 1. 1
4 | Identify number 2. 4
5 | Identify number 6. 1
6 | Identify number 8. 1
7 | Identify number 9. 1
8 | Identify number 10. 1
9 Identify the number that indicates the 4
garage door.
40 Deduce from the building plan the 1
omitted dimension of number 11.
Deduce from the building plan the
11. | material that must be used for 1
number 5.
Copyright reserved
Civil Technology: Civil Services
DBE/2023
SC/NSC
| CENTRE NUMBER: [ [| [| ] LJ] ]
[EXAMINATION NUMBER: | | | | | | | ]
Give the abbreviations for the Number 3:
following: ene
a Number 3 Number 4: 2
e Number 4 umber &
13 Describe the purpose of a two-way 2
switch.
14 Recommend an appropriate floor 7
covering for the kitchen.
15 Who was responsible for the checking 1
of the drawing?
16 Deduce ONE fault in the bathroom in 1
FIGURE A.
Name an alternative light source that
17 | can be used during load shedding for 1
a dwelling.
Revision 1:
18 State what was done during revision 1 evision 2
and revision 2 of the house plan. _
Revision 2:
19 Name the finish for the ramp as 1
prescribed by the architect.
20 Draw the symbol for a damp-proof 2
membrane.
21 | Draw the symbol for finished wood. 2
22 | Draw the symbol for hardcore filling. 2
Copyright reserved
Civil Technology: Civil Services
| CENTRE NUMBER: LJ [ I
DBE/2023
-| EXAMINATION NUMBER: | | | |
23
Prove, by means of a control test, that
the total horizontal dimensions on the
top and bottom of the plan in
FIGURE A are the same.
24
Calculate the area of the floor plan in
FIGURE B. Show ALL the
calculations. Give your answer in m?.
Round off your answers to TWO
decimal places.
TOTAL:
40
Copyright reserved
Civil Technology: Civil Services
DBE/2023
TOP VIEW
SC/NSC
| CENTRE NUMBER: Litt IL Id
| EXAMINATION NUMBER: | | LT] [ [ L |
ANSWER SHEET 3.10
FIGURE 3.10
ASSESSMENT CRITERIA |MARK| CM
Correctness of brick courses 1
Members 4
TOTAL:| 5
Copyright reserved
Civil Technology: Civil Services
DBE/2023
[ CENTRE NUMBER: [TTT I |]
[EXAMINATIONNUMBER: | | | | | L [J |]
ANSWER SHEET 4.9
WALL
WALL-MOUNTED
GEYSER
WALL
ASSESSMENT CRITERIA | MARK | CM
Correctness of layout 4
Members 6
TOTAL: | 7
Copyright reserved
Civil Technology: Civil Services
SC/NSC
| CENTRE NUMBER: l
DBE/2023
| EXAMINATION NUMBER: |
ANSWER SHEET 5.5
ASSESSMENT CRITERIA | MARK | CM
Correctness of drawing 21
TOTAL: 21
Copyright reserved
Civil Technology: Civil Services
[ CENTRE NUMBER: TT I
DBE/2023
[EXAMINATION NUMBER: | |_|
|
ANSWER SHEET 6.3
ASSESSMENT CRITERIA MARK | CM
Correctness of joining pipe and socket 1
Welding solvent 2
TOTAL: 3
Copyright reserved
I
I
Ul
Ul
I
Ul
Ul
it
Ul
I
'
1
Civil Technology: Civil Services DBE/2023
SC/NSC
[CENTRE NUMBER: TT TT [Tt 7
[EXAMINATIONNUMBER: | | | | | | | [| [| [| | | [ |
ANSWER SHEET 6.5
{ |
LJ
ASSESSMENT CRITERIA | MARK | CM
Correctness of French drain 4
Members 5
TOTAL: 6
Copyright reserved
Civil Technology: Civil Services DBE/2023
SCINSC
| CENTRE NUMBER: [TT TTT Ty
[EXAMINATIONNUMBER: | | | | | | | | | [| | | [| 4
ANSWER SHEET 6.7
MUNICIPAL CONNECTION
| O
—- £ =
[o) [e}
ASSESSMENT CRITERIA | MARK | CM
Correctness of drawing 10
TOTAL: 10
Copyright reserved
Study this subject
Recommended for this subject

Memorandum
Civil Technology Grade 12 Eastern Cape Mock 2023 Memo (Eng)

Question paper
Civil Technology Grade 12 Eastern Cape Mock 2022 QP (Eng)

Question paper
Civil Technology Grade 12 Eastern Cape Mock 2022 QP (Eng)

Question paper
Civil Technology Grade 12 Eastern Cape Mock 2021 QP (Eng)

Question paper
Civil Technology Grade 12 Eastern Cape Mock 2019 QP (Eng)
%20Afr_hlayiso.com_--b820ac91-947c-4aed-821f-256aa13aabe1/v1-3be01795eace6f81b174/card.webp)
Question paper
Civil Technology Grade 12 NSC November 2023 QP (Afr)
More from Grade 12 Civil Technology
%20MG%20Eng--0e265899-dc44-4809-aabf-8f374f1af392/v1-73a07814cfc9334618a1/card.webp)
Memorandum
Civil Technology Grade 12 NSC November 2025 Memo (English)

Memorandum
Civil Technology Grade 12 Eastern Cape Prelim 2024 Memo

Memorandum
Civil Technology Grade 12 Eastern Cape Prelim 2024 Memo

Memorandum
Civil Technology Grade 12 Eastern Cape Prelim 2024 Memo
%20%20MG%20Afr_hlayiso.com_--42b5315c-825c-40e3-b394-85e0253fc0fb/v1-6058b260e68654519cc3/card.webp)
Memorandum
Civil Technology Grade 12 NSC November 2023 Memo (Afrikaans)
%20Afr_hlayiso.com_--f6f7ac38-fb55-4d61-bc66-5441e4cbcee0/v1-b3313a875de5f3475dc0/card.webp)
Question paper