Confidential
basic education
Department:
Basic Education
REPUBLIC OF SOUTH AFRICA
NATIONAL
SENIOR CERTIFICATE
GRADE 12
CIVIL TECHNOLOGY: CIVIL SERVICES
NOVEMBER 2025
MARKS: 200
TIME: 3 hours
This question paper consists of 16 pages and 4 answer sheets.
Please turn over
Skip to contentQuestion paper %20(English%20and%20Afrikaans)%20June%202025%20Question%20Paper--c8edd459-5237-48e0-8588-69d7ecd7f8e5/v1-be996aaed91bf782e098/card.webp)
%20Afr--591d6ffd-20b1-4748-a1ba-b055be0a14c3/v1-4d98a131fd37e013458a/card.webp)
%20Afr--05a95faf-5891-4d88-9e5e-7d13c1d21648/v1-f5ca67113376f7457b83/card.webp)

%20Afr--eefaae29-fe93-4b75-8223-87bf4f3fc14c/v1-3553acfa446acbaa2a45/card.webp)
%20MG%20Eng--898ff365-3aa8-49fc-aa7a-8c58c79bf409/v1-0ee308106aa8bb2a75dc/card.webp)
%20Eng_hlayiso.com_--e6743728-8140-42ae-838d-282654a975a5/v1-dce3e047e0d7ad60a32b/card.webp)
%20Afr_hlayiso.com_--b820ac91-947c-4aed-821f-256aa13aabe1/v1-3be01795eace6f81b174/card.webp)
%20Afr_hlayiso.com_--f6f7ac38-fb55-4d61-bc66-5441e4cbcee0/v1-b3313a875de5f3475dc0/card.webp)
%20%20MG%20Afr_hlayiso.com_--42b5315c-825c-40e3-b394-85e0253fc0fb/v1-6058b260e68654519cc3/card.webp)
%20MG%20Afr_hlayiso.com_--8b448e9d-ad65-4911-ae38-b9af2b632f65/v1-008a0116953928fc25f8/card.webp)
%20Eng_hlayiso.com_--fdfc3cf4-1a3a-4817-a3e9-a2c7f9fe5c2e/v1-c9563485d35727af6c76/card.webp)
View all%20(Afrikaans)%20June%202025%20Possible%20Answers--c0a65d19-28ca-4ac3-8c61-d4627d2a3133/v1-5f42c573694769cf80ce/card.webp)



%20MG%20Afr--1af3bcd6-f360-4582-929e-be82586adfa1/v1-f9bfd9fe3f83289b1669/card.webp)

Civil Technology Grade 12 NSC November 2025 Question Paper
Grade 12 Civil Technology question paper from the NSC November Exam 2025, 21 pages. Read online or get the free PDF download, memo linked when available.
Civil Technology · Grade 12 · NSC November Exam · 2025. Question paper, 21 pages. Read online or download the PDF.
- Subject
- Civil Technology
- Grade
- Grade 12
- Document type
- Question paper
- Year
- 2025
- Exam period
- NSC November Exam
- Curriculum
- CAPS
- Pages
- 21
- File size
- 880.4 KB
Loading document…
Loading document…
1 of 21
Document textSearch extracted text and jump to a page.
Civil Technology: Civil Services 2 DBE/November 2025
NSC Confidential
REQUIREMENTS:
1.
2.
3.
Drawing instruments
A non-programmable calculator
ANSWER BOOK
INSTRUCTIONS AND INFORMATION
a F WO N
© @ N ®
11.
12.
13.
14.
15.
16.
17.
18.
This question paper consists of SIX questions.
Answer ALL the questions.
Read ALL the questions carefully.
Answer each question as a whole. Do NOT separate subsections of questions.
Number the answers correctly according to the numbering system used in this
question paper.
Start the answer to EACH question on a NEW page.
Do NOT write in the margins of the ANSWER BOOK.
You may use sketches to illustrate your answers.
Write ALL calculations and answers in the ANSWER BOOK or on the attached
ANSWER SHEETS.
Use the mark allocation as a guide to the length of your answers.
Make drawings and sketches in pencil, fully dimensioned and neatly finished
off with descriptive titles and notes to conform to the SANS/SABS Code of
Practice for Building Drawings.
For the purpose of this question paper, the size of a brick should be taken as
220 mm x 110 mm x 75 mm.
Use your own discretion where dimensions and/or details have been omitted.
Answer QUESTIONS 2, 3.4, 5.4 and 6.8 on the attached ANSWER SHEETS
using drawing instruments, where necessary.
Write your CENTRE NUMBER and EXAMINATION NUMBER on every
ANSWER SHEET and hand them in with your ANSWER BOOK, whether you
have used them or not.
Drawings in the question paper are NOT to scale due to electronic transfer.
Google Images was used as the source of all photographs and pictures.
Write neatly and legibly.
Copyright reserved Please turn over
Civil Technology: Civil Services 3 DBE/November 2025
QUESTION 1:
NSC Confidential
OHSA, MATERIALS, TOOLS, EQUIPMENT AND JOINING
(GENERIC).
Start this question on a NEW page.
4.1 Choose the correct word(s) from those given in brackets. Write only the word(s)
next to the question numbers (1.1.1 to 1.1.10) in the ANSWER BOOK,
e.g. 1.1.11 Plaster.
1.1.1 Every plank of a wooden scaffold platform must be at least
(28 mm/38 mm) thick.
1.1.2 Toe boards should be at least (150 mm/200 mm) high from the level
of the scaffold platform.
1.1.3 Steel scaffold standards with heavy platform loadings must not
exceed (320 kg per m7/160 kg per m?).
1.1.4 The framework of scaffolding must be constructed to have a safety
factor of at least (two/three).
1.1.5 Trestle scaffolds must not consist of more than (two/four) tiers.
1.1.6 When using a builder's hoist (overhead/hand) protection must be
provided to protect workers from falling objects.
1.1.7 Ladders must not be extended above (two thirds/three quarters) of
the extension length.
1.1.8 A construction site must be cordoned off to prevent (unauthorised
persons/building inspectors) from entering the site.
1.1.9 Stairways that will not be a permanent part of the building must have
landings of at least (760 x 560 mm/450 x 320 mm) for every 3,7 m
vertical rise.
1.1.10 The seller shall supply the user of any hazardous chemical
substance with sufficient information to enable the user to take
necessary measures regarding (safe stocktaking/health and safety).
1.2 Which pictorial view below represents a bolt that will resist rotation?
i (am (om | jo
A B c
Copyright reserved
Please turn over
(1)
(1)
(1)
(1)
(1)
(1)
(1)
(1)
(1)
(1)
(1)
Civil Technology: Civil Services 4 DBE/November 2025
1.3
1.4
1.5
1.6
1.7
NSC Confidential
Bolts are purchased according to different specifications. Name any TWO of
these specifications.
Powder coating is a coating that is applied to metals.
1.4.1 Explain the process of powder coating by referring to the material
that is used and the method of application.
1.4.2 Name ONE advantage of powder coating in terms of applying it to a
metal.
What should NOT be used to clean a multidetector?
Name TWO materials that can be detected in a brick wall using the
multidetector.
What accessory of the dumpy level will be used to position a telescope on a
centre point when horizontal measurements are taken?
QUESTION 2: GRAPHICS AS MEANS OF COMMUNICATION (GENERIC)
Start this question on a NEW page.
FIGURE A and FIGURE B on the next page show drawings that appear on a building
plan. Analyse the drawings and complete the table on ANSWER SHEET 2.
Copyright reserved Please turn over
(2)
(2)
(1)
(1)
(2)
(1)
[20]
Civil Technology: Civil Services 5 DBE/November 2025
NSC Confidential
NOTES:
Contractors must verify all
dimensions and levels on site
before commencing work.
(1) Architects to be notified
of any discrepancies immediately.
Guard rails on patio to be made of
stainless steel.
Aluminium sliding door
(2 400 x 2 000 mm)
Aluminium side panel with
windows (600 x 2 000 mm)
Roof: Hipped roof
Lintels must be instalied above
every window.
Architect's signature .............6
FIGURE A Client's signature ........ceeerees
DRAWING OF
DATE:
REVISION 1 ELECTRICAL
zaiosizozs | ELECTRICS
PRINTED BY: DATE OF PRINT:
8000 BUZZ PRINTERS 26/05/2025
wi wi 2110) DRAWING TITLE:
i = ELEVATION AND FLOOR PLAN
SERVING STATION PROJECT:
° PROPOSED BUILDING OF MR JD JONES
=) ——<———$_—_$_ ON PLOT 54, PROTEA STREET, CALEDON
Bs | _ COUNTER PROJECT NO. DRAWING NO.;
GR 866.464 334P2
= 2x40W \ DATE: DRAWN: | CHECKED:
ts |\ | RESTROOM 20/04/2025 | NCAR C BENN
( RESTAURANT LADIES
3 bes ELEVATION SCALE 1: 100
0 a
<a FLOOR PLAN SCALE 1: 100
Sy [> \
4 Jom REFERENCE CODE
2, ST we W2~ PATIO a
S|
———————|
WINDOW SCHEDULE
= :
@ @ lee
FIGURE B a Ny 1,600),
7800 ne"
ee W:
wi 2 [40]
Copyright reserved Please turn over
Civil Technology: Civil Services 6 DBE/November 2025
NSC Confidential
QUESTION 3: CONSTRUCTION ASSOCIATED WITH CIVIL SERVICES, OHSA
AND QUANTITIES (SPECIFIC)
Start this question on a NEW page.
3.1 FIGURE 3.1 below shows a faulty manhole installation.
sos
FIGURE 3.1
3.1.1 Identify any THREE faults in the manhole installation.
3.1.2 Any worker working in a manhole where there might be dangerous
gases must be assisted by a qualified person in case of an
emergency. In which field should this person be qualified?
3.1.3 What type of protective equipment is necessary when working in
manholes with dangerous gases?
3.1.4 Explain why it is NOT advisable to use a dust mask that covers the
mouth and nose when working in manholes.
3.1.5 Name the recommended brick bond that can be used in the
construction of a manhole.
3.1.6 Name ONE other type of manhole that is available in the
construction industry.
3.2 Show, by means of a sketch in your ANSWER BOOK, how the sides of firm
ground can be supported during excavations. Label any TWO parts.
3.3 The internal measurement of the sides of a cubic water storage tank is
2 650 mm.
3.3.1
3.3.2
Calculate the volume of the tank in m*.
Calculate the volume of the tank in litres.
Show ALL calculations and round off your answer to TWO decimal places.
Copyright reserved
Please turn over
(3)
(1)
(1)
(1)
(1)
(1)
(7)
(4)
(3)
Civil Technology: Civil Services 7 DBE/November 2025
NSC Confidential
3.4 FIGURE 3.4 below shows the first course of a double return angle of a
one-brick wail in stretcher bond.
A
FIGURE 3.4
Use ANSWER SHEET 3.4 to project and draw the second course of the double
return angle of a one-brick wall in stretcher bond.
NOTE: Project as seen from the direction of arrow A. (8)
[30]
Copyright reserved Please turn over
Civil Technology: Civil Services
8
DBE/November 2025
NSC Confidential
QUESTION 4: COLD- AND HOT-WATER SUPPLY, TOOLS, EQUIPMENT AND
MATERIALS (SPECIFIC)
Start this question on a NEW page.
41 Choose a description from COLUMN B that matches an item in COLUMN A.
Write only the letter (A-L) next to the question numbers (4.1.1 to 4.1.8) in the
ANSWER BOOK, e.g. 4.1.9 M.
COLUMN B
COLUMN A
4.1.1. Non-return valve
4.1.2 Expansion control valve
4.1.3 Stopcock
4.1.4 Ball valve in a cistem
4.1.5 Element
4.1.6 Red-water diverter
4.1.7 Anode
4.1.8 Mixer tap
allows back flow of water in pipes
controls the pressure of hot water in
a geyser
a floating device used to regulate
water flow
a device used to shut off the water
flow in a pipe system
a fitting that allows water to flow in
only one direction
a manually-operated valve used to
stop or control water flow in large
pipes
heats the water inside a geyser
a device that combines hot and cold
water before dispensing
redirects cool water to a rain-water
tank before it reaches the tap
a device that increases water
pressure in low-pressure systems
sacrifices itself to protect the element
inside the geyser
a pipe fitting that allows water to
change direction
Copyright reserved
(8 x 1)
Please turn over
(8)
Civil Technology: Civil Services 9
NSC Confidential
DBE/November 2025
4.2 FIGURE 4.2 below shows an installation of a hot-water supply system with the
corresponding components below the system.
c
4.2.1
4.2.2
4.2.3
4.2.4
4.2.5
4.2.6
4.2.7
Copyright reserved
FIGURE 4.2
Identify A to D.
Explain why the hot-water outlet is positioned at the top of the
geyser, as indicated at pipe F.
What is the minimum installation height for part B from the top of
the geyser?
Predict what could happen if the part under E is not installed.
Recommend the diameter of the outlet pipe at C.
Differentiate between part A and part D in terms of their use.
Draw the symbol used for component E in hot-water systems.
Please turn over
(4)
(1)
(1)
(1)
(1)
(2)
(2)
Civil Technology: Civil Services 10 DBE/November 2025
4.3
4.4
4.5
4.6
47
NSC Confidential
Differentiate between a water-pressure testing pump and a centrifugal pump in
terms of their use.
Draw the symbols of the following components that are used in hot-water
systems:
4.4.4 Non-return valve
4.4.2 Shower (movable)
4.4.3 Thermostatic controller
Many faults can occur in hot-water systems.
4.5.1 Give ONE reason why the water from geysers is sometimes NOT
hot enough.
45.2 Explain how you can prevent a shortage of hot water from a geyser.
FIGURE 4.6 below is a picture of a pipe fitting used for waste-water on the
outside of the kitchen.
FIGURE 4.6
4.6.1 Identify the pipe fitting.
4.6.2 Explain the function of the fitting.
46.3 Explain why the ends of the fitting should be larger than the bend.
4.6.4 What should be the diameter of this fitting?
Explain TWO methods that can be used to prevent an electrolytic reaction in a
water system.
Copyright reserved Please turn over
(2)
(2)
(2)
(2)
(1)
(2)
(1)
(1)
(1)
(1)
(2)
Civil Technology: Civil Services 11 DBE/November 2025
NSC Confidential
4.8 FIGURE 4.8 below shows TWO taps.
FIGURE 4.8
4.8.1 Differentiate between fap A and tap B in terms of how it saves water. (2)
4.8.2 Name a water-saving tap that can be operated hands-free. (1)
[40]
Copyright reserved Please turn over
Civil Technology: Civil Services 12 DBE/November 2025
NSC Confidential
QUESTION 5: GRAPHICS AS MEANS OF COMMUNICATION, ROOF WORK AND
STORM WATER (SPECIFIC)
Start this question on a NEW page.
5.1 Various options are provided as possible answers to the following questions.
Choose the answer and write only the letter (A—D) next to the question numbers
(5.1.1 to 5.1.5) in the ANSWER BOOK, e.g. 5.1.6 D.
5.1.1 The component that is attached to the downpipe, that allows rain-
water to flow out, is called the ...
A gutter.
B gully.
C_ holderbat.
D_ shoe.
5.1.2 The maximum distance between PVC downpipe clips used to fasten
the downpipe to the wall is ...
2 metres.
3 metres.
4,5 metres.
2,5 metres.
vuowDYr
5.1.3 ... can be used for a flashing at the junction of a wall and the roof.
A Zine
B PVC
Cc Tin
D_ None of the above-mentioned
5.1.4 Soakaways must be installed at least ... from a building.
A 3metres
B 2 metres
Cc 1metre
D 5 metres
5.1.5 Where artificial storm-water channels connect with open natural
channels, it must ...
correspond with the natural flow of water.
not cause soil erosion.
not damage the surrounding environment.
All the above-mentioned
wkekwP 4
Copyright reserved Please turn over
(1)
(1)
(1)
(1)
(1)
Civil Technology: Civil Services 13 DBE/November 2025
NSC Confidential
5.2 FIGURE 5.2 shows gutter components.
a .
A B
FIGURE 5.2
6.2.1 Identify A and B. (2)
5.2.2 Describe the locations of A and B in a rainwater system. (2)
5.3 A new school building has recently been completed. During heavy rainfall,
water pooled around the foundation. Explain the possible consequences of the
poorly designed storm-water drainage system around the building. (2)
5.4 ANSWER SHEET 5.4 shows the front view and left view of a shoe offset of a
cylindrical downpipe.
Use the drawings and information given and only draw the development of
pipe A.
The pipe has a 3 mm seam on both sides.
Start the development on the short side indicated by B.
Show ALL construction and projection lines. (19)
[30]
Copyright reserved Please turn over
Civil Technology: Civil Services 14 DBE/November 2025
NSC Confidential
QUESTION 6: SEWERAGE, SANITARY FITTINGS AND JOINING (SPECIFIC)
Start this question on a NEW page.
6.1 Complete the following sentences by using the words provided in the list below.
Write only the word(s) next to the question numbers (6.1.1 to 6.1.5) in the
ANSWER BOOK, e.g. 6.1.6 Scum.
fermentation; compost; bio-reactor; chlorine; sludge; biomass;
hydrochloric acid; septic tank;_waste-water; zinc chloride
6.1.1 During the sewerage treatment process, the ... is chemically treated
and separated at a treatment plant.
6.1.2 After the separation process, bigger solids are filtered out in the
treatment process. The solids are used as ...
6.1.3 Effluent in the treatment process is pumped into a ... where bacteria
breaks down the harmful matter.
6.1.4 Secondary clarifying in the treatment process allows the ... to settle
to the floor of the tank.
6.1.5 The water in the treatment process is chemically treated with ... to
make it safe for drinking.
Copyright reserved Please turn over
(1)
(1)
(1)
(1)
(1)
Civil Technology: Civil Services 15 DBE/November 2025
NSC Confidential
6.2 FIGURE 6.2 below illustrates a sink installation.
A — P&S
S
. FIGURE 6.2
6.2.1 Identify A.
6.2.2 Whatis the purpose of the rubber washer that is fitted underneath the
basin outlet indicated at B?
6.2.3 Identify C.
6.2.4 Name the adhesive that will be used to join C to the waste pipe.
6.2.5 Explain the purpose of the P-trap holding water at D.
6.2.6 Name the fixture that must be installed below E.
6.3 An efficient drainage system must comply with certain requirements.
6.3.1 Name the component that must be installed in a drainage system
when two or more pipes meet or when there is a change of direction
in the sewer pipeline.
6.3.2 State the minimum number of ventilation pipes that must be installed
Copyright reserved
in a sewerage system.
Please turn over
(1)
(1)
(1)
(2)
(1)
(1)
(1)
Civil Technology: Civil Services 16 DBE/November 2025
NSC Confidential
6.4 Name TWO materials that are used to manufacture drain pipes. (2)
6.5 State TWO properties of solder. (2)
6.6 Predict what the consequence will be when the head of the soldering iron is too
cold or too hot when preparing it for the tinning process. (2)
6.7 FIGURE 6.7 shows a drainage system.
A B Cc
a
FIGURE 6.7
6.7.1 Identify the system above. (1)
6.7.2 Identify parts A and part B. (2)
6.7.3. Name the fixture that part C should be connected to in order to allow
sewage to be removed. (1)
6.8 ANSWER SHEET 6.8 shows the floor plan of a dwelling and an outbuilding with
an incomplete sewerage system.
Use ANSWER SHEET 6.8 to design and draw the sewerage layout for the
dwelling and outbuilding. (16)
[40]
TOTAL: 200
Copyright reserved OPO
ae
Civil Technology: Civil Services
NSC Confidential
DBE/November 2025
| CENTRE NUMBER: [ | J] |
[EXAMINATION NUMBER: | | | | L | J
ANSWER SHEET 2
NO. QUESTIONS ANSWERS MARKS
1 What elevation is indicated by 1
* | FIGURE A?
2 Deduce, from the notes column, what 4
“| type of roof is indicated by number 1.
What energy-generating components
3. | are installed on the roof, as indicated 1
by number 2?
4. | Identify number 3. 1
Identify number 4. 1
6 What material is recommended to be 1
* | used to manufacture number 5?
7. | Identify number 6. 1
Write down the abbreviation for
8. 4
number 7.
9 Identify the end shape used to 1
* | manufacture number 8.
10 How many built-in cupboards are 1
* | there in the building?
11 What electrical installation has been 1
* | omitted in the building?
What type of material can be used to
12. | manufacture the fascia board in 4
FIGURE A?
How should the opening direction of
13. | the sliding door be indicated on the 1
floor plan?
14 Name ONE material that can be used 1
* | to manufacture number 9.
15 Deduce, from the notes column, what 1
* | must be installed above every window.
Copyright reserved
Civil Technology: Civil Services
NSC Confidential
| CENTRE NUMBER: |
DBE/November 2025
[EXAMINATIONNUMBER: | | | | | | [ [| [ |
16 How many external doors are visible 1
* | on the southern side of the building?
47 How many water closets are installed 1
* | in the building?
18. | Identify number 10. 1
19 Deduce the thickness of the internal 1
* | walls from FIGURE B.
20 State the reference code of the 1
* | proposed building.
21 How many 1 200 x 600 mm windows 1
* | are there in the building?
Deduce, from the notes column, the
22. | dimensions of the aluminium side 2
panel with windows.
23. | Draw the symbol for a grease trap. 3
Draw the symbol for undisturbed
24. | earth. 3
What sanitary fitting is installed in the
25. 4
scullery?
Calculate the area of the scullery to be
covered with floor tiles.
26. | The sink unit must be installed on top 3
of the tiles.
Give your answer in m?.
Calculate the total length of the wall
27, | on the northern side of the building. 7
* | Show ALL calculations. The length
must be indicated in metres.
TOTAL: 40
Copyright reserved
Civil Technology: Civil Services DBE/November 2025
NSC Confidential
[| CENTRE NUMBER: LTT TT TT J
[| | | | ft tT tT 4
[EXAMINATION NUMBER: | [| | |
ANSWER SHEET 3.4
FIGURE 3.4
ASSESSMENT CRITERIA
NO. MARK | CANDIDATE'S
MARK
1 3
2 3
3 2
TOTAL: 8
Copyright reserved
Civil Technology: Civil Services
NSC Confidential
| CENTRE NUMBER:
DBE/November 2025
| EXAMINATION NUMBER: LT {[1T[ Td TT J] 4
ANSWER SHEET 5.4
|
1
ASSESSMENT CRITERIA
NO. |MARK] CANDIDATE'S
MARK
1 1
2 2
3 2
4 6
5 6
6 2
TOTAL: | 19
Copyright reserved
Civil Technology: Civil Services DBE/November 2025
NSC Confidential
[| CENTRE NUMBER: LT [| 7] [ [ JT J
[EXAMINATIONNUMBER: | | | | | | | | | | | | | 4
ANSWER SHEET 6.8
MUNICIPAL CONNECTION
———
dloll_}
NS
=F
TC
o
a ——
ASSESSMENT CRITERIA
NO. | MARK] CANDIDATE'S
MARK
1 4
2 4
3 2
4 1
5 2
6 1
7 2
TOTAL: | 16
Copyright reserved
Study this subject
Revise the topics in this paper, then practise them question by question.
Recommended for this subject
More papers and memos for this grade and subject.
%20(English%20and%20Afrikaans)%20June%202025%20Question%20Paper--c8edd459-5237-48e0-8588-69d7ecd7f8e5/v1-be996aaed91bf782e098/card.webp)
Question paper
Civil Technology Grade 12 Gauteng June 2025 Question Paper (Afr)
%20Afr--591d6ffd-20b1-4748-a1ba-b055be0a14c3/v1-4d98a131fd37e013458a/card.webp)
Question paper
Civil Technology Grade 12 NSC June 2025 Question Paper (Afr)
%20Afr--05a95faf-5891-4d88-9e5e-7d13c1d21648/v1-f5ca67113376f7457b83/card.webp)
Question paper
Civil Technology Grade 12 NSC November 2025 Question Paper

Question paper
Civil Technology Grade 12 Eastern Cape Prelim 2024 QP (Eng)
%20Afr--eefaae29-fe93-4b75-8223-87bf4f3fc14c/v1-3553acfa446acbaa2a45/card.webp)
Question paper
Civil Technology Grade 12 November 2024 NSC Question Paper
%20MG%20Eng--898ff365-3aa8-49fc-aa7a-8c58c79bf409/v1-0ee308106aa8bb2a75dc/card.webp)
Question paper
Civil Technology Grade 12 November 2024 NSC MG Question Paper
Related documents
%20Eng_hlayiso.com_--e6743728-8140-42ae-838d-282654a975a5/v1-dce3e047e0d7ad60a32b/card.webp)
Question paper
Civil Technology Grade 12 NSC November 2023 Question Paper
%20Afr_hlayiso.com_--b820ac91-947c-4aed-821f-256aa13aabe1/v1-3be01795eace6f81b174/card.webp)
Question paper
Civil Technology Grade 12 NSC November 2023 Question Paper
%20Afr_hlayiso.com_--f6f7ac38-fb55-4d61-bc66-5441e4cbcee0/v1-b3313a875de5f3475dc0/card.webp)
Question paper
Civil Technology Grade 12 NSC November 2023 Question Paper
%20%20MG%20Afr_hlayiso.com_--42b5315c-825c-40e3-b394-85e0253fc0fb/v1-6058b260e68654519cc3/card.webp)
Question paper
Civil Technology Grade 12 NSC November 2023 Question Paper
%20MG%20Afr_hlayiso.com_--8b448e9d-ad65-4911-ae38-b9af2b632f65/v1-008a0116953928fc25f8/card.webp)
Question paper
Civil Technology Grade 12 NSC November 2023 Question Paper
%20Eng_hlayiso.com_--fdfc3cf4-1a3a-4817-a3e9-a2c7f9fe5c2e/v1-c9563485d35727af6c76/card.webp)
Question paper
Civil Technology Grade 12 NSC November 2023 Question Paper
More from Grade 12 Civil Technology
%20(Afrikaans)%20June%202025%20Possible%20Answers--c0a65d19-28ca-4ac3-8c61-d4627d2a3133/v1-5f42c573694769cf80ce/card.webp)
Memorandum
Civil Technology Grade 12 Gauteng June 2025 Memo (Afrikaans)

Memorandum
Civil Technology Grade 12 Eastern Cape Prelim 2024 Memo (Afr)

Memorandum
Civil Technology Grade 12 Eastern Cape Prelim 2024 Memo (English)

Memorandum
Civil Technology Grade 12 Eastern Cape Prelim 2024 Memo (English)
%20MG%20Afr--1af3bcd6-f360-4582-929e-be82586adfa1/v1-f9bfd9fe3f83289b1669/card.webp)
Question paper
Civil Technology Grade 12 November 2024 NSC MG Question Paper

Memorandum