NATIONAL
SENIOR CERTIFICATE
GRADE 11
NOVEMBER 2022
CIVIL TECHNOLOGY: CIVIL SERVICES
MARKING GUIDELINE
(EXEMPLAR)
MARKS: 200
This question paper consists of 17 pages, including 3 answer sheets.
Skip to contentAll 2022 papers 
/CIV%20TECH%20GR11%20QP%20NOV2022_Civil%20Services_English_hlayiso.com_--ed0b5808-e643-408f-bef2-165736e1c4b6/v1-0797091449081c3c3dfd/card.webp)
/CIV%20TECH%20GR11%20QP%20NOV2022_Construction_English_hlayiso.com_--ef9cc9f6-54a4-49fb-a7b1-407a487eeec8/v1-ddd234b1e4aa182f38ab/card.webp)


%20Afr%20Nov%202020_SIVIELE%20DIENSTE_hlayiso.com_.docx_hlayiso.com_--a014afb0-d15f-4eaa-838f-0768b568dc8b/v1-faed7b104eb0fbf75540/card.webp)
View all





Civil Technology Grade 11 Exemplar November 2022 Memo (Eng)
Grade 11 Civil Technology memorandum from the Exemplar November Exam 2022 (English), 17 pages. Read online or download the free PDF.
Civil Technology · Grade 11 · Exemplar November Exam · 2022 · English. Memorandum, 17 pages. Read online or download the PDF.
- Subject
- Civil Technology
- Grade
- Grade 11
- Language
- English
- Document type
- Memorandum
- Year
- 2022
- Exam period
- Exemplar November Exam
- Curriculum
- CAPS
- Pages
- 17
- File size
- 681.7 KB
Free to read online, no sign-up needed
Loading document…
Loading document…
1 of 17
This exam
Exemplar November Exam 2022
Document textSearch extracted text and jump to a page.
Downloaded from hlayiso.com
2 CIVIL TECHNOLOGY: CIVIL SERVICES (EC/NOVEMBER 2022)
INSTRUCTIONS FOR THE MARKERS
1. Markers should:
• Familiarise themselves with the question and answer before evaluating the
responses of candidates.
• Always interpret the responses of the candidates within the context of the
question.
• Consider any relevant and acceptable answer during pre-marking but
should strictly adhere to the answers after finalisation of the marking
guideline.
• There are two approaches to answering questions, these are (1) to describe
and (2) to explain.
• If a candidate is required to explain e.g., a process in 4 steps, only the first
4 responses should be considered.
• If, however a candidate is required to e.g., explain or describe how to
transfer heights from one point to another using a transparent pipe level we
need to consider that candidates may write a long description not
necessarily well organised as an intellectual response may do. In this case
the marker needs to evaluate the complete statement to judge if the
candidate explained the required outcome satisfactorily and allocate marks
on merit. The marker should apply his/her professional judgement with
these types of questions.
• Mark what the candidate wrote and do not award marks for answers that
the marker thinks the candidate meant with what was written.
• Indicate the tick or cross right at the position where the mark needs to be
awarded or where the candidate made the error.
• Accept the letter corresponding with the correct answer as well as the
answer written in full in multiple-choice questions.
• Accept incorrect spelling in one-word answers unless the spelling changes
the meaning of the answer.
2. For calculations:
• A mark is only awarded if the correct unit is written next to the answer.
• If TWO marks are awarded ONE mark is awarded for the answer and ONE
mark for the correct unit.
• Where the candidate made a principle error e.g. added instead of
multiplying, no marks will be awarded for the steps. If the answer is correct
according to what the candidate did, the mark for the answer can be
awarded for the application of skills.
• Where an incorrect answer could be carried over to the next step, the first
answer will be deemed incorrect. However, should the incorrect answer be
carried over correctly, the marker has to recalculate the values, using the
incorrect answer from the first calculation. If correctly used, the candidate
should receive the full marks for subsequent calculations.
• Markers should consider when and where a candidate has rounded off in a
calculation, as well as the subsequent effect it has on the final answer
obtained. The calculation should therefore be awarded marks on merit.
• Alternative methods of calculations must be considered, provided that the
correct answer is obtained.
Copyright reserved Please turn over
Downloaded from hlayiso.com
(EC/NOVEMBER 2022) CIVIL TECHNOLOGY: CIVIL SERVICES 3
3. When marking drawings:
• The member for which the mark should be awarded should be drawn
correctly in the correct position to receive a mark.
• A member incorrectly drawn but wrongfully repeated in another position
will be awarded the mark for the repeated incorrect member provided that
the marking guideline provide for TWO or more marks for that member
(positive marking).
• Marks can only be awarded for a label if the label is correctly indicating the
correct member.
• Scale drawings should always be marked using an appropriate mask.
When a candidate drew the wrong drawing e.g.:
• A horizontal section instead of a vertical section, no marks will be
allocated to the drawing as the candidate did not respond to the expected
outcome.
• An orthographic view instead of sectional view, no marks will be allocated
to the drawing as the candidate did not respond to the expected outcome.
• An orthographic view instead of an isometric view, no marks will be
allocated to the drawing as the candidate did not respond to the expected
outcome.
• If the incorrect drawing was drawn, the candidate can be awarded for only
what was asked but mark/s for the correctness of the drawing will not be
awarded e.g., if a King Post roof truss was asked in the question, and
candidate drew SA-Howe Truss.
Copyright reserved Please turn over
Downloaded from hlayiso.com
4 CIVIL TECHNOLOGY: CIVIL SERVICES (EC/NOVEMBER 2022)
QUESTION 1: SAFETY AND MATERIALS (GENERIC)
1.1 Gum boots (1)
1.2 Under what circumstances will the following personal protective equipment be
used?
1.2.1 Safety glasses
When working with a bench grinder, drills, electrical saws, etc. or any
electrical equipment. (1)
1.2.2 Earplugs
When noise levels are high. (1)
1.3 Loose clothing can be pulled (1) into the machine by its moving parts (1). (2)
1.4 Describe the safety precaution that is applicable with the following hand tools:
1.4.1 Hammer heads
Should fit snugly into the handle and be wedged in properly. (1)
1.4.2 Sawing equipment
Should be sharp and clean. / Handles should be properly attached. (1)
1.4.3 When carrying chisels.
Carry the blade facing downwards. (1)
1.5 The petrol fumes can be harmful, (1) when inhaled. (1)
(Similar answer.) (2)
1.6 Any TWO requirements for the storing of cement:
• Store on a pallet / planks / damp proof course. (Similar answer.)
• Store under cover / inside a building.
• No contact with water. (Any 2 x 1) (2)
1.7 Any ONE similar answer:
• Warning people against overhead work / dangers.
• To show that the wearing of a hard hat is compulsory. (1)
1.8 Any FOUR requirements for storing hazardous material in the workplace:
• The room must be well ventilated.
• The door must have a threshold.
• Material that may cause a spark must not be stored here.
• Liquids that may interact chemically must not be stored in close proximity.
• Containers must always be sealed or properly closed.
• Never store other flammable material with hazardous material. (Any 4 x 1) (4)
Copyright reserved Please turn over
Downloaded from hlayiso.com
(EC/NOVEMBER 2022) CIVIL TECHNOLOGY: CIVIL SERVICES 5
1.9 THREE ingredients to mix screed:
• Cement (1)
• Sand (1)
• Water (1) (3 x 1) (3)
1.10 Any THREE uses for screed:
• Finish for floors and walls.
• Facing material
• Levelling layer for suspended floors.
• Levelling layer for floor covering.
• Infill to accommodate various levels.
• Insulated roof screed. (Any 3 x 1) (3)
1.11 • Aggregate is too coarse.
• Aggregate too big for a mortar joint.
• Rough parts will give a weak finish.
• Similar answer. (Any 1 x 1) (1)
1.12 Identify the type of board products that will be used for the following work:
1.12.1 Backs of cupboards
Hard board or plywood (1)
1.12.2 Formwork for concrete
Shutter board (1)
1.13 Stock bricks:
No attractive appearance / Must be plastered / Not good quality (1)
Face bricks:
Attractive appearance / Require no plaster / Good quality (1) (2)
1.14 Any TWO uses of cast iron:
• Manhole covers
• Sewerage pipes and fittings
• Baths
• Wash basins
• Tools
• Hinges
• Similar answer (Any 2 x 1) (2)
[30]
Copyright reserved Please turn over
Downloaded from hlayiso.com
6 CIVIL TECHNOLOGY: CIVIL SERVICES (EC/NOVEMBER 2022)
QUESTION 2: EQUIPMENT, TOOLS AND GRAPHICS (GENERIC)
2.1 Round shovel cannot shape the corners / square edges / straight lines (similar
answer). (1)
2.2 Any THREE hand tools that can be used to dress / cut bricks:
• Comb hammer
• Cold chisel
• Club hammer
• Brick hammer (Any 3 x 1) (3)
2.3 2.3.1 Hand hawk (1)
2.3.2 Straight edge (1)
2.3.3 External corner trowel (1)
2.3.4 Nose trowel (1)
2.4 The rip saw is used for cutting with the grain of the wood. (1)
The cross-cut saw is used for cutting across the grain of wood. (1) (2)
2.5 2.5.1 Sliding bevel (1) (1)
Any ONE use:
• Drawing inclined / oblique lines.
• Drawing angles other than 90°.
• Copying angles to transfer them to other surfaces. (1 x 1) (1)
2.5.2 Bench grinder (1). (1)
Any ONE use:
• Sharpening tools
• Grinding
• Wire brush attachment can be installed. (Any 1 x 1) (1)
2.5.3 Electrical drill (1) (1)
Any ONE use:
• Drilling holes.
• Can be used as a screwdriver.
• Sanding / buffing / cutting accessories attached to drill. (Any 1 x 1) (1)
2.6 2.6.1 Plate compactor (1)
2.6.2 Any ONE use:
• Compacting disturbed or loose soil up to 150 mm.
• Tamping fillings for a hard-core layer under concrete floors.
• Compacting soil before paving bricks are laid.
• Similar answer. (Any 1 x 1) (1)
Copyright reserved Please turn over
Downloaded from hlayiso.com
(EC/NOVEMBER 2022) CIVIL TECHNOLOGY: CIVIL SERVICES 7
2.7 See ANSWER SHEET 1. (13)
2.8 Part of the structure is enlarged (1) to include more information to the
drawing. (1) (2)
2.9 Any THREE particulars of a site plan:
• Boundaries of property
• Building line
• Erf numbers of plot and adjacent plots
• Services and connections
• Name of street
• Driveway
• Trees / boulders
• Measurements
• Existing buildings
• Contours
• North arrow
• Scale (Any 3 x 1) (3)
2.10 2.10.1 Water closet
(2)
2.10.2 Hot-water cylinder
HW (2)
[40]
Copyright reserved Please turn over
Downloaded from hlayiso.com
8 CIVIL TECHNOLOGY: CIVIL SERVICES (EC/NOVEMBER 2022)
QUESTION 3: QUANTITIES, JOINING AND GRAPHICS
3.1 FIGURE 3.1 shows a foundation strip for a building.
The foundation is 600 mm wide and 200 mm thick.
A concrete mix of 1 : 4 : 4 is used.
9 000
6 000
3.1.1 Determine the centre line of the foundation:
2 x 9 000 = 18 000
2 x 6 000 = 12 000
20 000
4 x 600 - 2 400
17 600 = 17,6 m (5)
3.1.2 Determine the volume of concrete needed:
17,6 x 0,6 x 0,2 = 2,112 m³
3.2 A one brick wall of 1,2 m high and 12 m long.
Determine the amount of bricks needed:
Area of wall:
12 m
x 1,2 m = 14,4 m2
14,4 m2
x 2
x 50 = 1 440 bricks
(5)
Copyright reserved Please turn over
Downloaded from hlayiso.com
(EC/NOVEMBER 2022) CIVIL TECHNOLOGY: CIVIL SERVICES 9
3.3 Apply a thin layer of PVC glue (1) to the fitting and the pipe. (1)
Push the parts into position (1), while twisting. (1) (4)
3.4 3.4.1 True (1)
3.4.2 False (1)
3.4.3 False (1)
3.4.4 True (1)
3.4.5 True (1)
3.5 Any TWO safety precautions when using epoxy:
• Apply with care – cleaning excess/overruns is difficult once dry.
• Be careful – the fumes may be toxic.
• Join surfaces firmly together, before the compound dry (Any 2 x 1) (2)
3.6
(2)
3.7 Bottom (1) right-hand corner (1) of the drawing page. (2)
3.8 3.8.1 Fluorescent light (1)
3.8.2 Wall light (1)
[30]
Copyright reserved Please turn over
Downloaded from hlayiso.com
10 CIVIL TECHNOLOGY: CIVIL SERVICES (EC/NOVEMBER 2022)
QUESTION 4: SAFETY, MATERIAL, EQUIPMENT AND JOINING (SPECIFIC)
4.1 Any FOUR precautionary measures:
• Wear suitable personal protective equipment.
• Avoid hand-to-face contact.
• Cover open wounds.
• Wash immediately after removing protective equipment.
• Wash protective equipment.
• Adequate first-aid equipment should always be available.
• Thoroughly clean equipment.
• Make sure immunisations are up to date. (Any 4 x 1) (4)
4.2 To prevent inhalation of fumes / Fumes are dangerous. (1)
4.3 (1) Non-flammable / cotton clothing. (2) To prevent clothing from burning you
when solder is splashing. (2)
4.4 Any TWO properties:
• Hard
• Brittle
• Resistant to high temperatures. (Any 2 x 1) (2)
4.5 Identify the type of tools in FIGURES 4.5.1 to 4.5.3 and name ONE use of each.
4.5.1 Tin snips – Cutting sheet metal
4.5.2 File – Smoothing / shaping metal surfaces
4.5.3 Groover / Seaming tool – Straightening a rolled seam joint (3 x 2) (6)
4.6 4.6.1 Guillotine. (1)
4.6.2 A – Pressure plate
B – Working surface
C – Extension bar
D – Base
E – Push-down pedal (5)
4.6.3 Any TWO caring measures:
• Oil moving parts.
• Keep blades sharp.
• Maintain the service programme.
• Do not cut round bars. (Any 2 x 1) (2)
4.7 4.7.1 Ratchet cutter (1)
4.7.2 To cut polythene pipes. (1)
Copyright reserved Please turn over
Downloaded from hlayiso.com
(EC/NOVEMBER 2022) CIVIL TECHNOLOGY: CIVIL SERVICES 11
4.8 (1) Chemical resin base and (2) a hardening agent. (2)
4.9 9.4.1 C
9.4.2 D
9.4.3 A (3 x 1) (3)
[30]
Copyright reserved Please turn over
Downloaded from hlayiso.com
12 CIVIL TECHNOLOGY: CIVIL SERVICES (EC/NOVEMBER 2022)
QUESTION 5: GRAPHICS, CONSTRUCTION AND QUANTITIES (SPECIFIC)
5.1 FIGURE 5.1 on ANSWER SHEET 2 a 45° cut-off cylindrical pipe.
Use ANSWER SHEET 2 and develop and draw the development of the cut-off
of the cylindrical pipe on scale 1 : 1. (14)
5.2 Compacting (1)
5.3 Any THREE factors:
• Ramps must be erected before placing of concrete.
• Place all concrete needed in one day.
• Start in the corner furthest from the concrete mixer.
• Every new batch must be placed near the preceding one.
• Pour the concrete higher than needed.
• Concrete must fill all holes and corners.
• Concrete surface must be levelled.
• Leave the concrete for seven days before building on it. (Any 3 x 1) (3)
5.4 5.4.1 150 mm (1)
5.4.2 50 mm (1)
5.5 5.5.1 Soldier course (1)
5.5.2 Sailor course (1)
5.6 Use the quantity list on ANSWER SHEET 3 and determine the volume of
concrete needed for a floor of 6 m long, 3 m wide and 75 mm thick. (3)
5.7 Use the quantity list on ANSWER SHEET 3 and determine the number bricks
needed for a cavity wall with a length of 4 m and a height of 2,4 m. (5)
[30]
Copyright reserved Please turn over
Downloaded from hlayiso.com
(EC/NOVEMBER 2022) CIVIL TECHNOLOGY: CIVIL SERVICES 13
QUESTION 6: COLD AND HOT WATER SUPPLY, DRAINAGE, STORMWATER
AND SANITARY FITMENTS (SPECIFIC)
6.1 6.1.1 True (1)
6.1.2 True (1)
6.1.3 False (1)
6.1.4 False (1)
6.2 6.2.1 Stopcock (1)
6.2.2 A – Shank
B – Gland nut
C – Housing
D – Jumper (4)
6.2.3 E (1)
6.3 (1) Control the water level (2) in cisterns and supply tanks. (2)
6.4 Any TWO requirements:
• Pipes must be housed in builders’ work ducts / wall chases.
• Pipes must be laid in continuous lengths.
• Joints must be located within access ports. (Any 2 x 1) (2)
6.5 6.5.1 Flow switch (2)
6.5.2 Pipe crossing (2)
6.6 6.6.1 Bath tap (1)
6.6.2 Pressure-control valve (1)
6.7 Any TWO:
• Thermal expansion.
• Excess system pressure.
• Low temperature relief.
• Too high setting on the water heater. (Any 2 x 1) (2)
6.8 The (1) collector and the main tank (2) are a unit. (2)
6.9 Low pressure in taps. (1)
Copyright reserved Please turn over
Downloaded from hlayiso.com
14 CIVIL TECHNOLOGY: CIVIL SERVICES (EC/NOVEMBER 2022)
6.10 The north side is the most exposed to sunlight. (1)
6.11 (1) Transparent tube that allow light rays through with (2) minimal reflection. (2)
6.12 1 : 80 (1)
6.13 6.13.1 G (1)
6.13.2 WC (1)
6.13.3 SP (1)
6.14 Any TWO:
• Fewer connections.
• Only one gully is needed.
• Fewer vent pipes.
• Pipe arrangement is simplified. (Any 2 x 1) (2)
6.15 2,1 m (1)
6.16 6.16.1 Flush valve (1)
6.16.2 Flush of a water closet, etc. / In the place of a cistern. (1)
6.16.3 Any THREE:
• Parts can be expensive.
• Difficult to fix.
• Sand grains can prevent it to work properly.
• Moving parts can become defective.
• Leakage can prevent it from working effective. (Any 3 x 1) (3)
[40]
Copyright reserved Please turn over
Downloaded from hlayiso.com
(EC/NOVEMBER 2022) CIVIL TECHNOLOGY: CIVIL SERVICES 15
ANTWOORDBLAD NAAM:
1 CIVIL SERVICES
ANSWER SHEET NAME:
2.7 FIGURE 2.7 on ANSWER SHEET 1 shows the isometric view of a T-junction
of a half brick wall in stretcher bond.
Use ANSWER SHEET 1 and draw the front view of the brick wall on scale
1 : 10. (13)
T-junction 4
Brick sizes / Scale 3
Height and length 2
Stretcher bond 2
Line work / Neatness 2
TOTAL: 13
Copyright reserved Please turn over
Downloaded from hlayiso.com
16 CIVIL TECHNOLOGY: CIVIL SERVICES (EC/NOVEMBER 2022)
ANTWOORDBLAD NAAM:
2 CIVIL SERVICES
ANSWER SHEET NAME:
5.1 FIGURE 5.1 on ANSWER SHEET 2 a 45° cut-off cylindrical pipe.
Use ANSWER SHEET 2 and develop and draw the development of the cut-
off of the cylindrical pipe on scale 1 : 1. (14)
0 1 2 3 4 5 6 7 8 9 1 1 1
SIDE VIEW 0 1 2
9
10 8
11 7
12
0 6
1 5
2 4
3
TOP VIEW
Copyright reserved Please turn over
Downloaded from hlayiso.com
(EC/NOVEMBER 2022) CIVIL TECHNOLOGY: CIVIL SERVICES 17
ANTWOORDBLAD NAAM:
3 CIVIL SERVICES
ANSWER SHEET NAME:
5.6 Use the quantity list on ANSWER SHEET 3 and determine the volume of
concrete needed for a floor of 6 m long, 3 m wide and 75 mm thick. (3)
5.7 Use the quantity list on ANSWER SHEET 3 and determine the number bricks
needed for a cavity wall with a length of 4 m and a height of 2,4 m. (5)
A B C D
5.6
1/ 6 Volume concrete: 6 m x 3 m x 75 mm.
3
0,75 13,5 Thus: 13,5 m2 concrete needed for the floor.
beton
5,7
1/ 4 Quantity bricks: 4 m x 2,4 m.
2,4 9,6 Wall area. = 9,6 m2
9,6
100 960 Thus: 960 bricks needed for wall.
Copyright reserved Please turn over
Study this subject
Recommended for this subject

Question paper
Civil Technology Grade 11 Exemplar November 2022 QP (Eng)
/CIV%20TECH%20GR11%20QP%20NOV2022_Civil%20Services_English_hlayiso.com_--ed0b5808-e643-408f-bef2-165736e1c4b6/v1-0797091449081c3c3dfd/card.webp)
Question paper
Civil Technology Grade 11 2022 QP (Eng)
/CIV%20TECH%20GR11%20QP%20NOV2022_Construction_English_hlayiso.com_--ef9cc9f6-54a4-49fb-a7b1-407a487eeec8/v1-ddd234b1e4aa182f38ab/card.webp)
Question paper
Civil Technology Grade 11 2022 QP (Eng)

Memorandum
Civil Technology Grade 11 Eastern Cape November 2019 Memo

Practical assessment task
Civil Technology PAT GR 11 2017 Eng
%20Afr%20Nov%202020_SIVIELE%20DIENSTE_hlayiso.com_.docx_hlayiso.com_--a014afb0-d15f-4eaa-838f-0768b568dc8b/v1-faed7b104eb0fbf75540/card.webp)
Memorandum
Civil Technology Grade 11 Eastern Cape November 2020 Memo
More from Grade 11 Civil Technology

Annual teaching plan
Gr 11 Cons ATP 2023 24

Annual teaching plan
Gr 11 Civil Ser ATP 2023 24

Memorandum
Civil Technology Grade 11 Eastern Cape November 2020 Memo

Memorandum
Civil Technology Grade 11 Eastern Cape November 2020 Memo

Memorandum
Civil Technology Grade 11 Eastern Cape November 2020 Memo

Memorandum