GRAAD 12
SENIOR CERTIFICATE/
NATIONAL SENIOR CERTIFICATE
GRADE 12
CIVIL TECHNOLOGY: CONSTRUCTION
NOVEMBER 2020
MARKING GUIDELINES
MARKS: 200
These marking guidelines consist of 20 pages.
Copyright reserved Please turn over
Skip to contentAll 2020 papers %20Memo%20Afr_hlayiso.com_--8cffc125-69c0-44e9-b0eb-88ae7e930363/v1-fca2156d2557644edb35/card.webp)
%20Afr_hlayiso.com_--b796705a-6588-4c35-a6ed-9d9659bce995/v1-978b69e54ed8b19a2f08/card.webp)
%20Eng_hlayiso.com_--f45b898c-a9ab-4069-ae4b-2b730f88cf1b/v1-5a72c6e9110b3de20e2e/card.webp)
%20Eng_hlayiso.com_--6e24138d-3f1b-42f9-8076-7ae0b7db457a/v1-e0a7b2645cde7f912d21/card.webp)
%20Eng_hlayiso.com_--8ecb8551-97e5-4a57-8187-0130f8d158da/v1-b424a911dcff7aea0ac5/card.webp)
%20Afr_hlayiso.com_--7e3d3218-d564-4a19-b535-b7ed8a417256/v1-01d006aa21634bdcd998/card.webp)
View all
%20(English%20and%20Afrikaans)%20June%202025%20Question%20Paper--c8edd459-5237-48e0-8588-69d7ecd7f8e5/v1-be996aaed91bf782e098/card.webp)
%20Afr--591d6ffd-20b1-4748-a1ba-b055be0a14c3/v1-4d98a131fd37e013458a/card.webp)
%20Afr--05a95faf-5891-4d88-9e5e-7d13c1d21648/v1-f5ca67113376f7457b83/card.webp)


Civil Technology Grade 12 NSC November 2020 Memo (English)
Grade 12 Civil Technology memorandum from the NSC November Exam 2020 (English), 20 pages. Read online or download the free PDF.
Civil Technology · Grade 12 · NSC November Exam · 2020. Memorandum, 20 pages. Read online or download the PDF.
- Subject
- Civil Technology
- Grade
- Grade 12
- Document type
- Memorandum
- Year
- 2020
- Exam period
- NSC November Exam
- Curriculum
- CAPS
- Pages
- 20
- File size
- 437.1 KB
Free to read online, no sign-up needed
Loading document…
Loading document…
1 of 20
This exam
Document textSearch extracted text and jump to a page.
Downloaded from hlayiso.com
Civil Technology: Construction 2 DBE/November 2020
SC/NSC – Marking Guidelines
INSTRUCTIONS FOR THE MARKERS
1. Markers should:
Familiarise themselves with the question and answer before evaluating the
responses of candidates.
Always interpret the responses of the candidates within the context of the
question.
Consider any relevant and acceptable answer during pre-marking but
should strictly adhere to the answers after finalisation of the marking
guideline.
There are two approaches to answering questions, these are (1) to describe
and (2) to explain.
If a candidate is required to explain e.g., a process in 4 steps, only the first 4
responses should be considered.
If, however a candidate is required to e.g., explain or describe how to
transfer heights from one point to another using a transparent pipe level we
need to consider that candidates may write a long description not
necessarily well organised as an intellectual response may do. In this case
the marker needs to evaluate the complete statement to judge if the
candidate explained the required outcome satisfactorily and allocate marks
on merit. The marker should apply his/her professional judgement with
these types of questions.
Mark what the candidate wrote and do not award marks for answers that the
marker thinks the candidate meant with what was written.
Indicate the tick or cross right at the position where the mark needs to be
awarded or where the candidate made the error.
Accept the letter corresponding with the correct answer as well as the
answer written in full in multiple-choice questions.
Accept incorrect spelling in one-word answers unless the spelling changes
the meaning of the answer.
2. For calculations:
A mark is only awarded if the correct unit is written next to the answer.
If TWO marks are awarded ONE mark is awarded for the answer and ONE
mark for the correct unit.
Where the candidate made a principle error e.g. added instead of
multiplying, no marks will be awarded for the steps. If the answer is correct
according to what the candidate did, the mark for the answer can be
awarded for the application of skills.
Where an incorrect answer could be carried over to the next step, the first
answer will be deemed incorrect. However, should the incorrect answer be
carried over correctly, the marker has to recalculate the values, using the
incorrect answer from the first calculation. If correctly used, the candidate
should receive the full marks for subsequent calculations.
Markers should consider when and where a candidate has rounded off in a
calculation, as well as the subsequent effect it has on the final answer
obtained. The calculation should therefore be awarded marks on merit.
Alternative methods of calculations must be considered, provided that the
correct answer is obtained.
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 3 DBE/November 2020
SC/NSC – Marking Guidelines
3. When marking drawings:
The member for which the mark should be awarded should be drawn
correctly in the correct position to receive a mark.
A member incorrectly drawn but wrongfully repeated in another position will
be awarded the mark for the repeated incorrect member provided that the
marking guideline provide for TWO or more marks for that member (positive
marking).
Marks can only be awarded for a label if the label is correctly indicating the
correct member.
Scale drawings should always be marked using an appropriate mask.
When a candidate drew the wrong drawing e.g.:
A horizontal section instead of a vertical section, no marks will be allocated
to the drawing as the candidate did not respond to the expected outcome.
An orthographic view instead of sectional view, no marks will be allocated to
the drawing as the candidate did not respond to the expected outcome.
An orthographic view instead of an isometric view, no marks will be
allocated to the drawing as the candidate did not respond to the expected
outcome.
If the incorrect drawing was drawn, the candidate can be awarded for only
what was asked but mark/s for the correctness of the drawing will not be
awarded e.g., if a King Post roof truss was asked in the question, and
candidate drew SA-Howe Truss
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 4 DBE/November 2020
SC/NSC – Marking Guidelines
QUESTION 1: OHSA, SAFETY, MATERIALS, TOOLS, EQUIPMENT AND JOINING
(GENERIC)
1.1 1.1.1 E (1)
1.1.2 C (1)
1.1.3 D (1)
1.1.4 H (1)
1.1.5 B (1)
1.1.6 F (1)
1.1.7 A/I (1)
1.1.8 G/K (1)
1.2 Galvanising:
Adds strength to the original, uncoated metal.
Make it last longer/Preservation/Durable.
Decorative/Enhance appearance.
Makes metal thicker than the uncoated metal.
Nails and screws prevent staining.
Prevent the material from rusting/corroding.
ANY ONE OF THE ABOVE (1)
1.3 Material safety data sheet.
Sufficient information regarding the protection of health and safety.
ANY ONE OF THE ABOVE (1)
1.4 Materials can be moved manually/by means of a wheelbarrow/trolley.
Materials can be moved by means of machinery/builders hoist/truck/
crane/tractor/conveyor/fork lift. (2)
1.5 Water-based paint:
Dry quickly.
Allows marks/smudges to be easily cleaned with water.
Give an elastic flexible finish.
Durable
Gives a decorative finish.
Enhances the appearance.
Resistant to cracking.
Cost effective/Cheaper
Easy to apply.
ANY TWO OF THE ABOVE (2)
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 5 DBE/November 2020
SC/NSC – Marking Guidelines
1.6 1.6.1 Multi detector (1)
1.6.2 Care of the multi detector:
Place the multi-detector in its holder directly after use.
Do not bump the instrument against objects or drop it.
Protect the multi-detector against moisture and direct sunlight.
If the measuring tool is not used for a long period, remove the
battery.
Wipe away dirt or spots with a dry, soft cloth.
Switch off the device before storing.
ANY TWO OF THE ABOVE (2)
1.7 Drill a hole in the wall.
Insert the plastic plug into the hole.
Align the hole in the bracket with the hole in the wall and fasten the
screw. (3)
[20]
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 6 DBE/November 2020
SC/NSC – Marking Guidelines
QUESTION 2: GRAPHICS AS MEANS OF COMMUNICATION (GENERIC)
NO. QUESTION ANSWER MARKS
Identify the elevation in FIGURE
1 South Elevation 1
A.
Describe the type of house that is Double-storey house/Building/Multi-storey
2 1
indicated in FIGURE A. building
Ridge Capping/Ridge tile/Ridge
3 Identify number 1. 1
plate/Ridge
4 Identify number 3. Fascia board 1
5 Identify number 4. Overhang/Eave/Dimension line 1
Identify the fastener indicated by
6 Holder bat/Clamp/Clip 1
number 5.
Window/Window frame/Casement/
7 Identify number 6. 1
Casement frame
Shoe/Down pipe outlet/
8 Identify number 7. 1
Spout
9 Identify number 8. Natural ground level/NGL 1
What does DPM stands for, as
10 Damp proof membrane 1
indicated in the notes?
11 Identify number 10. Built-in cupboard/BIC 1
Recommend a suitable material Fibre cement/Galvanised sheeting/Sheet
that can be used for the metal/Timber/Wood/Plastic/Fibre
12 glass/Aluminium sheeting 1
manufacturing of number 2 in
FIGURE A.
Name the TWO elevations on West elevation
13 2
which number 2 is installed. East elevation
The gutter is fixed against it.
Describe the purpose of number
14 It finishes off the roof. 1
3.
Protect roofs/rafters from rainwater.
Deduce ONE feature that has Step missing at the door
15 been omitted from the elevation in 1
FIGURE A. Sill missing at the window
Recommend any TWO sanitary Hand basin/Wash hand basin/Hand
fitments carrying waste water basin/Basin/WB/WHB/HB
16 other than a bath that can be 2
Shower/SH
installed in the room indicated by
number 11.
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 7 DBE/November 2020
SC/NSC – Marking Guidelines
What sanitary fixture carrying soil Water closet/WC
17 water can be installed in the room 1
indicated by number 12? Bidet/BT
The two side windows are opening to the
Describe the error that appears at wrong sides/No window sill/The window
18 number 6 in the elevation in 1
drawn in FIGURE A is not the same as that
FIGURE A. in the window schedule/Window opening.
State the reference code for this
19 QP 4 - 2020 1
plan.
20 Which room will number 13 serve? Bedroom 2 1
Electrical wiring/cable/connection
21 What does the line between Wiring/Wiring from light switch to
1
numbers 13 and 14 represent? light/Shows which switch operates which
electrical fitting
15: Single tube fluorescent light/
17: Double/ tube fluorescent light.
Differentiate between number 15 15: Will use less electricity/Watt than 17/
22 in FIGURE B and number 17 in 15: Will provide less light than 17/ 2
the notes. 15: Running cost will be cheaper than 17.
15: Has one tube/1 x 40 Watt.
17: Has two tubes/2 x 40 Watt.
Explain the installation of brick
Brick force must be installed between
force from the top of the window to
23 every course above the window up to wall 1
the wall plate, as indicated by the
plate.
architect.
Face bricks
Plaster and paint/Plaster/Paint/Plaster
Recommend a possible finish for
24 finish (Smooth finish/Splatter finish/Wavy 1
the outside walls of the house.
finish/Bagging finish)
Cladding/Tiling
Deduce from FIGURE 2 which
25 elevation does NOT have East elevation 1
windows.
Deduce the thickness of the
26 220 mm 1
external wall from FIGURE 2.
Name a material that can be used
Wood/Timber/Stainless steel/Mild
27 to close the open sides of number 1
steel/Steel/Aluminium/Glass/Perspex
16.
Name the town in which the
28 Cradock 1
proposed dwelling will be build.
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 8 DBE/November 2020
SC/NSC – Marking Guidelines
Calculate the area of the ℓxb ℓxb
bathroom. Show ALL calculations.
29 Give your answer in m². = 2 m x 2 m OR 2 000 mm x 2 000 mm 3
= 4 m² = 4 m²
30 Calculate the total length of the 220 + 3 000 + 110
wall on the eastern side of the
building. Show ALL calculations. + 1 400 + 110 + 2 000 +220
The length must be indicated in = 7 060 mm
metres.
= 7,06 m
6
OR
220 + 3 000 + 110 + 3 510 + 220
= 7 060 mm
= 7,06 m
TOTAL: 40
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 9 DBE/November 2020
SC/NSC – Marking Guidelines
QUESTION 3: ROOFS, STAIRCASES AND JOINING (SPECIFIC)
3.1.1 760 mm (1)
3.1.2 Sisalation/Fire-proof material (1)
3.1.3 300 mm (1)
3.1.4 Fibre cement tiles (1)
3.1.5 76 x 50 mm/38 x 38 mm (1)
3.2 3.2.1 750 mm (1)
3.2.2 1,5 m/2 m/2,1 m (1)
3.2.3 All stairs must have handrails/Stairs must be secured.
The regulations as stipulated by local authorities or SANS
should be met when stairs are built or cast.
ANY TWO OF THE ABOVE (1)
3.3 Rise: vertical distance between two consecutive threads.
Riser: vertical member between two consecutive threads. (2)
3.4 Pitch board (1)
3.5 Balustrades:
hold up the handrail.
fills the space between the handrail and string on the open side of a
staircase.
prevent people from falling off the staircase.
ANY TWO OF THE ABOVE (2)
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 10 DBE/November 2020
SC/NSC – Marking Guidelines
3.6
RAFTER
CLOUT NAILS
TIE-BEAM
WALL PLATE
HOOP-IRON STRAP
WALL
CORRECTNESS OF DRAWING
ASSESSMENT CRITERIA MARK
Brick wall 1
Wall plate 1
Tie beam 1
Rafter 1
Hoop-iron strap 3
Clout nails 1
Correctness of drawing 1
TOTAL: 9
(9)
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 11 DBE/November 2020
SC/NSC – Marking Guidelines
3.7
KING POST 114 X 38 MM
STRUTS 114 X 38 MM
TIE-BEAM 114 X 38 MM
JUNCTION AT THE TIE-BEAM, KING POST AND STRUTS
SCALE 1:10
APPLICATION OF SCALE
CORRECTNESS OF DRAWING
(USE A MASK TO MARK THIS QUESTION)
ASSESSMENT CRITERIA MARK
Tie beam 1
King post 1
Struts 2
Any ONE label with dimensions 2
Application of scale 1
Correctness of drawing 1
TOTAL: 8
(8)
[30]
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 12 DBE/November 2020
SC/NSC – Marking Guidelines
QUESTION 4: EXCAVATIONS, FORMWORK, TOOLS, EQUIPMENT AND
MATERIALS (SPECIFIC)
4.1 Removal of soil/earth. (1)
4.2 The sides of the excavations can collapse/crack. (1)
4.3 Tension cracks will appear/collapse. (1)
4.4 Start at the bottom of the excavation. (1)
4.5 A fence/suitable barrier/warning signs must be provided
The working edge of each ditch deeper than 2 m must be inspected by a
competent person before the start of each shift.
ANY ONE OF THE ABOVE (1)
4.6 4.6.1 Location of the following services:
Electric cables
Water pipes
Gas lines
Communication line
Sanitation services
ANY TWO OF THE ABOVE (2)
4.6.2 Trenches should be inspected:
before workers working in it.
at the start of each shift.
following rainfall or other water intrusion.
ANY ONE OF THE ABOVE (1)
4.7 4.7.1 Safety precautions to be considered:
Operate with care.
Wear appropriate personal equipment e.g., gloves and
boots.
Avoid making any adjustments while the machine is vibrating.
Never use a faulty machine.
Never lay the machine on its side.
Do not place your hands and feet near the moving parts.
Switch off the machine when it is left unattended.
Use both hands to operate the machine.
Ensure a firm and well-balanced stance.
Check the controls for proper response before use.
Check the condition of the machine at the start and end of
every shift.
Report any defects.
ANY TWO OF THE ABOVE (2)
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 13 DBE/November 2020
SC/NSC – Marking Guidelines
4.7.2 Stored in a safe, dry place to:
prevent corrosion/rust.
protect the machine
prevent machine from being damaged by moisture.
ANY ONE OF THE ABOVE (1)
4.8 4.8.1 Cube test (1)
4.8.2 A - Tamping rod/Steel rod
B – Mould/Cube (2)
4.8.3 7 days
14 days
28 days
ANY TWO OF THE ABOVE (2)
4.8.4 Compressive strength (1)
4.9 Properties of ductile cast iron:
Excellent ability to withstand blows and knocks.
Very good fatigue strength/limit.
Elasticity makes it ideal for casting.
ANY TWO OF THE ABOVE (2)
4.10 Material to fix cladding to a wall:
Silicon
Cement based mixture
Colour matching screws/Face fixings
Tile adhesive
Proprietary fixings
ANY ONE OF THE ABOVE (1)
4.11 Poling boards are used to:
keep the soil from entering the excavation.
prevent soil from falling into the trench/collapse.
ANY ONE OF THE ABOVE (1)
4.12 To keep the poling boards in place.
To keep the struts in place. (2)
4.13 One/Two (1)
4.14 Poling boards for firm soil are spaced further apart.
Polling boards for loose soil are spaced closer together. (2)
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 14 DBE/November 2020
SC/NSC – Marking Guidelines
4.15
WALL 220 mm
LANDING
WALL
STRING
SHUTTERBOARD
BEVELLED
RISER
CLEAT PROP
BEARER
JOIST
CROSS
BEARERS
FOLDING WEDGES
CLEAT
SOLE PLATE
CORRECTNESS OF DRAWING
ASSESSMENT CRITERIA MARK
Cross bearers 1
Bearer/Joist 1
Props 3
Folding wedges 2
Cleats to support props 1
Wall string 1
Bevelled riser 2
Cleats 2
Correctness of drawing 1
TOTAL: 14 (14)
[40]
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 15 DBE/November 2020
SC/NSC – Marking Guidelines
QUESTION 5: PLASTER AND SCREED, BRICKWORK AND GRAPHICS AS
MEANS OF COMMUNICATION (SPECIFIC)
5.1 5.1.1 Splatter finish/Splatter dash finish/Roughcast finish (1)
5.1.2 Bagging finish (1)
5.2 Purpose of screed:
To provide a smooth/level/neat/flat surface.
To increase the structural depth and strength of the base slab.
To prepare floor for floor covering. (2)
5.3 Preparing a smooth concrete floor to receive the screed:
Chip the surface with a sharp tool to remove the surface skin and expose
the hard, clean concrete.
Wet the surface.
ANY ONE OF THE ABOVE (1)
5.4 Builders' lime (1)
5.5 Rough arch - the mortar joint will be wedge shaped/triangular shaped.
Gauged arch - the mortar joint will be uniform/rectangular shape. (2)
5.6
FIRST COURSE
SECOND COURSE
ASSESSMENT CRITERIA MARK
Stretcher bond - first course 5
Stretcher bond - second course 5
TOTAL: 10 (10)
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 16 DBE/November 2020
SC/NSC – Marking Guidelines
5.7
PLASTER
EXTERIOR REVEAL
DOOR FRAME 110 mm X 70 mm
DPC ATTACHED TO THE DOOR FRAME
QUARTER ROUND
CORRECTNESS OF 220 mm BRICK WALL
DRAWING
(USE A MASK TO MARK THIS QUESTION)
ASSESSMENT CRITERIA MARK
Wall 220 mm 2
Plaster 12 mm 2
Exterior reveal 1
Door frame 110 mm x 70 mm 2
DPC attached to door frame 1
Quarter rounds 2
Any ONE label 1
Correctness of drawing 1
TOTAL: 12 (12)
[30]
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 17 DBE/November 2020
SC/NSC – Marking Guidelines
QUESTION 6: REINFORCEMENT IN CONCRETE, FOUNDATIONS, CONCRETE
FLOORS AND QUANTITIES (SPECIFIC)
6.1 6.1.1 A (1)
6.1.2 C (1)
6.1.3 B (1)
6.1.4 D (1)
6.1.5 D (1)
6.2 Reasons for the installation of pile foundations:
Poor soil conditions
Soft soil
Unstable soil
Loose soil
Non-cohesive soil
Where there is soil movement.
Constantly wet areas.
Ground conditions are not stable enough to support ordinary, shallow
foundations.
Foundation piles distribute the load to more stable ground and can be
used as underground or underwater supports.
Piles provide stability when a raft or floating foundation is used.
When structures are subjected to horizontal forces, pile foundations resist
bending stress while still lending vertical support, e.g., multi storey
buildings.
Where soils are prone to swelling and shrinking according to the moisture
content, e.g., for clay soil, shallow foundations cannot be used.
When the superstructure is exposed to uplifting forces, e.g., offshore
platforms.
Where soil erosion is possible, piles should be used to carry the load of
the superstructure, e.g., for bridges and piers.
ANY TWO OF THE ABOVE (2)
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 18 DBE/November 2020
SC/NSC – Marking Guidelines
6.3
STEEL CABLE
STEEL PIPE CASING
DROP HAMMER
CORRECTNESS OF DRAWING
ASSESSMENT CRITERIA MARK
Steel cable 1
Steel pipe-casing 1
Drop hammer 1
Any ONE label 1
Correctness of drawing 1
TOTAL: 5 (5)
6.4.1 Consequences:
Block will not be supported/fall through/collapse.
No bonding between the rib and block.
Installation will not be successful.
The block will be heavy as there is no holes in it.
Service pipes may not be able to be laid.
ANY TWO OF THE ABOVE (2)
6.4.2
ASSESSMENT CRITERIA MARK
Hollow block 2
Rebates in block 2
Reinforcement in ribs 2
TOTAL: 6 (6)
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 19 DBE/November 2020
SC/NSC – Marking Guidelines
6.4.3 220 mm (1)
6.5
8 MAIN BARS
COLUMN
STIRRUP
COVER DEPTH
CORRECTNESS OF DRAWING
ASSESSMENT CRITERIA MARK
Column 2
Stirrup 1
Main bars 2
Cover depth indicated 1
Correctness of drawing 1
TOTAL: 7
(7)
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 20 DBE/November 2020
SC/NSC – Marking Guidelines
6.6 A B C D
Internal measurement of floor:
4 500 – 440 = 4 060 (4,06 m)
6 500 – 440 = 6 060 (6,06 m)
Area of floor:
1/ 4,06
6,06 24,6 m2
(5)
Volume of concrete for the
floor:
24,6
0,075 1,85 m3
OR
4,06
6,06
(2)
0,075 1,85 m3
Number of tiles to cover the floor:
1/ 0,35 One tile is 350 mm x 350 mm
0,35 0,12 m2 Area of one tile = 0,12 m²
24,6 m²
0,12 m²
= 205 tiles (5)
[40]
TOTAL: 200
Copyright reserved
Study this subject
Recommended for this subject
%20Memo%20Afr_hlayiso.com_--8cffc125-69c0-44e9-b0eb-88ae7e930363/v1-fca2156d2557644edb35/card.webp)
Memorandum
Civil Technology Grade 12 NSC November 2020 Memo (Afrikaans)
%20Afr_hlayiso.com_--b796705a-6588-4c35-a6ed-9d9659bce995/v1-978b69e54ed8b19a2f08/card.webp)
Question paper
Civil Technology Grade 12 NSC November 2020 QP (Afr)
%20Eng_hlayiso.com_--f45b898c-a9ab-4069-ae4b-2b730f88cf1b/v1-5a72c6e9110b3de20e2e/card.webp)
Question paper
Civil Technology Grade 12 NSC November 2020 QP (Eng)
%20Eng_hlayiso.com_--6e24138d-3f1b-42f9-8076-7ae0b7db457a/v1-e0a7b2645cde7f912d21/card.webp)
Question paper
Civil Technology Grade 12 NSC November 2020 QP (Eng)
%20Eng_hlayiso.com_--8ecb8551-97e5-4a57-8187-0130f8d158da/v1-b424a911dcff7aea0ac5/card.webp)
Question paper
Civil Technology Grade 12 NSC November 2020 QP (Eng)
%20Afr_hlayiso.com_--7e3d3218-d564-4a19-b535-b7ed8a417256/v1-01d006aa21634bdcd998/card.webp)
Question paper
Civil Technology Grade 12 NSC November 2020 QP (Afr)
More from Grade 12 Civil Technology

Question paper
Civil Technology Grade 12 Eastern Cape Mock 2025 QP (Eng)
%20(English%20and%20Afrikaans)%20June%202025%20Question%20Paper--c8edd459-5237-48e0-8588-69d7ecd7f8e5/v1-be996aaed91bf782e098/card.webp)
Question paper
Civil Technology Grade 12 Gauteng June 2025 QP (Afr)
%20Afr--591d6ffd-20b1-4748-a1ba-b055be0a14c3/v1-4d98a131fd37e013458a/card.webp)
Question paper
Civil Technology Grade 12 NSC June 2025 Question Paper (Afr)
%20Afr--05a95faf-5891-4d88-9e5e-7d13c1d21648/v1-f5ca67113376f7457b83/card.webp)
Question paper
Civil Technology Grade 12 NSC November 2025 QP (Afr)

Question paper
Civil Technology Grade 12 Eastern Cape Prelim 2024 QP (Afr)

Question paper