CIVIL TECHNOLOGY: CONSTRUCTION
2019
MARKING GUIDELINES
MARKS: 200
These marking guidelines consist of 19 pages.
Copyright reserved Please turn over
Skip to contentAll 2019 papers %20Memo%20Afr_hlayiso.com_--2a9b9e1b-37dc-48dc-9aa7-67dd5fa19a10/v1-8a03885eb99c8043e8b1/card.webp)
%20Memo%20Eng_hlayiso.com_--8c1355fc-f6e2-40c6-85ff-1d03eb2991ea/v1-808c163218d7215c1652/card.webp)
%20Eng_hlayiso.com_--3f3d8211-a2ae-4ecd-89a4-623bb435b86a/v1-648207bcb15a032d7837/card.webp)
%20Afr_hlayiso.com_--87c657e9-94a5-422f-ade2-b3b897806384/v1-9312fb31c11787e210aa/card.webp)
%20Afr_hlayiso.com_--bdea7087-4612-4372-bd72-70147466f760/v1-e8611611e9b476da11a3/card.webp)
%20Memo%20Afr_hlayiso.com_--13c03cd5-cfa4-42cf-9a7c-5d7b0e1069f0/v1-b52b9528a267b4d4a925/card.webp)
View all%20(English%20and%20Afrikaans)%20June%202025%20Question%20Paper--c8edd459-5237-48e0-8588-69d7ecd7f8e5/v1-be996aaed91bf782e098/card.webp)
%20Afr--591d6ffd-20b1-4748-a1ba-b055be0a14c3/v1-4d98a131fd37e013458a/card.webp)
%20Afr--05a95faf-5891-4d88-9e5e-7d13c1d21648/v1-f5ca67113376f7457b83/card.webp)


%20Afr--eefaae29-fe93-4b75-8223-87bf4f3fc14c/v1-3553acfa446acbaa2a45/card.webp)
Civil Technology Grade 12 NSC June 2019 Memo (English)
Grade 12 Civil Technology memorandum from the NSC June Exam 2019 (English), 19 pages. Read online or download the free PDF.
Civil Technology · Grade 12 · NSC June Exam · 2019. Memorandum, 19 pages. Read online or download the PDF.
- Subject
- Civil Technology
- Grade
- Grade 12
- Document type
- Memorandum
- Year
- 2019
- Exam period
- NSC June Exam
- Curriculum
- CAPS
- Pages
- 19
- File size
- 406.2 KB
Free to read online, no sign-up needed
Loading document…
Loading document…
1 of 19
This exam
Document textSearch extracted text and jump to a page.
Downloaded from hlayiso.com
Civil Technology: Construction 2 DBE/2019
SC/NSC – Marking Guidelines
QUESTION 1: OHSA, SAFETY, MATERIALS, TOOLS, EQUIPMENT AND JOINING
(GENERIC)
1.1 1.1.1 G (1)
1.1.2 E (1)
1.1.3 A (1)
1.1.4 C (1)
1.1.5 D (1)
1.2 • When heavy materials/loads are not lifted/lowered/handled correctly.
• Wrong posture when lifting materials.
• Not using safety apparel.
ANY ONE OF THE ABOVE (1)
1.3
1 : 4 OR 76° (2)
1.4 • A qualified person must operate the device.
• The device must never be overloaded.
• The gates and wire components of the lift of the hoisting device must be
at least 1 980 mm high.
• The gates must be shut when the device is being used.
• Emergency brake mechanisms must be installed.
• Safety measures must be displayed inside the cage.
• Inspections and maintenance work should be carried out regularly
(at least six-monthly) by qualified persons.
• Overhead protection must be provided to protect workers from falling
objects.
• When material or equipment is being hoisted, it must be stacked firmly
and correctly, and secured properly.
• The hoist must be inspected weekly by a qualified person.
ANY TWO OF THE ABOVE (2)
1.5.1 A = Laser level
B = Dumpy level (2)
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 3 DBE/2019
SC/NSC – Marking Guidelines
1.5.2 Laser level (A) Dumpy level (B)
To determine levels when: The dumpy level is used
• installing ceilings and floor tiles. when:
• installing chair rails for example in • determining differences
a dining room. between levels and
• installing receptacles for power vertical heights,
inside a building during especially over longer
construction. distances.
• hanging pictures. • determining levels and
• excavating for new buildings. slopes.
• aligning and levelling floors. • setting out buildings.
• when installing doors and windows. • transferring levels and
• aligning shelves and cabinets. heights.
• levelling post and beams on decks, • determining/measuring
fences and porches. the distances between
• setting out buildings on a site. two points.
• aligning fences, post and decks.
• determining gradient/slope for
drainage and irrigation.
• establishing contours for farming or
drainage.
• To determine levels and slopes
when installing sewer pipes.
ANY ONE IN EACH COLUMN ABOVE (2)
1.6 1.6.1 Rawl bolt (1)
1.6.2 A – Drill a hole of the required diameter and depth.
B – Remove debris and thoroughly clean the hole with a brush or
by blowing into it.
C – Remove the bolt and washer, insert the sleeve/shield into the
hole and align the fixture (for example base plate, etc…) with
the hole.
D – Insert the bolt with washer through the fixture and tighten to the
recommended torque. (4)
1.6.3 Rawl bolts:
• are stronger fasteners than a screw with a plastic plug.
• are designed to resist pull-out failure.
• have excellent mechanical properties such as tensile and yield
stress.
• have excellent carrying capacity.
• have excellent tolerance to variance in the hole size.
ANY ONE OF THE ABOVE (1)
[20]
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 4 DBE/2019
SC/NSC – Marking Guidelines
QUESTION 2: GRAPHICS AS MEANS OF COMMUNICATION (GENERIC)
ANSWER SHEET 2
NO. QUESTIONS ANSWERS MARKS
1 Identify the elevation shown in
Eastern/East elevation/East 1
FIGURE A.
1
2 Name the scale of FIGURE B. 1 : 100
1
3 Identify number 1. Barge board
1
4 Identify number 2. Roof overhang/Eave/Open eave
5 Recommend a suitable finish for Plaster/Paint/Face brick/Tiles/
number 3. 1
Cladding
6 What is indicated by number 4? Door/Entrance door/Door opening 1
7 Identify the drawing symbol indicated
Finished floor level/FFL
by number 5. 1
8 Identify the drawing symbol indicated
Natural ground level/NGL 1
by number 6.
9 What is indicated by number 7? Step 1
10 Give the date on which the building
1
plan was printed. 2019/06/16
1
11 Who checked the building plan? P Blade
12 Name the electrical drawing symbol Two-way switch
in the column for the notes in
1
FIGURE 2 that must be placed at a
staircase.
DO NOT MARK
THESE QUESTIONS
13 Name the electrical feature in the
column for the notes in FIGURE 2
Wall light 1
that must be placed at the entrance
door of the house.
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 5 DBE/2019
SC/NSC – Marking Guidelines
14 Identify the type of roof that is
used on the building in Gable roof 1
FIGURE A.
15 Explain the purpose of number 1. To cover ends of purlins/battens/fixed to
the purlins/battens for a neat appearance. 1
To finish of the gable end of the roof.
16 Who is the owner of this house? Mr H Smith 1
17 In which street is the proposed
Jupiter street 1
dwelling situated?
18 Identify number 8. Rainwater down pipe/Downpipe 1
19 To wash your face/Body
What is the sanitary fitting Brush your teeth 1
indicated by number 9 used for? Wash your hands
Washing/Rinsing
20 Recommend an alternative
sanitary fitting to replace
Bath 1
number 10 that will serve a similar
purpose.
21 Explain the purpose of number 11 Landing to serve as resting place or
1
as indicated on the staircase. change of direction of staircase.
22 Emergency light/External light
What is indicated by number 13? 1
Thickness of wall/110 mm
23 What is indicated by number 15? North- symbol/direction/point 1
24 Deduce the height of window 1
1,8 m or 1 800 mm 1
from the window schedule.
25 Deduce the width of window 2
2,4 m or 2 400 mm 1
from the window schedule.
26 Name the elevations of the
building on which the staircase is Western/West elevation/West 2
situated. Southern/South elevation/South
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 6 DBE/2019
SC/NSC – Marking Guidelines
27 12 – One way light switch single pole/
Differentiate between the
electrical symbols indicated by lever 2
numbers 12 and 14. 14 – One way light switch double pole/
lever
28 Recommend a suitable floor Tiles/Novilon/Carpets/Laminated
1
covering for the lounge. flooring/Wooden flooring.
29 Calculate the area of the lounge 6 m x 3 m = 18 m²
in m². Show ALL calculations.
OR 3
6 000 mm x 3 000 mm = 18 m²
30 Calculate the perimeter of the (220 + 3 000 + 110 + 3 000 + 220) x 2
building. Show ALL calculations.
= 6 550 x 2
=13 100 mm
(220 + 6 000 + 220) x 2
= 6 440 x 2 7
= 12 880 mm
13 100 + 12 880
= 25 980 mm OR
= 25,98 m
TOTAL: 40
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 7 DBE/2019
SC/NSC – Marking Guidelines
QUESTION 3: ROOFS, STAIRCASES AND JOINING (SPECIFIC)
3.1 17° (1)
3.2 76 mm x 50 mm OR 76 mm x 76 mm (2)
3.3 650 mm (1)
3.4 Tilting batten/Foot batten (1)
3.5 A - King post
B - Rafter
C - Strut
D - Queen post
E - Tie beam (5)
3.6
Any TWO labels
Rafter
Wall
Wall plate
Span
Wall
Proportion
IF A LINE DIAGRAM IS DRAWN MINUS ONE MARK FOR PROPORTION
ASSESSMENT CRITERIA MARK
Span 1
Walls 2
Wall plate 1
Rafter 1
Any TWO labels 2
Proportion 1
TOTAL: 8
(8)
3.7 • At least 300 mm to 600 mm for concrete tile.
• The galvanised strap should be embedded above the lintel and the last
course of bricks at wall plate level.
• At least four brick courses.
ANY ONE OF THE ABOVE (1)
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 8 DBE/2019
SC/NSC – Marking Guidelines
3.8 3.8.1 Nosing (1)
3.8.2 Apron (1)
3.8.3 Pitch board (1)
3.8.4 Stairwell (1)
3.8.5 Handrail (1)
3.9 38° (1)
3.10 • Long steel bolts are placed into holes of a loose template base plate,
which is placed into the wet concrete.
• Allow the concrete to dry.
• Weld the base plate to the column/drill holes in the base plate/Fit
prefabricated column over bolts and fasten.
• Place the column with a steel foot plate with holes in over the bolts after
the concrete has dried.
• The column is then bolted firmly into the concrete base. (5)
[30]
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 9 DBE/2019
SC/NSC – Marking Guidelines
QUESTION 4: EXCAVATIONS, FORMWORK, TOOLS AND EQUIPMENT AND
MATERIALS (SPECIFIC)
4.1 4.1.1 • Very strong
• Very tough
• Easy to cast into shapes
• Durability/Long lasting/Sturdy
• Good tensile and yield strength
• Good thermal conductivity
• Resistance against corrosion if protected (painted, oxide)
• Ductile
• Easy to weld
• Heavy/High density
ANY TWO OF THE ABOVE (2)
4.1.2 • Very soft metal
• Malleable – can be stretched in any direction
• Heavy/High density
• Corrosion-proof
• Low melting point
• Blue-grey metal
• Highly toxic
• Ductile
• Durability/Long lasting
• Easy to cut
ANY TWO OF THE ABOVE (2)
4.2 Purpose of the cube test:
• To determine the maximum compressive strength of cured concrete
when load is applied.
• To ensure that the concrete complies with the requirements of the project
specifications.
• To indicate the compressive strength (measured in MPa or N/m²), thus its
ability to resist loads.
ANY TWO OF THE ABOVE (2)
4.3 4.3.1 Safety factors to be considered before excavations:
• Ensure that a competent person evaluates the stability of the
ground.
• Draw up a safety plan.
• Take sufficient steps to ensure safe working conditions.
• Ensure that any planned trench or excavation will be
supported by a protective system (formwork or shoring).
• Eliminate as many hazards and risks as possible (e.g. risk of a
person being buried or trapped by collapsing or dislodgement
of material)
• Erect fencing at least one metre high around the perimeter of
the excavation site.
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 10 DBE/2019
SC/NSC – Marking Guidelines
• Ensure that all excavations take place under the supervision of
a qualified person whose appointment has been confirmed in
writing.
• Carry out inspections to determine whether there are electric
cables, water pipes, gas lines or any other service pipes in the
area to be excavated, since this may affect the excavation
process.
ANY THREE OF THE ABOVE (3)
4.3.2 Factors than can cause excavations to collapse:
• Heavy rains
• Poor soil strata, structure of composition.
• Sides not dug at the correct angle.
• Incorrect use of formwork or shoring to support the walls.
• Vibration by machinery or heavy vehicles nearby.
• Human traffic close to excavations.
• Water seeping into the excavated area.
• Contact with underground service.
• Access to and exit from the excavation.
• Soil slides due to cracks or loose soil.
• Natural causes
ANY THREE OF THE ABOVE (3)
4.4
Poling boards
Folding wedges
Struts
Walling boards/Wailing boards
Shuttering correctly drawn
Proportion
ASSESSMENT CRITERIA MARK
Folding wedge 1
Walling boards/Wailing boards 1
Poling boards 2
Struts 1
Shuttering correctly drawn 1
Any ONE label 1
Proportion 1
TOTAL: 8 (8)
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 11 DBE/2019
SC/NSC – Marking Guidelines
4.5 • The shape of folding wedges simplifies the erecting and dismantling of
formwork.
• Folding wedges ease the removal/striking of formwork by knocking one
away from the other.
• Folding wedges help to keep formwork components sturdy and secured.
• Folding wedges play an important role in the levelling of formwork for
beams, floor slabs and columns.
• Folding wedges are used as pins to strengthen adjoining concrete
formwork.
• Folding wedges are used to raise or lower the formwork to the required
height.
ANY ONE OF THE ABOVE (1)
4.6
Cleats
Beam/Joist
Brace for
beams Shutterboard
Wedges Fixing plates/kickers
Bearer
Braces/Strut
ASSESSMENT CRITERIA MARK Proportion
Bearer/Joist for the soffit 1
Cleats 2
Braces for beams/struts 2
Fixing plates/Kickers 2
Wedges 2
Any ONE label 1
Proportion 1
TOTAL: 11
(11)
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 12 DBE/2019
SC/NSC – Marking Guidelines
4.7 4.7.1 Safety precautions when using a plate compactor:
• Operate with care.
• Wear gloves and boots etc. as personal protective
equipment.
• Do not place your hands or feet near the moving parts.
• Check the controls for proper response before use.
• Check for wear and damaged parts before use.
• Never use a defective/faulty machine.
• Avoid making any adjustments while the machine is vibrating.
• Use both hands to operate the machine.
• Ensure a firm and well balanced stance.
• Work from side to side to achieve the best, even surface.
• Wet the soil slightly to make it easier to compact.
ANY TWO OF THE ABOVE (2)
4.7.2 Care of a plate compactor:
• Maintain like all machinery – lubricate and adjust according to
the manufacturers, instruction.
• Clean after use.
• Store in a safe dry place/allocated place.
• Service the plate compactor regularly.
• Remove loose dust and soil after use.
• Ensure that all parts are firmly attached.
• Repair or replace damaged electric cords/parts.
ANY ONE OF THE ABOVE (1)
4.8 4.8.1 Concrete mixer (electric) (1)
4.8.2 Care of a concrete mixer:
• Only use parts as recommended by the manufacturer.
• Maintain like all machinery – lubricate and adjust according to
the manufacturers, instruction.
• Rinse with water.
• Clean after use.
• Wash of any concrete residue of the body of the mixer.
• Do not allow the water to remain inside the drum.
• Oil the inside of the drum when stored for a long time.
• Keep bearings, bushes and gears lubricated.
• Replace worn parts, especially in the drum.
• Maintain electric or internal combustion engines according to
the manufacturer’s instructions.
• Store in a dry place.
• Service the concrete mixer regularly.
• Repair or replace damaged electric cords.
ANY TWO OF THE ABOVE (2)
4.9 • Boom pump
• Line pump (2)
[40]
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 13 DBE/2019
SC/NSC – Marking Guidelines
QUESTION 5: PLASTER AND SCREED, BRICKWORK AND GRAPHICS AS
MEANS OF COMMUNICATION (SPECIFIC)
5.1 5.1.1 F (1)
5.1.2 D (1)
5.1.3 A (1)
5.1.4 B (1)
5.1.5 C (1)
5.2 Three wheelbarrows/2½ wheelbarrows (1)
5.3 • Pavements
• Patios
• Town centres/Schools/Stadiums etc.
• Road surfaces
• Driveways
• Walkways
• Any specific area suitable for paving.
ANY THREE OF THE ABOVE (3)
5.4 Advantages of using paving:
• It is more economical than concrete.
• Low initial installation cost as compared to concrete.
• Individual pavers can be lifted to access the surface underneath while
concrete must be broken up.
• Easier to repair than concrete.
• It is more user friendly than concrete.
• It has a better appearance.
• It can be laid in decorative patterns.
• Less labour intensive.
ANY ONE OF THE ABOVE (1)
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 14 DBE/2019
SC/NSC – Marking Guidelines
5.5
FIRST COURSE
SECOND COURSE
Proportion
ASSESSMENT CRITERIA MARK
One full brick on outer skin of first course 1
One full brick on inner skin of first course 1
Brick on first course to close cavity 1
One full brick on outer skin on second course 1
One full brick on inner skin on second course 1
Brick on second course to close cavity 1
Proportion 1
TOTAL: 7 (7)
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 15 DBE/2019
SC/NSC – Marking Guidelines
5.6
Wall plate Rafter
Eaves Tie beam
overhang
Hanger
Fascia board
Bearer
Fibre cement board
Quarter round mould
220 mm wall Any ONE label
SCALE: 1:10
Application of scale
USE A MASK TO MARK THIS QUESTION
ASSESSMENT CRITERIA MARK
Wall: 220 mm wide 1
Tie beam: 114 x 38 mm 1
Wall plate: 114 x 38 mm 1
Eaves overhang: 400 mm 1
Rafter: 114 x 38 mm 1
Fascia board: 228 x 28 mm 1
Bearer: 38 x 38 mm 1
Hanger: 38 x 38 mm 1
6 mm fibre-cement board on closed eaves 1
Two quarter-round mouldings below fibre-cement board 1
Any ONE label 1
Application of scale 2
TOTAL: 13
[30]
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 16 DBE/2019
SC/NSC – Marking Guidelines
QUESTION 6: REINFORCEMENT IN CONCRETE, FOUNDATIONS, CONCRETE
FLOORS AND QUANTITIES (SPECIFIC)
6.1 6.1.1 C (1)
6.1.2 D (1)
6.1.3 C (1)
6.1.4 C (1)
6.1.5 A (1)
6.2
Steel casing
Shape of the bottom/
Enlarged base
Driven in-situ pile
Any ONE label
ASSESSMENT CRITERIA MARK
Steel casing 1
Shape of the bottom 2
Any ONE label 1
TOTAL: 4
(4)
6.3 The purpose of the steel capping is to protect the top of the pile from breaking
when it is driven into the ground with the drop hammer. (1)
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 17 DBE/2019
SC/NSC – Marking Guidelines
6.4
Stirrups
Minimum concrete cover
Main bar Main bar
Any two labels
Proportion
ASSESSMENT CRITERIA MARK
L-shaped column 2
8 main bars 2
Stirrups/Binders 2
Minimum concrete cover 1
Any TWO labels 2
Proportion 1
TOTAL 10 (10)
6.5 6.5.1 A – In-situ cast concrete
B – Concrete hollow block
C – Precast ribs (3)
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 18 DBE/2019
SC/NSC – Marking Guidelines
6.5.2 The rib is used to:
• support the weight of the floor and any other loads imposed on
it.
• support the hollow blocks that form part of the construction.
• prevents the hollow blocks from moving.
ANY ONE OF THE ABOVE (1)
6.5.3 Factors to consider when planning a rib- and block floor:
• Maximum span
• Unit weight
• Nature of props
• Sound insulation
• Thickness of units
• Pre-stressed units
• Fire resistance
• Construction speed
• Reinforcement properties
• Support and formwork required
• Safety features
• Weight reduction
• Volume reduction
• Precast top layer
ANY THREE OF THE ABOVE (3)
6.5.4 Services:
• Electrical services/Conduits
• Plumbing/Hot water/Cold water/Waste pipes/
Sewerage pipes
• Communication/Telephone/Tele camera
• Security services/Alarm/Camera
ANY THREE OF THE ABOVE (3)
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 19 DBE/2019
SC/NSC – Marking Guidelines
6.6
A B C D
Concrete for foundations
Centre line
2/6 000 = 12 000 mm
2/3 000 = 6 000 mm
Total = 18 000 mm
Minus 4/600 = 2 400 mm
Total centre line = 15,6 m
1/ 15,6
0,6
0,25 2,34 m³
(10)
[40]
TOTAL: 200
Copyright reserved
Study this subject
Recommended for this subject
%20Memo%20Afr_hlayiso.com_--2a9b9e1b-37dc-48dc-9aa7-67dd5fa19a10/v1-8a03885eb99c8043e8b1/card.webp)
Memorandum
Civil Technology Grade 12 NSC June 2019 Memo (Afrikaans)
%20Memo%20Eng_hlayiso.com_--8c1355fc-f6e2-40c6-85ff-1d03eb2991ea/v1-808c163218d7215c1652/card.webp)
Memorandum
Civil Technology Grade 12 NSC June 2019 Memo (English)
%20Eng_hlayiso.com_--3f3d8211-a2ae-4ecd-89a4-623bb435b86a/v1-648207bcb15a032d7837/card.webp)
Question paper
Civil Technology Grade 12 NSC June 2019 Question Paper (Eng)
%20Afr_hlayiso.com_--87c657e9-94a5-422f-ade2-b3b897806384/v1-9312fb31c11787e210aa/card.webp)
Question paper
Civil Technology Grade 12 NSC June 2019 Question Paper (Afr)
%20Afr_hlayiso.com_--bdea7087-4612-4372-bd72-70147466f760/v1-e8611611e9b476da11a3/card.webp)
Question paper
Civil Technology Grade 12 NSC June 2019 Question Paper (Afr)
%20Memo%20Afr_hlayiso.com_--13c03cd5-cfa4-42cf-9a7c-5d7b0e1069f0/v1-b52b9528a267b4d4a925/card.webp)
Memorandum
Civil Technology Grade 12 NSC November 2019 Memo (Afrikaans)
More from Grade 12 Civil Technology
%20(English%20and%20Afrikaans)%20June%202025%20Question%20Paper--c8edd459-5237-48e0-8588-69d7ecd7f8e5/v1-be996aaed91bf782e098/card.webp)
Question paper
Civil Technology Grade 12 Gauteng June 2025 QP (Afr)
%20Afr--591d6ffd-20b1-4748-a1ba-b055be0a14c3/v1-4d98a131fd37e013458a/card.webp)
Question paper
Civil Technology Grade 12 NSC June 2025 Question Paper (Afr)
%20Afr--05a95faf-5891-4d88-9e5e-7d13c1d21648/v1-f5ca67113376f7457b83/card.webp)
Question paper
Civil Technology Grade 12 NSC November 2025 QP (Afr)

Question paper
Civil Technology Grade 12 Eastern Cape Prelim 2024 QP (Afr)

Question paper
Civil Technology Grade 12 Eastern Cape Prelim 2024 QP (Eng)
%20Afr--eefaae29-fe93-4b75-8223-87bf4f3fc14c/v1-3553acfa446acbaa2a45/card.webp)
Question paper