CIVIL TECHNOLOGY: CIVIL SERVICES
2022
MARKING GUIDELINES
MARKS: 200
These marking guidelines consist of 19 pages
Copyright reserved Please turn over
Skip to contentAll 2022 papers %20Eng_hlayiso.com_--6bfe9199-25cf-4c12-8dc6-817a01e3c184/v1-832d27151183c3221d20/card.webp)
%20Afr_hlayiso.com_--a141cdd2-0859-4ede-bb4e-499b3261db3d/v1-022b7e467b33a0558683/card.webp)
%20Afr_hlayiso.com_--b7830db2-93f0-405b-b704-e06c38ed8339/v1-cf6b1e51b55241f6f631/card.webp)
%20Eng_hlayiso.com_--97927c67-c7a8-40fb-af20-ad306ca6284c/v1-020cf7738d1b507a3ebb/card.webp)
%20Afr_hlayiso.com_--c4a7cdae-7306-4e0c-a474-e8856468ab9d/v1-d469c6c2c3eebf16cad8/card.webp)

View all%20(English%20and%20Afrikaans)%20June%202025%20Question%20Paper--c8edd459-5237-48e0-8588-69d7ecd7f8e5/v1-be996aaed91bf782e098/card.webp)
%20Afr--591d6ffd-20b1-4748-a1ba-b055be0a14c3/v1-4d98a131fd37e013458a/card.webp)
%20Afr--05a95faf-5891-4d88-9e5e-7d13c1d21648/v1-f5ca67113376f7457b83/card.webp)


%20Afr--eefaae29-fe93-4b75-8223-87bf4f3fc14c/v1-3553acfa446acbaa2a45/card.webp)
Civil Technology Grade 12 NSC June 2022 Memo (English)
Grade 12 Civil Technology memorandum from the NSC June Exam 2022 (English), 19 pages. Read online or download the free PDF.
Civil Technology · Grade 12 · NSC June Exam · 2022. Memorandum. Read online or download the PDF.
- Subject
- Civil Technology
- Grade
- Grade 12
- Document type
- Memorandum
- Year
- 2022
- Exam period
- NSC June Exam
- Curriculum
- CAPS
- Pages
- 19
- File size
- 468.8 KB
Free to read online, no sign-up needed
Loading document…
Loading document…
1 of 19
This exam
Document textSearch extracted text and jump to a page.
Downloaded from hlayiso.com
Civil Technology: Civil Services 2 DBE/2022
SC/NSC – Marking guidelines
INSTRUCTIONS FOR THE MARKERS
1. Markers should:
Familiarise themselves with the question and answer before evaluating the
responses of candidates.
Always interpret the responses of the candidates within the context of the
question.
Consider any relevant and acceptable answer during pre-marking but
should strictly adhere to the answers after finalisation of the marking
guideline.
There are TWO approaches to answering questions; these are (1) to
describe and (2) to explain.
o If a candidate is required to explain, e.g. a process in 4 steps, only the
first 4 responses should be considered.
o However, if for example a candidate is required to explain or describe
how to transfer heights from one point to another using a transparent pipe
level we need to consider that candidates may write a long description,
not necessarily well organised, as an intellectual response may do. In this
case the marker needs to evaluate the complete statement to judge if the
candidate explained the required outcome satisfactorily and allocate
marks on merit. The marker should apply his/her professional judgement
with these types of questions.
Mark what the candidate wrote and do not award marks for answers that the
marker thinks the candidate meant with what was written.
Indicate the tick or cross right at the position where the mark needs to be
awarded or where the candidate made the error.
Accept the letter corresponding with the correct answer as well as the
answer written in full in multiple-choice questions.
Accept incorrect spelling in one-word answers unless the spelling changes
the meaning of the answer.
2. For calculations:
A mark is only awarded if the correct unit is written next to the answer.
If TWO marks are awarded ONE mark is awarded for the answer and ONE
mark for the correct unit.
Where the candidate made a principle error, e.g. added instead of
multiplying, no marks will be awarded for the steps. If the answer is correct
according to what the candidate did, the mark for the answer can be
awarded for the application of skills.
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Civil Services 3 DBE/2022
SC/NSC – Marking guidelines
Where an incorrect answer could be carried over to the next step, the first
answer will be deemed incorrect. However, should the incorrect answer be
carried over correctly, the marker has to recalculate the values, using the
incorrect answer from the first calculation. If correctly used, the candidate
should receive the full marks for subsequent calculations.
Markers should consider when and where a candidate has rounded off in a
calculation, as well as the subsequent effect it has on the final answer
obtained. The calculation should therefore be awarded marks on merit.
Alternative methods of calculations must be considered, provided that the
correct answer is obtained.
3. When marking drawings:
The member for which the mark should be awarded should be drawn
correctly in the correct position to receive a mark.
A member incorrectly drawn but wrongfully repeated in another position will
be awarded the mark for the repeated incorrect member provided that the
marking guideline provide for TWO or more marks for that member (positive
marking).
Marks can only be awarded for a label if the label is correctly indicating the
correct member.
Scale drawings should always be marked using an appropriate mask.
When a candidate drew the wrong drawing, e.g.:
A horizontal section instead of a vertical section, no marks will be allocated
to the drawing as the candidate did not respond to the expected outcome.
An orthographic view instead of sectional view, no marks will be allocated to
the drawing as the candidate did not respond to the expected outcome.
An orthographic view instead of an isometric view, no marks will be
allocated to the drawing as the candidate did not respond to the expected
outcome.
If the incorrect drawing was drawn, the candidate can be awarded for only
what was asked but mark/s for the correctness of the drawing will not be
awarded e.g., if a King Post roof truss was asked in the question, and
candidate drew SA-Howe Truss
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Civil Services 4 DBE/2022
SC/NSC – Marking guidelines
QUESTION 1: OHSA, MATERIALS, TOOLS, EQUIPMENT AND JOINING
(GENERIC)
1.1 1.1.1 Thermo plastic/Thermo plastic powder coating (1)
1.1.2 Electroplating (1)
1.1.3 Curing (1)
1.1.4 Paint/Varnish (1)
1.1.5 Galvanising (1)
1.2 1.2.1 Non-skid material should be fitted to:
Prevent ladders from moving when workers are using
them
Ensure stability of the ladder when in use
ANY ONE OF THE ABOVE (1)
1.2.2 Wooden ladders are better:
To prevent electrical shock
Because it is a poor conductor of electricity
ANY ONE OF THE ABOVE (1)
1.2.3 Aluminium ladder is:
Lighter
More durable
Easier to handle
Easy to clean
Stronger
Suitable to extend to higher hights
ANY ONE OF THE ABOVE (1)
1.2.4 Wooden ladders can be treated with:
Linseed Oil/Oil
Clear varnish/Varnish
Wood preservative/Preservative
ANY TWO OF THE ABOVE (2)
1.3 The scaffold platform:
Must have guard rails
Must have toe boards
Should have sufficient room between the structure and the platform for
the worker to sit and work
Must be free of any obstruction/waste/projecting nails/equipment that can
cause injury
Must be non-slip
Should not be filled with unnecessary equipment/Overloaded
ANY TWO OF THE ABOVE (2)
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Civil Services 5 DBE/2022
SC/NSC – Marking guidelines
1.4 A safety net can be erected:
Above an entrance
At passageways
At areas where persons work while work is being performed above them
To prevent falling objects from injuring workers
ANY TWO OF THE ABOVE (2)
1.5 1.5.1 Rawlbolt/Expansion bolt/Anchor bolt (1)
1.5.2 Drill hole
Remove debris/Clean the hole
Remove the bolt and washer/insert the shield (3)
1.6 Dumpy level determines:
Levels and heights
Differences between levels and vertical heights
Levels and slopes
Distances
ANY ONE OF THE ABOVE (1)
Protect the dumpy level by:
Placing the telescope in its case directly after use
Not bumping the instrument against objects
Not dropping the instrument
Performing the collimation test regularly to ensure accuracy
Keeping it dry
ANY ONE OF THE ABOVE (1)
[20]
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Civil Services 6 DBE/2022
SC/NSC – Marking guidelines
QUESTION 2: GRAPHICS AS MEANS OF COMMUNICATION (GENERIC)
ANSWER SHEET 2
NO. QUESTIONS ANSWERS MARKS
Identify the scale that was used for the 1:500
1 2
site plan and the floor plan respectively. 1:100
Who is responsible for checking the
2 C. Lee 1
building plan?
What type of fencing does the architect
3 Precast concrete fencing 1
recommend for the new dwelling?
Name the town where the new dwelling
4 Jeffreys Bay 1
will be erected.
5 What was done as revision 1? Window in room A 1
6 Identify number 1. Municipal sewer line/Sewer line 1
Identify number 3 by giving the
7 MH 1
abbreviation.
8 Identify number 4. New dwelling 1
9 Identify number 5. Earth 1
10 Identify number 9. Distribution board/DB 1
11 Identify number 11. One-way switch-double pole 1
Sink unit-single/Single bowl
12 Identify number 12. 1
sink/Sink
Identify the number that indicates the
13 8 1
boundary line.
For pedestrians/Area dedicated for
14 Describe the purpose of number 2. 1
walking
Deduce the plot number of the existing
15 Plot 73 1
dwelling from FIGURE A.
What is omitted in Maple Street with Municipal connection/Municipal
16 1
reference to number 6? manhole
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Civil Services 7 DBE/2022
SC/NSC – Marking guidelines
What leisure feature is located on the
17 Swimming pool 1
site plan?
Draw the north symbol to show that the
18 3
driveway side is facing east.
OR
Direction
What is the purpose of the north symbol To indicate the direction/
19 1
on a house plan? elevation
20 Which feature indicates that this is a Staircase/Stairs 1
double storey building?
Dimension incorrectly indicated as
110 mm of outside wall
21 Deduce THREE faults from bedroom 2. No electrical connection from light 3
switch to the light fitting/
No wiring
Window symbol incorrect
22 Draw the symbol for a wash tub. 2
23 Draw the symbol for a bath.
2
24 Draw the symbol for a water meter. 2
Omitted dimensions/
Measurements
No levels/heights/invert
levels/corner heights
Describe TWO reasons why the local indicated
25 municipality would not approve 2
Impossible to position new
FIGURE A. dwelling
No north symbol
Incomplete sewage layout
No contour lines indicated
Calculate the length of the house. 4 000 + 5 000 + 4 000 + 4 000
Give your answer in m. 6
26
Show all calculations. + 220 +220 + 110 + 110 +110
= 17 770
= 17,77 m
TOTAL: 40
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Civil Services 8 DBE/2022
SC/NSC – Marking guidelines
QUESTION 3: CONSTRUCTION ASSOCIATED WITH CIVIL SERVICES, OHSA
AND QUANTITIES (SPECIFIC)
3.1 3.1.1 76 mm x 50 mm (1)
3.1.2 Water-logged ground (1)
3.1.3 1:90 (1)
3.1.4 Spirit level (1)
3.1.5 150 mm (1)
3.2.1 Precautions that are used to safeguard the area around an opened manhole:
The area must be cordoned off/Use a barrier net/barrier tape
Warning signs/safety signs must be posted.
Warning lights must be placed around the perimeter.
ANY ONE OF THE ABOVE (1)
3.2.2 Ways to enter a manhole:
Step irons
Safety harness and rope/rope
Ladder
ANY TWO OF THE ABOVE (2)
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Civil Services 9 DBE/2022
SC/NSC – Marking guidelines
3.3 INLET
BRICK WALL
BRANCH
PIPE
BENCHING
OUTLET
Application of
scaleMark this drawing with a mask.
ASSESSMENT CRITERIA MARK
Correctness of drawing:
Thickness of the wall 2
Ø110 mm main pipe and channel 1
Ø110 mm branch pipe and channel 1
Hatching lines of the wall 1
Direction of flow 2
Application of scale 1
TOTAL: 8
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Civil Services 10 DBE/2022
SC/NSC – Marking guidelines
3.4
A B C D
Area of walls
1/ 6,82 m Centre line of walls = 6,82 m
1,3 m 8,866 m² Height of wall for manhole = 1 300 mm (4)
Area of walls is 8,866 m²
Number of bricks
2/ 8,866 Area of walls = 8,87 m²
50 886,6 bricks Height of wall for manhole = 1 300 mm (4)
50 bricks per m² for a ½ brick wall
887 bricks are needed
OR
1/ 8,866
100 886,6 bricks 887 bricks are needed
OR
2/ 6,82 m
1,3 m
50 886,6 bricks 887 bricks are needed
OR
1/ 6,82 m
1,3 m
100 886,6 bricks 887 bricks are needed
(8)
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Civil Services 11 DBE/2022
SC/NSC – Marking guidelines
3.5
QUEEN CLOSERS
ASSESSMENT CRITERIA MARK
Correctness of drawing:
Header course 2
Queen closers 4
TOTAL: 6
[30]
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Civil Services 12 DBE/2022
SC/NSC – Marking guidelines
QUESTION 4: COLD- AND HOT-WATER SUPPLY, TOOLS, EQUIPMENT AND
MATERIALS (SPECIFIC)
4.1 4.1.1 I (1)
4.1.2 D (1)
4.1.3 J (1)
4.1.4 F (1)
4.1.5 B (1)
4.1.6 A (1)
4.1.7 H (1)
4.1.8 C (1)
4.2 4.2.1 Pressure-control valve (1)
4.2.2 Hot-water storage tank (1)
4.3 Fault when cold water flows from hot-water tap:
Power is off
Pipes were incorrectly connected
Setting of the thermostat may be too low
Thermostat is malfunctioning
Element is malfunctioning
ANY ONE OF THE ABOVE (1)
4.4 4.4.1 Step 1: Loosen the compression nut
Step 2: Use a pipe cutter to cut off the piece of pipe containing
the compression ring/ferrule
Step 3: Ream the pipe after cutting it
Step 4: Insert compression nut and new ring over pipe and fasten (4)
4.4.2 Open the water supply to check for leaks. (1)
4.5 Water-saving wash basin taps:
Electronic tap/Electric tap/Tap with sensors
Metered taps
Demand taps
ANY TWO OF THE ABOVE (2)
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Civil Services 13 DBE/2022
SC/NSC – Marking guidelines
4.6 4.6.1 Flat plate collector (1)
4.6.2 To receive direct sunlight for the entire day (1)
4.6.3 Non-return valve (1)
4.6.4 THREE disadvantages of solar heating panels:
Can be a safety hazard – the tubes can explode due to build
up of heat that cannot be pumped out in time
Heating capacity depends on the sun – in winter the system
may not function at full capacity
There is no guarantee that the water will always be hot
Leakage that results when tubes explode can damage ceilings
and furniture
Corrosion of the components
Initially requires high capital investment
If one glass tube breaks, the system must be shut down
ANY THREE OF THE ABOVE (3)
4.7 4.7.1 T-junction 90° single reducing (1)
4.7.2 uPVC /unplasticised polyvinyl chloride/PVC (1)
4.7.3 This fitting can be used:
For T-shaped connection of soil pipes and waste pipes with a
different diameter
To join 110 mm pipes in a straight line and 40/50 mm pipes at 90°
ANY ONE OF THE ABOVE (1)
4.7.4 The purpose of the inspection eye is for:
Inspection and testing purposes
Access to plumbing rods to clear out blockages
ANY ONE OF THE ABOVE (1)
4.8 4.8.1 Capstan head (1)
4.8.2 The jumper holds the washer in place. /moves up and down, and
moves washer upwards or downwards. (1)
4.8.3 If the washer is not fitted:
Water will leak from the pillar tap
The inlet water supply will not be sealed
ANY ONE OF THE ABOVE (1)
4.8.4 The pillar tap can be used for a:
Bath
Wash hand basin
Sink
Wash tub
ANY ONE OF THE ABOVE (1)
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Civil Services 14 DBE/2022
SC/NSC – Marking guidelines
4.9 4.9.1 Drain-cleaning machine/Jetting machine (1)
4.9.2 The elements that will ensure the efficient removal of blockages:
High pressure
Flow rate of the solution
Type of cleaning solution used
Heat setting of the machine
ANY TWO OF THE ABOVE (2)
4.10 It is important to clean the drain rods after use in order to remove:
Harmful bacteria
Unpleasant smells
ANY ONE OF THE ABOVE (1)
4.11 To avoid galvanic corrosion (1)
4.12 A visible sign of dezincification:
A white powder on the metal surface
Brass turns red (2)
4.13 Hydrochloric acid (1)
[40]
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Civil Services 15 DBE/2022
SC/NSC – Marking guidelines
QUESTION 5: GRAPHICS AS MEANS OF COMMUNICATION, ROOF WORK AND
STORMWATER (SPECIFIC)
5.1.1 Pre-fabricated surface channel:
It is stronger than mass concrete
Withstand the force of water flow
Handles water flow/large volumes of water flow
ANY TWO OF THE ABOVE (2)
5.1.2 Concrete shoe should have a fall/slope:
To allow water to flow away from the building. (1)
5.2
FASCIA BOARD
SQUARE GUTTER
GUTTER CLIP
OFFSET
HOLDER BAT
DOWN PIPE
ASSESSMENT CRITERIA MARK
Correctness of drawing:
Fascia board 1
Square gutter 1
Gutter clip/bracket 1
Offset 1
Down pipe 1
Holder bats 2
Rainwater shoe 1
TOTAL: 8
RAINWATER SHOE
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Civil Services 16 DBE/2022
SC/NSC – Marking guidelines
5.3
5
5
6
5
5 4
5
5
5
1
2 4
3
2 2 2
4
3
6
A
USE A MASK TO MARK DRAWING
A MAXIMUM OF 17 MARKS WILL BE AWARDED IF THE DEVELOPMENT OF PIPE A WAS
NOT CORRECTLY PROJECTED.
A MAXIMUM OF 5 MARKS WILL BE AWARDED IF PIPE A WAS NOT DEVELOPED
(1 MARK - DIVIDING CIRCLE; 2 MARKS - VERTICAL PROJECTION LINES; 2 MARKS -
DIVIDING CIRCUMFERENCE)
NO ASSESSMENT CRITERIA MARK
Correctness of drawing:
1 Dividing circle in 12 parts (auxiliary view) 1
2 Projection lines 4
3 Dividing development into 12 parts (Any
2
acceptable method)
4 Outside lines of base and sides 3
5 Outside lines of development (curve) 7
6 3 mm seam on both sides 2 (19)
TOTAL: 19 [30]
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Civil Services 17 DBE/2022
SC/NSC – Marking guidelines
QUESTION 6: SEWERAGE, SANITARY FITTINGS AND JOINING (SPECIFIC)
6.1 6.1.1 C (1)
6.1.2 B (1)
6.1.3 A (1)
6.1.4 B (1)
6.1.5 C (1)
6.2 6.2.1 A - Overflow
B - Wiped joint
C - P-trap (3)
6.2.2 P-trap:
Traps water
To make a seal to keep bad odours out (2)
6.2.3 Overflow:
Allows extra water to flow through the waste pipe
Ensures that water does not over flow the hand wash basin
ANY ONE OF THE ABOVE (1)
6.3
(2)
6.4 60 degrees /60° (1)
6.5 Flux:
To clean the material to be soldered
Promotes the flow of solder during soldering
ANY ONE OF THE ABOVE (1)
6.6 French drain:
Allows the liquid from the septic tank to seep into the ground
Grey water channelled to a French drain will seep into the ground
ANY ONE OF THE ABOVE (1)
6.7 The water in the borehole can become contaminated. (1)
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Civil Services 18 DBE/2022
SC/NSC – Marking guidelines
6.8
(10)
ASSESSMENT CRITERIA MARK
Correctness of drawing:
Concrete base 1
Outside wall 1
Partition wall 1
Opening 1
Outlet 2
Concrete slab on top 1
Manhole cover 2
Hatching (Any ONE wall) 1
TOTAL: 10
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Civil Services 19 DBE/2022
SC/NSC – Marking guidelines
6.9
RE IE
IE IE
IE IE
VP G
IE IE RE
HWB S IE
WC RE VP
SH
HWB
WC
FOR THE JUNCTIONS OF THE TWO MAIN SEWER LINES 45° LINES WILL ALSO
BE ACCEPTED
ASSESSMENT CRITERIA MARK
Correctness of drawing:
Branch pipes (ANY TWO) 2
Vent pipes 2
Gully 1
Junction of two main sewer
2
pipes (curved/45° angle)
Rodding eyes 3
Inspection eyes (ANY THREE) 3
TOTAL: 13
[40]
TOTAL:: 200
Copyright reserved
Study this subject
Recommended for this subject
%20Eng_hlayiso.com_--6bfe9199-25cf-4c12-8dc6-817a01e3c184/v1-832d27151183c3221d20/card.webp)
Question paper
Civil Technology Grade 12 NSC June 2022 Question Paper (Eng)
%20Afr_hlayiso.com_--a141cdd2-0859-4ede-bb4e-499b3261db3d/v1-022b7e467b33a0558683/card.webp)
Question paper
Civil Technology Grade 12 NSC June 2022 Question Paper (Afr)
%20Afr_hlayiso.com_--b7830db2-93f0-405b-b704-e06c38ed8339/v1-cf6b1e51b55241f6f631/card.webp)
Question paper
Civil Technology Grade 12 NSC June 2022 Question Paper (Afr)
%20Eng_hlayiso.com_--97927c67-c7a8-40fb-af20-ad306ca6284c/v1-020cf7738d1b507a3ebb/card.webp)
Question paper
Civil Technology Grade 12 NSC June 2022 Question Paper (Eng)
%20Afr_hlayiso.com_--c4a7cdae-7306-4e0c-a474-e8856468ab9d/v1-d469c6c2c3eebf16cad8/card.webp)
Question paper
Civil Technology Grade 12 NSC June 2022 Question Paper (Afr)

Memorandum
Civil Technology Grade 12 Eastern Cape Mock 2022 Memo (Afr)
More from Grade 12 Civil Technology
%20(English%20and%20Afrikaans)%20June%202025%20Question%20Paper--c8edd459-5237-48e0-8588-69d7ecd7f8e5/v1-be996aaed91bf782e098/card.webp)
Question paper
Civil Technology Grade 12 Gauteng June 2025 QP (Afr)
%20Afr--591d6ffd-20b1-4748-a1ba-b055be0a14c3/v1-4d98a131fd37e013458a/card.webp)
Question paper
Civil Technology Grade 12 NSC June 2025 Question Paper (Afr)
%20Afr--05a95faf-5891-4d88-9e5e-7d13c1d21648/v1-f5ca67113376f7457b83/card.webp)
Question paper
Civil Technology Grade 12 NSC November 2025 QP (Afr)

Question paper
Civil Technology Grade 12 Eastern Cape Prelim 2024 QP (Afr)

Question paper
Civil Technology Grade 12 Eastern Cape Prelim 2024 QP (Eng)
%20Afr--eefaae29-fe93-4b75-8223-87bf4f3fc14c/v1-3553acfa446acbaa2a45/card.webp)
Question paper