NATIONAL
SENIOR CERTIFICATE
GRADE 12
CIVIL TECHNOLOGY: CONSTRUCTION
NOVEMBER 2021
MARKING GUIDELINES
MARKS: 200
TIME: 3 hours
This question paper consists of 20 pages.
Copyright reserved Please turn over
Skip to contentAll 2021 papers %20Eng_hlayiso.com_--dcb7f976-b3d6-42a9-b2b1-44ae9b2d8e3f/v1-323df2bd04b35e089240/card.webp)
%20Eng_hlayiso.com_--f39d7571-db9f-4ded-b5e7-27008235ca8b/v1-4efe03b2e24afe8e530e/card.webp)

%20%20MG%20Afr_hlayiso.com_--42b5315c-825c-40e3-b394-85e0253fc0fb/v1-6058b260e68654519cc3/card.webp)
%20Memo%20Eng_hlayiso.com_--f06cef7f-235e-45f7-9f9b-f8e6a2b0c0ca/v1-45ae92f9d9d194afe959/card.webp)
%20Memo%20Afr_hlayiso.com_--8cffc125-69c0-44e9-b0eb-88ae7e930363/v1-fca2156d2557644edb35/card.webp)
View all%20(English%20and%20Afrikaans)%20June%202025%20Question%20Paper--c8edd459-5237-48e0-8588-69d7ecd7f8e5/v1-be996aaed91bf782e098/card.webp)
%20Afr--591d6ffd-20b1-4748-a1ba-b055be0a14c3/v1-4d98a131fd37e013458a/card.webp)
%20Afr--05a95faf-5891-4d88-9e5e-7d13c1d21648/v1-f5ca67113376f7457b83/card.webp)


%20Afr--eefaae29-fe93-4b75-8223-87bf4f3fc14c/v1-3553acfa446acbaa2a45/card.webp)
Civil Technology Grade 12 NSC November 2021 Memo (English)
Grade 12 Civil Technology memorandum from the NSC November Exam 2021 (English), 20 pages. Read online or download the free PDF.
Civil Technology · Grade 12 · NSC November Exam · 2021. Memorandum. Read online or download the PDF.
- Subject
- Civil Technology
- Grade
- Grade 12
- Document type
- Memorandum
- Year
- 2021
- Exam period
- NSC November Exam
- Curriculum
- CAPS
- Pages
- 20
- File size
- 377.1 KB
Free to read online, no sign-up needed
Loading document…
Loading document…
1 of 20
This exam
Document textSearch extracted text and jump to a page.
Downloaded from hlayiso.com
Civil Technology: Construction 2 DBE/November 2021
NSC – Marking Guidelines
INSTRUCTIONS FOR THE MARKERS
1. Markers should:
Familiarise themselves with the question and answer before evaluating the
responses of candidates.
Always interpret the responses of the candidates within the context of the
question.
Consider any relevant and acceptable answer during pre-marking, but
should strictly adhere to the answers after finalisation of the marking
guidelines.
There are two approaches to answering questions, these are (1) to describe
and (2) to explain.
If a candidate is required to explain e.g. a process in 4 steps, only the first 4
responses should be considered.
If, however a candidate is required to e.g. explain or describe how to
transfer heights from one point to another using a transparent pipe level we
need to consider that candidates may write a long description not
necessarily well organised as an intellectual response may do. In this case
the marker needs to evaluate the complete statement to judge if the
candidate explained the required outcome satisfactorily and allocate marks
on merit. The marker should apply his/her professional judgement with
these types of questions.
Mark what the candidate wrote and do not award marks for answers that the
marker thinks the candidate meant with what was written.
Indicate the tick or cross right at the position where the mark needs to be
awarded or where the candidate made the error.
Accept the letter corresponding with the correct answer as well as the
answer written in full in multiple-choice questions.
Accept incorrect spelling in one-word answers unless the spelling changes
the meaning of the answer.
2. For calculations:
A mark is only awarded if the correct unit is written next to the answer.
If TWO marks are awarded, ONE mark is awarded for the answer and ONE
mark for the correct unit.
Where the candidate made a principle error, e.g. use an incorrect method to
calculate the answer, marks will be awarded for the correct values used in
the calculation. No marks will be awarded for the answer of the incorrect
method that was followed.
Where an incorrect answer could be carried over to the next step, the first
answer will be deemed incorrect. However, should the incorrect answer be
carried over correctly, the marker has to recalculate the values, using the
incorrect answer from the first calculation. If correctly used, the candidate
should receive the full marks for subsequent calculations.
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 3 DBE/November 2021
NSC – Marking Guidelines
Markers should consider when and where a candidate has rounded off in
a calculation, as well as the subsequent effect it has on the final answer
obtained. The mark for calculations should therefore be awarded on
merit.
Alternative methods of calculations must be considered, provided that the
correct answer is obtained.
3. When marking drawings:
The member for which the mark should be awarded should be drawn
correctly in the correct position to receive a mark.
A member incorrectly drawn but wrongfully repeated in another position will
be awarded the mark for the repeated incorrect member, provided that the
marking guidelines provide for TWO or more marks for that member
(positive marking).
Marks can only be awarded for a label if the label is correctly indicating the
correct member.
Scale drawings should always be marked using an appropriate mask.
When a candidate drew the wrong drawing, e.g.:
A horizontal sectional view instead of a vertical sectional view, no marks will
be allocated to the drawing as the candidate did not respond to the
expected outcome.
An orthographic view instead of a sectional view, no marks will be allocated
to the drawing as the candidate did not respond to the expected outcome.
An orthographic view instead of an isometric view, no marks will be
allocated to the drawing as the candidate did not respond to the expected
outcome.
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 4 DBE/November 2021
NSC – Marking Guidelines
QUESTION 1: OHSA, SAFETY, MATERIALS, TOOLS, EQUIPMENT AND JOINING
(GENERIC)
1.1 1.1.1 Galvanising (1)
1.1.2 Paint (1)
1.1.3 Electroplating (1)
1.1.4 Curing (1)
1.1.5 Powder coating (1)
1.2 1.2.1 Scaffolding must be:
Properly propped against displacement.
Able to carry the mass or load.
Securely and effectively braced to ensure stability/Stable.
Secured at suitable vertical and horizontal distances to the
structure.
Free of defects/sharp edges.
Constructed so that it has a safety factor of at least two.
Levelled.
Inspected regularly.
ANY TWO OF THE ABOVE (2)
1.2.2 Toe-board/Kickboard (1)
1.2.3 When working on scaffolding:
Wear a safety harness/safety equipment/PPE.
Do not throw any materials from a scaffold.
Do not throw any tools from a scaffold.
Never jump from a scaffold.
Do not overload a scaffold.
Remove or cover sharp edges or corners of a scaffold.
Scaffold should be kept free of waste/obstructions.
ANY TWO OF THE ABOVE (2)
1.3 To remove waste:
Use a chute/pipe chute
Use a conveyor belt/ramp
Use a bucket with a rope/pulley system
Use a forklift/mobi-lift/TLB/crane with a bucket/builders’ hoist
ANY TWO OF THE ABOVE (2)
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 5 DBE/November 2021
NSC – Marking Guidelines
1.4 Safe use of trestle scaffolds:
Scaffolds should be soundly constructed of solid material.
All precautionary measures should be taken to prevent the unexpected
spreading of its supporting legs when in use.
Trestles should not exceed a height of 3 m.
Trestles scaffolds should not consist of more than two tiers.
ANY TWO OF THE ABOVE (2)
1.5 Hoisting materials and equipment in a builder’s hoist:
Materials and equipment should be firmly stacked.
Materials and equipment should be correctly stacked.
Materials and equipment should be properly secured.
Gates must be shut when in use.
Overhead protection must be provided.
Qualified person must operate the builders' hoist.
Emergency brake mechanism must be installed.
Not exceed the working capacity of the hoist/Not overload the hoist.
Safety measures must be displayed inside the cage.
ANY ONE OF THE ABOVE (1)
1.6 Drill a hole through the two metal plates.
Insert the bolt into the drilled holes.
Fasten the two plates with a bolt and nut. (3)
1.7 Used to locate:
Materials behind walls.
Materials in ceilings.
Materials under floors.
Steel bars
Copper pipes
Ferrous metals
Non-ferrous metals
Electrical wiring
Services
Wood/Wooden/metal studs behind walls.
The distance to and from an object.
ANY ONE OF THE ABOVE (1)
Care
Protect the multi-detector against:
Moisture/Water/Corrosion
Direct sunlight/heat
Extreme temperature changes
Bumps/Falling
Damage caused by the release of acid from the battery
ANY ONE OF THE ABOVE (1)
[20]
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 6 DBE/November 2021
NSC – Marking Guidelines
QUESTION 2: GRAPHICS AS MEANS OF COMMUNICATION (GENERIC)
ANSWER SHEET 2
NO. QUESTIONS ANSWERS MARKS
Identify the scale you will use for the 1 : 200
1. site plan and the floor plan 2
1 : 100
respectively.
Who is responsible to verify all
2. dimensions and levels on site before Contractors 1
commencing work?
What type of fencing does the
3. architect recommend for the new Palisade fencing/Palisade 1
dwelling?
State the colour that you would use to
4. indicate the new dwelling on the site Red 1
plan.
5. Identify number 1. Boundary line 1
6. Identify number 2. Building line 1
7. Identify number 3. Electricity meter/Watt meter 1
8. Identify number 4. Entrance/Exit/Driveway 1
9. Identify number 5. Water storage tank/Water tank 1
10. Identify number 6. Pavement/Walkway/Sidewalk 1
North point/North symbol/North
11. Identify number 7. 1
sign/North direction
Municipal connection/Municipal
12. Identify number 8. 1
manhole/Main sewer connection
13. Identify number 9. Manhole 1
Determine the distance between
14. number 2 and the new dwelling on the 4 000 mm/4 m 1
eastern side of the building.
Deduce the plot number of the new
15. Plot 31 1
dwelling from FIGURE A.
Which elevation is the closest to
16. South elevation/South 1
Loerie Street?
What is the plot number of the
17. property on the western side of the Plot 35 1
dwelling?
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 7 DBE/November 2021
NSC – Marking Guidelines
No window in the dining room
110 mm of outside wall is incorrect/
Internal wall thickness
Light switch in bathroom is in wrong
place
220 mm inside wall in room A is
incorrect/External wall thickness
No step at the kitchen door
No door in dining room/living
room/door opening
No arch indicated at dining 2
18. Deduce TWO faults on FIGURE B.
room/living room
Floor covering not indicated in
rooms
No socket outlets/plugs in rooms
No hatching of floor plan
No ceiling light in passage
No dashed/hidden detail lines
shown between living/dining/kitchen
to indicate the arch
ANY TWO OF THE ABOVE
Which natural feature is indicated on Trees/Shrubs 1
19.
the site plan?
What is wrong with the electrical The light switch is fitted on the
20. installation in the bathroom in inside of the bathroom/Switch is 1
FIGURE B? incorrectly placed.
21. Identify number 10. Ramp 1
Sink–double bowl/
22. Identify number 11. 1
Double bowl sink/Double sink
23. Identify number 12. Two-way switch 1
One-way switch single-pole/One-
24. Identify number 13. 1
way switch/Single-pole switch
25. Draw the symbol of a socket outlet. 2
26. Draw the symbol for a shower.
2
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 8 DBE/November 2021
NSC – Marking Guidelines
2
Draw the symbol for a wall-mounted
27.
light.
Dressing room/Walk-in closet
En-suite/Bathroom
Gym/Gymnasium
Study/Office
28. Recommend TWO uses for ROOM A. 2
Store/Rest/Baby/Play/Games/
Guest/TV room
Laundry
ANY TWO OF THE ABOVE
24 500 – 5 000 – 9 000 –
3 000 – 5 000
Calculate the omitted horizontal = 2 500 mm
29. dimension on the site plan. Give your ANY OTHER CALCULATION 6
answer in mm. Show ALL calculations. METHOD TO ARRIVE AT THE
ANSWER
TOTAL: 40
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 9 DBE/November 2021
NSC – Marking Guidelines
QUESTION 3: ROOFS, STAIRCASES AND JOINING (SPECIFIC)
3.1 Balustrade patterns:
Mopani pattern
Transvalia pattern
Ultra-modern pattern
Space-age pattern
Straight
Spiralled
Curved
ANY ONE OF THE ABOVE (1)
3.2 Timber handrails can be mounted to walls by:
Screwing the handrails onto the walls.
Using brackets.
ANY ONE OF THE ABOVE (1)
3.3 850 mm (1)
3.4 To cover the floor joist and trimmers exposed by the stairwell openings. (1)
3.5 14 days (1)
3.6 Nuts (1)
3.7 Types of cast-in anchors:
Hex-head bolt with washer
L-bolt
J-bolt
Welded headed stud
ANY ONE OF THE ABOVE (1)
3.8 Wall plate (1)
3.9 Tie beam (1)
3.10 White/Yellow/Blue/Silver/Black/Green (1)
3.11 Lean-to roof (1)
3.12 Couple roof (1)
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 10 DBE/November 2021
NSC – Marking Guidelines
3.13
KING POST 114 mm x 38 mm
RAFTER 114 mm x 38 mm
QUEEN POST 114 mm x 38 mm
WALL PLATE 114 mm x 38 mm
30º
TIE BEAM 114 mm x 38 mm
STRUT 114 mm x 38 mm
SPAN
WALL 220 mm
ASSESSMENT CRITERIA MARK
Correctness of drawing:
Rafters 2
King post 1
Tie beam 1
Queen post 1
Struts 2
Wall plate 1
Any ONE label with dimensions 2
TOTAL: 10 (10)
Copyright reserved Please turn over
Civil Technology: Construction
Downloaded from hlayiso.com 11 DBE/November 2021
NSC – Marking Guidelines
3.14
RIDGE BEAM
RAFTER
WALL PLATE
TIE BEAM
ASSESSMENT CRITERIA MARK
Correctness of drawing:
Tie beam 1 SCALE 1:10 USE A MASK TO MARK THE DRAWING
Rafters 2
Ridge beam 1
Wall plates 2
Application of scale:
One or Two incorrect =2 2
Three or Four incorrect = 1
More than Five incorrect = 0
TOTAL: 8
(8)
[30]
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 12 DBE/November 2021
NSC – Marking Guidelines
QUESTION 4: EXCAVATIONS, FORMWORK, TOOLS, EQUIPMENT AND
MATERIALS (SPECIFIC)
4.1 4.1.1 D (1)
4.1.2 H (1)
4.1.3 E (1)
4.1.4 I (1)
4.1.5 J (1)
4.1.6 G (1)
4.1.7 A (1)
4.1.8 F (1)
4.2 Consequences of neglecting to determine the location of services:
This may affect/hamper/delay the excavation/construction process.
It may have unplanned cost implications.
Damage to services may occur.
Injuries may occur.
ANY ONE OF THE ABOVE (1)
4.3 Safety precautions at night:
The excavation must be well-lit at night.
Red or orange warning lights should be visible.
Fence off the area.
Post visible warning signs.
Wear appropriate visible PPE.
ANY THREE OF THE ABOVE (3)
4.4 4.4.1 Members omitted:
Walling boards
Folding wedges/Wedge
Struts
ANY TWO OF THE ABOVE
Consequence:
The excavation could collapse. (3)
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 13 DBE/November 2021
NSC – Marking Guidelines
4.4.2
ASSESSMENT CRITERIA MARK
Correctness of drawing:
Poling boards 1
Walling boards 2
Folding wedges 1
Strut 1
TOTAL: 5 (5)
4.5 4.5.1 The removal of the formwork. (1)
4.5.2 Applied to the interior surfaces of the formwork for quick release
of the formwork.
Ensures that formwork does not stick to the concrete.
ANY ONE OF THE ABOVE (1)
4.5.3 The bottom board that supports freshly poured concrete. (1)
4.6 4.6.1 Formwork for a concrete beam with floor slab. (1)
4.6.2 A – Cleats
B – Fixing plate/Kicker plates
C – Shutter board/Soffit board sides
D – Bearer/Head tree
E - Brace/Strut (5)
4.7 4.7.1 Personal protective equipment:
Gloves
Safety boots/Gumboots/Boots
Overall
Safety glasses
Earmuffs/Earplugs
Dust mask
Hard hat/Safety helmet
ANY THREE OF THE ABOVE (3)
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 14 DBE/November 2021
NSC – Marking Guidelines
4.7.2 Methods to prevent rusting:
Remove water from the drum.
Oil the inside of the drum.
Store concrete mixer with the opening of drum facing
downwards.
ANY ONE OF THE ABOVE (1)
4.8 Strength - Cube test
Workability - Slump test (2)
4.9 24 hours/7 days/14 days/28 days (1)
4.10 Non–Ferrous metals
Ferrous metals
Alloys
ANY TWO OF THE ABOVE (2)
4.11 Reasons for cladding a wall:
To protect walls against weather elements like rainwater and wind.
For aesthetical purposes.
For functional purposes.
For insulation purposes.
To cover defects/imperfections.
ANY TWO OF THE ABOVE (2)
[40]
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 15 DBE/November 2021
NSC – Marking Guidelines
QUESTION 5: PLASTER AND SCREED, BRICKWORK AND GRAPHICS AS
MEANS OF COMMUNICATION (SPECIFIC)
5.1 5.1.1 C - Wet/Prepare/Clean the wall
B - Apply the plaster
D - Level/Cut the plaster/Removing access plaster (Sawing
movement)
A - Smoothen/Float/Finish the surface (8)
5.1.2 Purpose of wetting the wall:
If not done, the plaster will not stick properly to the wall.
If not done, the plaster will dry out too quickly.
If not done, the strength of the plaster will be affected
ANY ONE OF THE ABOVE (1)
5.1.3 Builder’s lime/Lime (1)
5.2 5.2.1 Jointing:
River sand/Plaster sand is used as grouting between paving
blocks/bricks.
Mixture of plaster sand and cement is used as grouting
between paving blocks/bricks.
ANY ONE OF THE ABOVE (1)
5.2.2 Bedding sand:
The final layer upon which the paving units are laid. (1)
5.2.3 Walkways:
Paving is subjected to only pedestrian use. (1)
5.3 5.3.1
OR
BASKET-WEAVE PAVING PATTERN
ASSESSMENT CRITERIA MARK Creating
Vertical first and second full bricks 2 pattern
Horizontal first and second full bricks 2
Creating pattern 1
TOTAL: 5 (5)
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 16 DBE/November 2021
NSC – Marking Guidelines
5.3.2
OR
OR
HERRINGBONE PAVING PATTERN
Creating pattern
ASSESSMENT CRITERIA MARK
Half brick 1
Full bricks to create pattern 3
Creating pattern 1
TOTAL: 5
(5)
5.4 5.4.1 To hold the two skins (walls) of the cavity wall together. (1)
5.4.2 Weep holes must be positioned:
Above the horizontal damp-proof course of the external wall.
On the same level as the concrete floor.
Above the lintel on top of the window/door opening.
Minimum 150 mm above NGL.
ANY ONE OF THE ABOVE (1)
5.4.3 Water that penetrates the outside wall can drain out through
the weep hole.
For ventilation purposes.
ANY ONE OF THE ABOVE (1)
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 17 DBE/November 2021
NSC – Marking Guidelines
5.5
FACE BRICK
. ..................
PLASTER HINGE
DOOR FRAME IN FACE BRICK WALL
ASSESSMENT CRITERIA MARK
Face brick wall
1
(Correct hatching)
Plaster 1
Steel door frame 2
TOTAL: 4 (4)
[30]
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 18 DBE/November 2021
NSC – Marking Guidelines
QUESTION 6: REINFORCEMENT IN CONCRETE, FOUNDATIONS, CONCRETE
FLOORS AND QUANTITIES (SPECIFIC)
6.1 6.1.1 C (1)
6.1.2 C (1)
6.1.3 A (1)
6.1.4 D (1)
6.1.5 A (1)
6.2 1 500 mm (1)
6.3 90 mm (1)
6.4 On the load bearing wall. (1)
6.5
HOLLOW-CORE
STEEL MAT/REINFORCING
CONCRETE
MESH/REINFORCING BARS
BLOCKS
WALL
PRE-STRESSED REINFORCING IN
CONCRETE RIBS RIBS
ASSESSMENT CRITERIA MARK
Correctness of drawing:
Ribs with reinforcing 4
Reinforcing mesh 2
Concrete floor 2
Any ONE Label 1
TOTAL: 9 (9)
6.6 6.6.1 Main bar (1)
6.6.2 Anchor bar/Pressure bar/Compression bar (1)
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 19 DBE/November 2021
NSC – Marking Guidelines
MINIMUM CONCRETE COVER DEPTH
6.6.3 STIRRUPS
SHEAR BAR
MAIN BAR ANCHOR BAR
FIGURE 6.6
ASSESSMENT CRITERIA MARK
Correctness of drawing:
Binders close spacing 1
Binders bigger spacing 1
Shear bar 3
Minimum concrete cover depth 1
TOTAL: 6 (6)
6.7 Minimum cover depth in reinforced concrete is important:
To protect the steel against corrosion.
To ensure adequate bonding between the steel and the concrete.
To ensure adequate protection of steel in the event of a fire.
ANY TWO OF THE ABOVE (2)
6.8 6.8.1 40 mm (1)
6.8.2 30 mm (1)
6.8.3 60 mm (1)
Copyright reserved Please turn over
Downloaded from hlayiso.com
Civil Technology: Construction 20 DBE/November 2021
NSC – Marking Guidelines
6.9.1 A B C D
Total length of damp-proof course needed
for outer walls:
2/ 8,5 17 m Length of the long wall = 8 500 mm
2/ 4 8m Length of the short wall = 4 000 mm
25 m
OR
2/8 500 = 17 000
2/4 000 = 8 000
25 000
25 m damp-proof course needed (6)
6.9.2 Number of bricks for inner wall
1/ 2,78 Length of inner wall: 3 000 – 220 = 2780 mm
2,6 Height of inner wall: 2 600 mm
50 Use 50 bricks/m² for half brick wall
361,4/ 362 Bricks needed for the inner wall.
362
bricks (4)
[40]
TOTAL: 200
Copyright reserved
Study this subject
Recommended for this subject
%20Eng_hlayiso.com_--dcb7f976-b3d6-42a9-b2b1-44ae9b2d8e3f/v1-323df2bd04b35e089240/card.webp)
Question paper
Civil Technology Grade 12 NSC November 2021 QP (Eng)
%20Eng_hlayiso.com_--f39d7571-db9f-4ded-b5e7-27008235ca8b/v1-4efe03b2e24afe8e530e/card.webp)
Question paper
Civil Technology Grade 12 NSC November 2021 QP (Eng)

Memorandum
Civil Technology Grade 12 Eastern Cape Mock 2021 Memo (Eng)
%20%20MG%20Afr_hlayiso.com_--42b5315c-825c-40e3-b394-85e0253fc0fb/v1-6058b260e68654519cc3/card.webp)
Memorandum
Civil Technology Grade 12 NSC November 2023 Memo (Afrikaans)
%20Memo%20Eng_hlayiso.com_--f06cef7f-235e-45f7-9f9b-f8e6a2b0c0ca/v1-45ae92f9d9d194afe959/card.webp)
Memorandum
Civil Technology Grade 12 NSC November 2020 Memo (English)
%20Memo%20Afr_hlayiso.com_--8cffc125-69c0-44e9-b0eb-88ae7e930363/v1-fca2156d2557644edb35/card.webp)
Memorandum
Civil Technology Grade 12 NSC November 2020 Memo (Afrikaans)
More from Grade 12 Civil Technology
%20(English%20and%20Afrikaans)%20June%202025%20Question%20Paper--c8edd459-5237-48e0-8588-69d7ecd7f8e5/v1-be996aaed91bf782e098/card.webp)
Question paper
Civil Technology Grade 12 Gauteng June 2025 QP (Afr)
%20Afr--591d6ffd-20b1-4748-a1ba-b055be0a14c3/v1-4d98a131fd37e013458a/card.webp)
Question paper
Civil Technology Grade 12 NSC June 2025 Question Paper (Afr)
%20Afr--05a95faf-5891-4d88-9e5e-7d13c1d21648/v1-f5ca67113376f7457b83/card.webp)
Question paper
Civil Technology Grade 12 NSC November 2025 QP (Afr)

Question paper
Civil Technology Grade 12 Eastern Cape Prelim 2024 QP (Afr)

Question paper
Civil Technology Grade 12 Eastern Cape Prelim 2024 QP (Eng)
%20Afr--eefaae29-fe93-4b75-8223-87bf4f3fc14c/v1-3553acfa446acbaa2a45/card.webp)
Question paper