NATIONAL
SENIOR CERTIFICATE
GRADE 12
CIVIL TECHNOLOGY: CIVIL SERVICES
NOVEMBER 2025
MARKING GUIDELINES
MARKS: 200
These marking guidelines consist of 18 pages.
Copyright reserved Please turn over
Skip to contentAll 2025 papers %20Afr--05a95faf-5891-4d88-9e5e-7d13c1d21648/v1-f5ca67113376f7457b83/card.webp)
%20%20MG%20Afr_hlayiso.com_--42b5315c-825c-40e3-b394-85e0253fc0fb/v1-6058b260e68654519cc3/card.webp)
%20Memo%20Eng_hlayiso.com_--f06cef7f-235e-45f7-9f9b-f8e6a2b0c0ca/v1-45ae92f9d9d194afe959/card.webp)
%20Memo%20Afr_hlayiso.com_--8cffc125-69c0-44e9-b0eb-88ae7e930363/v1-fca2156d2557644edb35/card.webp)
%20Memo%20Afr_hlayiso.com_--13c03cd5-cfa4-42cf-9a7c-5d7b0e1069f0/v1-b52b9528a267b4d4a925/card.webp)
%20Memo%20Eng_hlayiso.com_--53bd979c-a0bb-411f-960b-1f8755cd4874/v1-6e2a9c2564a39a8c61d5/card.webp)
View all%20(English%20and%20Afrikaans)%20June%202025%20Question%20Paper--c8edd459-5237-48e0-8588-69d7ecd7f8e5/v1-be996aaed91bf782e098/card.webp)
%20Afr--591d6ffd-20b1-4748-a1ba-b055be0a14c3/v1-4d98a131fd37e013458a/card.webp)


%20Afr--eefaae29-fe93-4b75-8223-87bf4f3fc14c/v1-3553acfa446acbaa2a45/card.webp)
%20Afr--307147a5-3280-4a11-a82e-cf3e33388eb0/v1-e53e38093df191bfe243/card.webp)
Civil Technology Grade 12 NSC November 2025 Memo (English)
Grade 12 Civil Technology memorandum from the NSC November Exam 2025 (English), 18 pages. Read online or download the free PDF.
Civil Technology · Grade 12 · NSC November Exam · 2025. Memorandum, 18 pages. Read online or download the PDF.
- Subject
- Civil Technology
- Grade
- Grade 12
- Document type
- Memorandum
- Year
- 2025
- Exam period
- NSC November Exam
- Curriculum
- CAPS
- Pages
- 18
- File size
- 560.3 KB
Free to read online, no sign-up needed
Loading document…
Loading document…
1 of 18
This exam
Document textSearch extracted text and jump to a page.
Civil Technology: Civil Services 2 DBE/November 2025
NSC – Marking Guidelines
INSTRUCTIONS FOR MARKERS
1. Markers should:
• Familiarise themselves with the question and answer before evaluating the
responses of candidates.
• Always interpret the responses of the candidates within the context of the
question.
• Consider any relevant and acceptable answer during pre-marking but
should strictly adhere to the answers after finalisation of the marking
guideline.
• There are TWO approaches to answering describe and explain type of
questions.
1. If a candidate is required to explain e.g., a process in a prescribed
number of steps (e.g. 3 steps), only the first required number of
responses should be considered.
2. However, if for example candidate is required to explain or describe a
process, we need to consider that candidates may write a long
description, not necessarily well organised. In this case the marker
needs to evaluate the complete statement to judge if the candidate
explained the required outcome satisfactorily and allocate marks on
merit.
Answering short questions.
1. Bullet Form Answers: When a candidate provides their answers in
bulleted points, each bullet should be treated as a single answer.
Award 1 mark for each complete bulleted response.
2. Paragraph Form Answers: When a candidate provides answers in
paragraph form, the response should be evaluated based on the
accuracy and completeness of each fact presented. Award marks for
each distinct fact or point made, ensuring that each fact is correctly
articulated.
• Mark what the candidate wrote and do not interpret or predict responses.
• Indicate the tick or cross right at the position where the mark needs to be
awarded or where the candidate made the error.
• Accept the letter corresponding with the correct answer as well as the
answer written in full in multiple-choice questions or similar questions.
• Accept incorrect spelling in answers unless the spelling changes the
meaning of the answer.
• If a learner writes two or more answers separated by a slash (/) mark only
the first response, unless the additional answer/s are different names for the
same item, e.g. Yale lock/Night latch. In this case, the answer for the
response should be awarded and the slash (/) should NOT be considered as
an additional answer.
Copyright reserved Please turn over
Civil Technology: Civil Services 3 DBE/November 2025
NSC – Marking Guidelines
2. For calculations:
• A mark is only awarded if the correct unit is written next to the answer. If the
question states that the answer must be in a specific unit, a mark will be
awarded even if the answer is indicated without the unit.
• Marks will only be allocated for the correct values if the candidates add
instead of multiply. NO marks will be awarded for the calculations and the
answer.
• Where an incorrect answer is correctly carried over, the marker must
recalculate the values, using the incorrect answer from the first calculation.
If correctly used, the candidate should receive the full marks for subsequent
calculations.
• Alternative methods of calculations must be considered, provided that the
correct answer is obtained.
• For the calculation of quantities marks will be awarded for the correct use of
the dimension paper.
3. When marking drawings:
• The member for which the mark should be awarded should be drawn
correctly in the correct position to receive a mark.
• A member incorrectly drawn but wrongfully repeated in another position will
be awarded the mark for the repeated incorrect member provided that the
marking guideline provides for TWO or more marks for that member
(positive marking).
• Marks can only be awarded for a label if the label is correctly indicating the
correct member. Do not consider labels for members of which the labels
were provided on the answer sheet.
• Scale drawings should always be marked using an appropriate mask.
• If the incorrect/wrong drawing was drawn, the candidate can be awarded for
only what was provided for on the marking guideline.
• If a line diagram or an orthographic view instead of a pictorial drawing
(isometric/oblique/perspective) is drawn, the first assessment criteria for
each member will be marked wrong, but marks will be awarded for the
subsequent members if TWO or more marks are awarded for the same
member.
• If candidates draw/give more information than what is required, mark strictly
according to the assessment criteria. However, if the additional information
alters or contradicts the correct response, the answer should be marked as
incorrect.
4. Incorrect numbering of questions:
• If a candidate numbered incorrectly, but the answer is in the correct position
according to the sequence of the questions in the question paper, circle the
incorrect numbering and mark the response.
• If questions were answered randomly not following the same sequence as
in the question paper and the learner numbered incorrectly, the response
should NOT be marked.
5. Duplication of responses and questions answered in the correct place:
• If a question is answered twice, mark the first response.
• If a question should be answered on an answer sheet and the candidate
answered it on both the answer sheet and in the answer book, mark the
response on the answer sheet and cancel the response in the answer book.
Copyright reserved Please turn over
Civil Technology: Civil Services 4 DBE/November 2025
NSC – Marking Guidelines
• If the question was answered in the answer book instead of on the answer
sheet, mark the response in the answer book according to the assessment
criteria on the marking guideline.
QUESTION 1: OHSA, MATERIALS, TOOLS, EQUIPMENT AND JOINING
(GENERIC)
1.1 1.1.1 38 mm ✓ (1)
1.1.2 150 mm ✓ (1)
1.1.3 320 kg per m² ✓ (1)
1.1.4 two ✓ (1)
1.1.5 two ✓ (1)
1.1.6 overhead ✓ (1)
1.1.7 two thirds ✓ (1)
1.1.8 unauthorised persons ✓ (1)
1.1.9 760 x 560 mm ✓ (1)
1.1.10 health and safety ✓ (1)
1.2 C✓ (1)
1.3 Bolts are purchased according to:
• Length of the shank ✓
• Diameter ✓
• Type of thread
• Head size
• Type of head
• Strength
• Material
ANY TWO OF THE ABOVE (2)
1.4 1.4.1 Process of powder coating:
Applying a plastic finish/coating in powder form, ✓ by using a spray
gun ✓ (2)
Copyright reserved Please turn over
Civil Technology: Civil Services 5 DBE/November 2025
NSC – Marking Guidelines
1.4.2 Advantages of applying powder coating to a metal:
• Strengthen the metal ✓
• Provides stability
• Environmentally friendly
• Thicker coat can be applied
• More durable
• Available in a variety of colours, textures and gloss levels
• Withstand higher levels of heat
• Thermoset powder coatings have a beautiful appearance
• It is cheaper than other methods
• Resists corrosion
ANY ONE OF THE ABOVE (1)
1.5 Do not use the following to clean a multi detector:
• Cleaning agents ✓
• Solvents/Chemicals
• Moist cloth
ANY ONE OF THE ABOVE (1)
1.6 Two materials that can be detected:
• Steel ✓
• Copper ✓
• Brass
• Wiring/AC
ANY TWO OF THE ABOVE (2)
1.7 Plumb bob ✓ (1)
[20]
Copyright reserved Please turn over
Civil Technology: Civil Services 6 DBE/November 2025
NSC – Marking Guidelines
QUESTION 2: GRAPHICS AS MEANS OF COMMUNICATION (GENERIC)
NO. QUESTIONS ANSWERS MARKS
What elevation is indicated by
1. West elevation/West/W ✓ 1
FIGURE A?
Deduce, from the notes column, what
2. Hipped roof ✓ 1
type of roof is indicated by number 1.
What energy-generating components
3. are installed on the roof, as indicated Solar Panels ✓ 1
by number 2?
4. Identify number 3. Fascia board ✓ 1
5. Identify number 4. Window sill/Sill ✓ 1
What material is recommended to be
6. Stainless steel ✓ 1
used to manufacture number 5?
7. Identify number 6. NGL/Natural ground level ✓ 1
Write down the abbreviation for
8. FFL ✓ 1
number 7.
Identify the end shape used to
9. Round/Square/Rectangular ✓ 1
manufacture number 8.
How many built-in cupboards are
10. One/1 ✓ 1
there in the building?
Socket outlet/Switch socket
What electrical installation has been outlet/Lights/Electrical wiring/
11. 1
omitted in the building? Switch/Distribution board/
Inverter ✓
What type of material can be used to Timber/Fibre cement/
12. manufacture the fascia board in uPVC/Aluminium/Stainless 1
FIGURE A? steel/Galvanised sheets ✓
How should the opening direction of
13. the sliding door be indicated on the By means of an arrow ✓ 1
floor plan?
Ceramic/PVC/Timber/Steel/
Stainless steel/Porcelain/Clay/
Name ONE material that can be used
14. Plastic/Fibre glass/Glass/Concrete/ 1
to manufacture number 9.
Stone/Marble/Terrazzo/
Cast iron/Pressed steel/Brass ✓
Copyright reserved Please turn over
Civil Technology: Civil Services 7 DBE/November 2025
NSC – Marking Guidelines
Deduce, from the notes column, what
15. Lintels ✓ 1
must be installed above every window.
How many external doors are visible
16. Two/2 ✓ 1
on the southern side of the building?
How many water closets are installed
17. Four/4 ✓ 1
in the building?
18. Identify number 10. One-way switch double pole ✓ 1
Deduce the thickness of the internal
19. 110 mm/110 ✓ 1
walls from FIGURE B.
State the reference code of the
20. QP 5 - 2025 ✓ 1
proposed building.
How many 1 200 x 600 mm windows
21. Five/5 ✓ 1
are there in the building?
Deduce, from the notes column, the
22. dimensions of the aluminium side 600 ✓ x 2 000 mm ✓ 2
panel with windows.
✓
23. Draw the symbol for a grease trap. ✓ 3
✓✓ ✓
Draw the symbol for undisturbed ✓
24. earth. 3
✓ ✓
What sanitary fitting is installed in the
25. Sink unit – double/Double sink ✓ 1
scullery?
5✓x4✓
Calculate the area of the scullery to be = 20 ✓ m²
covered with floor tiles.
26. The sink unit must be installed on top OR 3
of the tiles.
Give your answer in m². = 5 000 mm x 4 000 mm
= 20 m²
220 ✓ + 5 000 ✓ + 110 ✓ +
5 000 ✓ + 220 ✓
Calculate the total length of the wall = 10 550 ✓ mm
on the northern side of the building. = 10,55 ✓m
27. 7
Show ALL calculations. The length
must be indicated in metres. OR
0,22 + 5 + 0,11 + 5 + 0,22= 10,55 m
TOTAL: 40
Copyright reserved Please turn over
Civil Technology: Civil Services 8 DBE/November 2025
NSC – Marking Guidelines
QUESTION 3: CONSTRUCTION ASSOCIATED WITH CIVIL SERVICES, OHSA
AND QUANTITIES (SPECIFIC)
3.1 3.1.1 Faults in the manhole installation:
• The walls are not on the foundation ✓
• The benching is not at a slope ✓
• The channel is too shallow ✓
• The channel needs to be half-round
• No manhole cover/Cover lid omitted
• No manhole cover frame
ANY THREE OF THE ABOVE (3)
3.1.2 Medical/First aid ✓ (1)
3.1.3 Breathing apparatus/Respirator/Gas mask ✓ (1)
3.1.4 A dust mask that covers the mouth and nose does not filter the air
to protect a person from harmful gasses ✓/It will not provide
sufficient protection where harmful gasses are present.
ANY ONE OF THE ABOVE (1)
3.1.5 Stretcher bond/English bond ✓ (1)
3.1.6 Concrete ring manhole/Plastic/Fibre glass ✓ (1)
Copyright reserved Please turn over
Civil Technology: Civil Services 9 DBE/November 2025
NSC – Marking Guidelines
3.2
POLING BOARD 4 POLING BOARD
3
1
2 2
3
OR
STRUT/BRACE 4 STRUT/BRACE
OR
NO. ASSESSMENT CRITERIA MARK
1 Excavation/Trench 1
2 Poling boards 2
3 Struts/Braces 2
5 Any TWO labels 2
TOTAL: 7 (7)
Copyright reserved Please turn over
Civil Technology: Civil Services 10 DBE/November 2025
NSC – Marking Guidelines
3.3 3.3.1 Volume of a cubic water storage tank:
Volume = l x b x h
Volume = s3
= 2,65 ✓ m x 2,65 ✓ m x 2,65 ✓ m
= 18,61 ✓ m3
OR
2 650 x 2 650 x 2 650
= 18 609 625 000
= 18,61 m3 (4)
3.3.2 Volume of water in tank = 18,61 ✓ x 1 000 ✓
= 18 610 ℓ ✓ (3)
3.4
1
A 1
3
2
2
3
2
1
NO. ASSESSMENT CRITERIA MARK
1 Horizontal bricks 3
2 Vertical bricks 3
3 Projection lines 2
TOTAL: 8 (8)
[30]
Copyright reserved Please turn over
Civil Technology: Civil Services 11 DBE/November 2025
NSC – Marking Guidelines
QUESTION 4: COLD AND HOT-WATER SUPPLY, TOOLS, EQUIPMENT AND
MATERIALS (SPECIFIC)
4.1 4.1.1 E✓
4.1.2 B✓
4.1.3 D✓
4.1.4 C✓
4.1.5 G✓
4.1.6 I✓
4.1.7 K✓
4.1.8 H✓ (8)
4.2 4.2.1 A – Pressure-reducing valve/Pressure control valve ✓
B – Vacuum breaker ✓
C – TP safety valve/Outlet/Pipe ✓
D – Drain cock ✓ (4)
4.2.2 When hot water heats up it rise to the top of the cylinder. ✓ (1)
4.2.3 300 mm ✓ (1)
4.2.4 If a leakage occurs water may damage the ceiling and anything
below the ceiling. ✓ (1)
4.2.5 Ø 50 mm ✓ (1)
4.2.6 A – Reduces and controls the incoming water pressure to the
geyser. ✓
D – Is used to drain the geyser when repairs need to be done or
when the geyser needs to be replaced. ✓ (2)
✓
4.2.7 ✓
WH
(2)
4.3 Uses of water-pressure testing pump:
• To test the water pressure in pipes ✓ (1)
Centrifugal pump:
• To pump water from one place to another ✓
• To increase the water pressure
ANY ONE OF THE ABOVE (1)
Copyright reserved Please turn over
Civil Technology: Civil Services 12 DBE/November 2025
NSC – Marking Guidelines
4.4 4.4.1 ✓ ✓
(2)
4.4.2 ✓
✓
(2)
4.4.3
H ✓
✓
C (2)
4.5 4.5.1 If water is not hot enough it may be:
• that the thermostat is set too low ✓
• that the thermostat and element is malfunctioning
• that there is an insufficient electricity supply
ANY ONE OF THE ABOVE (1)
4.5.2 Preventing the shortage of hot water:
• Set thermostat to 65°✓/The required temperature
• Ensure that the thermostat and element is in good working
Condition ✓
• Provide additional insulation to geyser and pipes
• Ensure that the electricity supply to the geyser is switched
on for a sufficient period of time
ANY TWO OF THE ABOVE (2)
4.6 4.6.1 Waste bend plain 90° ✓ (1)
4.6.2 The function of the fitting is:
• To connect two pipes of the same diameter at an angle of 90°✓
• To connect wastewater pipes at an angle
• To change the direction of wastewater
ANY ONE OF THE ABOVE (1)
4.6.3 The ends of the fitting are larger:
• To ensure that the pipe fits in the fitting ✓
• For joining purposes
ANY ONE OF THE ABOVE (1)
4.6.4 Ø 40/50 mm ✓ (1)
4.7 The electrolytic reaction can be prevented:
• By using the same type of metal throughout the whole system ✓
• By using a non-metal coupling when copper pipe and galvanized pipes are
connected ✓ (2)
Copyright reserved Please turn over
Civil Technology: Civil Services 13 DBE/November 2025
NSC – Marking Guidelines
4.8.1 Water saving valves in terms of use:
A – This tap can be opened halfway to save water ✓
OR
A strainer in the outlet of this tap can mix air with the water to
reduce water usage (1)
B – This tap allows water to flow as long as the button is pressed ✓
OR
Water flows for a pre-set period when the button is pressed
and saves water (1)
4.8.2 Electronic tap with sensor/Sensor tap/Electronic tap ✓ (1)
[40]
Copyright reserved Please turn over
Civil Technology: Civil Services 14 DBE/November 2025
NSC – Marking Guidelines
QUESTION 5: GRAPHICS AS MEANS OF COMMUNICATION, ROOF WORK AND
STORM WATER (SPECIFIC)
5.1 5.1.1 D✓ (1)
5.1.2 A✓ (1)
5.1.3 D✓ (1)
5.1.4 D✓ (1)
5.1.5 D✓ (1)
5.2 5.2.1 A – Gutter corner ✓
B – Union clip ✓ (2)
5.2.2 A – At a 90º corner where two gutters meet ✓
B – To join two gutters along its length ✓ (2)
5.3 Consequences of poorly designed storm water systems:
• Might lead to learners losing their lives ✓
• Structural damage to the building ✓
• Moisture penetrating the walls
• Structural integrity can be compromised
• Moisture on inside of wall
ANY TWO OF THE ABOVE (2)
Copyright reserved Please turn over
Civil Technology: Civil Services 15 DBE/November 2025
NSC – Marking Guidelines
5.4
1 6
4
4
2 4
3 4
4
4
5
6 5 5 5
5 5
B
A
2
3
USE A MASK TO MARK THIS QUESTION
NO. ASSESSMENT CRITERIA MARK
1 Division of circle into 12 parts 1
2 Projection lines from circle 2
3 Projection lines from shoe 2
4 Development of base of shoe 6
5 Development of top of shoe 6
6 3 mm seams 2
TOTAL: 19
(19)
[30]
Copyright reserved Please turn over
Civil Technology: Civil Services 16 DBE/November 2025
NSC – Marking Guidelines
QUESTION 6: SEWERAGE, SANITARY FITTINGS AND JOINING (SPECIFIC)
6.1 6.1.1 sludge ✓ (1)
6.1.2 compost ✓ (1)
6.1.3 Bio-reactor ✓ (1)
6.1.4 biomass ✓ (1)
6.1.5 chlorine ✓ (1)
6.2 6.2.1 90º elbow ✓ (1)
6.2.2 The rubber washer will prevent leaking/Seal the outlet ✓ (1)
6.2.3 PVC bend with inspection eye/PVC access bend ✓ (1)
6.2.4 • PVC weld ✓
• Solvent weld
• PVC glue/adhesive
ANY ONE OF THE ABOVE (1)
6.2.5 Prevents odours/sewer gas ✓from entering the dwelling. ✓ (2)
6.2.6 Gully ✓ (1)
6.3 6.3.1 Manhole/Rodding eye ✓ (1)
6.3.2 One/1 ✓ (1)
6.4 Materials that can be used for drainpipes:
• uPVC/Unplasticised Polyvinyl chloride ✓
• PVC/Polyvinyl chloride ✓
• Cast iron
• Fibre cement
• Clay or earthenware
• Concrete
ANY TWO OF THE ABOVE (2)
Copyright reserved Please turn over
Civil Technology: Civil Services 17 DBE/November 2025
NSC – Marking Guidelines
6.5 Properties of solder:
• Silver-coloured ✓
• Heavy ✓
• The higher the tin content, the higher the melting point
• The higher the lead content, the lower the melting point
• Can creep/Capillary action in liquid form
• Elastic modulus
• Elongation is possible
• Ductile
• High strain rate
• Malleable
ANY TWO OF THE ABOVE (2)
6.6 If the head is too cold, the solder will not melt sufficiently to obtain proper
adhesion. ✓
If the head is too hot, the tin in the solder will burn, leaving it useless. ✓ (2)
6.7 6.7.1 Vacuum tank/Conservancy tank ✓ (1)
6.7.2 A – Vent pipe/Vent valve ✓
B – Manhole cover/Lid ✓ (2)
6.7.3 Draw-off valve ✓ (1)
Copyright reserved Please turn over
Civil Technology: Civil Services 18 DBE/November 2025
NSC – Marking Guidelines
6.8
MUNICIPAL CONNECTION
MH
IE
6 2
G
1 IE
2
1 IE
VP 5 VP
5 2
3 2 4
RE IE 7 7 IE
1 1
RE 3
NO. ASSESSMENT CRITERIA MARK
1 Inspection eyes (Any FOUR) 4
2 Branch pipes (Any FOUR) 4
3 Rodding eyes 2
4 Junction of the main sewer pipes 1
5 Vent pipe (Correctly placed) 2
6 Gully 1
7 Main sewer line 2
TOTAL: 16 [40]
TOTAL: 200
Copyright reserved
Study this subject
Recommended for this subject
%20Afr--05a95faf-5891-4d88-9e5e-7d13c1d21648/v1-f5ca67113376f7457b83/card.webp)
Question paper
Civil Technology Grade 12 NSC November 2025 QP (Afr)
%20%20MG%20Afr_hlayiso.com_--42b5315c-825c-40e3-b394-85e0253fc0fb/v1-6058b260e68654519cc3/card.webp)
Memorandum
Civil Technology Grade 12 NSC November 2023 Memo (Afrikaans)
%20Memo%20Eng_hlayiso.com_--f06cef7f-235e-45f7-9f9b-f8e6a2b0c0ca/v1-45ae92f9d9d194afe959/card.webp)
Memorandum
Civil Technology Grade 12 NSC November 2020 Memo (English)
%20Memo%20Afr_hlayiso.com_--8cffc125-69c0-44e9-b0eb-88ae7e930363/v1-fca2156d2557644edb35/card.webp)
Memorandum
Civil Technology Grade 12 NSC November 2020 Memo (Afrikaans)
%20Memo%20Afr_hlayiso.com_--13c03cd5-cfa4-42cf-9a7c-5d7b0e1069f0/v1-b52b9528a267b4d4a925/card.webp)
Memorandum
Civil Technology Grade 12 NSC November 2019 Memo (Afrikaans)
%20Memo%20Eng_hlayiso.com_--53bd979c-a0bb-411f-960b-1f8755cd4874/v1-6e2a9c2564a39a8c61d5/card.webp)
Memorandum
Civil Technology Grade 12 NSC November 2019 Memo (English)
More from Grade 12 Civil Technology
%20(English%20and%20Afrikaans)%20June%202025%20Question%20Paper--c8edd459-5237-48e0-8588-69d7ecd7f8e5/v1-be996aaed91bf782e098/card.webp)
Question paper
Civil Technology Grade 12 Gauteng June 2025 QP (Afr)
%20Afr--591d6ffd-20b1-4748-a1ba-b055be0a14c3/v1-4d98a131fd37e013458a/card.webp)
Question paper
Civil Technology Grade 12 NSC June 2025 Question Paper (Afr)

Question paper
Civil Technology Grade 12 Eastern Cape Prelim 2024 QP (Afr)

Question paper
Civil Technology Grade 12 Eastern Cape Prelim 2024 QP (Eng)
%20Afr--eefaae29-fe93-4b75-8223-87bf4f3fc14c/v1-3553acfa446acbaa2a45/card.webp)
Question paper
Civil Technology Grade 12 November 2024 NSC QP (Afr)
%20Afr--307147a5-3280-4a11-a82e-cf3e33388eb0/v1-e53e38093df191bfe243/card.webp)
Question paper